July 2019
- Report Date
- July 2019
(Draft) SMI Programme Report compiled by Colin Watt (IS Apps Programme Manager) for Programme Owners Neil Bruce and Alex Carter
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Projects in Progress:
SMI019 UniDesk for UHI
SMI020 UniDesk for RCA
SMI022 Journyx Service
SMI023 UniDesk for Malta
SMI024 UniDesk Procurement
Overall Programme RAG: AMBER
Forward Look and RAG
Resource Summary
Section Two: Projects Not Started
Project Info | Project Manager's Commentary |
AP89-028 UniDesk Upgrade | Project withdrawn |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||||||||||||
UniDesk for UHI Category: Discretionary Milestones Agreed at WIS 03-May-2019:
RAG Status: BLUE |
Report by Richard Bailey for Jul 2019 Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||||||||||
Journyx Service Category: Compliance Milestones
Completion of milestones delayed and now unrealistic. RAG Status: RED |
Report by Colin Watt for Jul 2019 Achievements in Last Period
Issues
Next Steps
Project RAG status is RED. Currently no funding agreed for project days beyond 31/07/19. Without a decision the formal project planning cannot be progressed, and due to the delays a migration cannot now be scheduled until the UoE Change Freeze is completed. Impact is that if there is no funding to complete the work in 19/20, the project will close and the current local platform will remain in place for a further year until it reaches EOL. |
||||||||||||||||||||||||
UniDesk for Malta Category: Discretionary Milestones Agreed at WIS 19-Jul-2019:
RAG Status: GREEN
|
Report by Richard Bailey for Jul 2019 Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||||||||||
UniDesk Procurement Category: Discretionary Milestones
RAG Status: AMBER |
Report by Colin Watt for Jul 2019 Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
UniDesk Annual Upgrade |
Closure Approved 28/09/18 |
UniDesk for RCA |
Closure Approved 22/03/19 |
UniDesk for UHI |
Closure Approved 05/07/19 |
Attachment | Size |
---|---|
![]() | 133.1 KB |
![]() | 107.77 KB |
![]() | 171.57 KB |
![]() | 144.04 KB |
![]() | 129.44 KB |
![]() | 112.47 KB |
![]() | 143.07 KB |
![]() | 126.12 KB |
![]() | 131.05 KB |
![]() | 121.75 KB |
![]() | 151.17 KB |
![]() | 134.29 KB |
![]() | 148.51 KB |
![]() | 154.88 KB |
![]() | 148.52 KB |
![]() | 148.52 KB |
![]() | 188.91 KB |
![]() | 148.31 KB |
![]() | 150.3 KB |
![]() | 169.68 KB |
![]() | 162.35 KB |
![]() | 160.64 KB |