November 2018
- Report Date
- November 2018
(Draft) SMI Programme Report compiled by Colin Watt (IS Apps Programme Manager) for Programme Owners Neil Bruce and Alex Carter
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Projects in Progress:
SMI019 UniDesk for UHI
SMI020 UniDesk for RCA
Overall Programme RAG: GREEN
Forward Look and RAG
Resource Summary
Section Two: Projects Not Started
Project Info | Project Manager's Commentary |
AP89-028 UniDesk Upgrade | Currently scheduled to start Q1 2019 |
AP89-029 JournyX Service | Currently scheduled to start Q1 2019 |
Section Three: Projects in Progress
Project Info | Project Managers Commentary |
UniDesk for UHI Category: Discretionary Milestones:
RAG Status: |
Report by Richard Bailey for November 2018 Achievements this Period
Issues Next Steps |
UniDesk for RCA Category: Discretionary Milestones
RAG Status: |
Report by Richard Bailey for November 2018 Achievements this Period
Issues Next Steps |
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
UniDesk Annual Upgrade |
Closure Approved 28/09/18 |