Section One: Programme Commentary, RAG and Resources Update
Projects in Progress:
SMI019 UniDesk for UHI
SMI020 UniDesk for RCA
Overall Programme RAG: GREEN
Forward Look and RAG

Resource Summary

Section Two: Projects Not Started
| Project Info | Project Manager's Commentary |
| AP89-028 UniDesk Upgrade | Currently scheduled to start Q1 2019; status not confirmed. |
| AP89-029 JournyX Service | Currently scheduled to start Q1 2019; status not confirmed. |
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | ||||||||||||||||||||||||||||||
|
UniDesk for UHI Category: Discretionary Milestones: Agreed at WIS 17-Dec-2018:
RAG Status: GREEN
|
Report by Richard Bailey for January 2019 Achievements this Period
Issues
Next Steps
|
||||||||||||||||||||||||||||||
|
UniDesk for RCA Category: Discretionary Milestones: Agreed at WIS 25-Jan-2019:
RAG Status: GREEN
|
Report by Richard Bailey for January 2019 Achievements this Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
|
UniDesk Annual Upgrade |
Closure Approved 28/09/18 |
| Attachment | Size |
|---|---|
| 133.1 KB | |
| 107.77 KB | |
| 171.57 KB | |
| 144.04 KB | |
| 129.44 KB | |
| 112.47 KB | |
| 143.07 KB | |
| 126.12 KB | |
| 131.05 KB | |
| 121.75 KB |