December 2018
- Report Date
- December 2018
(Draft) SMI Programme Report compiled by Colin Watt (IS Apps Programme Manager) for Programme Owners Neil Bruce and Alex Carter
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Projects in Progress:
SMI019 UniDesk for UHI
SMI020 UniDesk for RCA
Overall Programme RAG: GREEN
Forward Look and RAG
Resource Summary
Section Two: Projects Not Started
Project Info | Project Manager's Commentary |
AP89-028 UniDesk Upgrade | Currently scheduled to start Q1 2019 |
AP89-029 JournyX Service | Currently scheduled to start Q1 2019 |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||||||||||||||||||||
UniDesk for UHI Category: Discretionary Milestones: Agreed at WIS 17-Dec-2018:
RAG Status: GREEN
|
Report by Richard Bailey for December 2018 Achievements this Period
Issues
Next Steps
|
||||||||||||||||||||||||||||||||
UniDesk for RCA Category: Discretionary Milestones: Agreed at WIS 21-Sep-2018:
RAG Status: AMBER |
Report by Richard Bailey for December 2018 Achievements this Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
UniDesk Annual Upgrade |
Closure Approved 28/09/18 |
Attachment | Size |
---|---|
![]() | 133.1 KB |
![]() | 107.77 KB |
![]() | 171.57 KB |
![]() | 144.04 KB |
![]() | 129.44 KB |
![]() | 112.47 KB |
![]() | 143.07 KB |
![]() | 126.12 KB |