(Draft) SMI Programme Report compiled by Colin Watt (IS Apps Programme Manager) for Programme Owners Neil  Bruce and Alex Carter

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update

Projects in Progress:

SMI018 UniDesk Annual Upgrade

SMI019 UniDesk for UHI

SMI020 UniDesk for RCA

 

Overall Programme RAG: AMBER

 

Forward Look and RAG

 

Resource Summary

 

Section Two: Projects Not Started

 

Project Info Project Manager's Commentary
AP89-028 UniDesk Upgrade  
AP89-029 JournyX Service  

 

Section Three: Projects in Progress

 

Project Info Project Managers Commentary

SMI018 (AP67-042)

UniDesk Annual Upgrade

Category: Compliance

Milestones

Closure 31-Aug-2018

RAG Status:  AMBER

 

 

Report by Chris Konczak for August 2018

Achievements in Last Period

  • JIRAs for QuickCalls deployed to LIVE
  • Transfer agreed with Production and Service Management for remaining JIRAs to move to support and the API project
  • Closure report re-submitted for approval

 

Issues

  • JIRA 99 has just been re-opened as Durham have reported a bug (04/09/18). Durham have a different way of logging "Priority" and as such they are the only institution with this specific error.  Error fixed and deployed to TEST (05/09/18) tested and passed. As it's a live issue, it's been agreed that this can be deployed during the change freeze. This will be deployed on either 06/09/18 or 10/09/18. This has impacted the closure of the project and the closure date will have to be revised, PICCL to be raised at WIS on 07/10/18 requesting closure for 20/10/18.

 

Next Steps​

  • Fix QuickCalls bug for Durham
  • Project Closure agreed

SMI019

UniDesk for UHI

Category: Discretionary

Milestones

TBC

Target Datesort descending Title
14-Sep-2018           

End of Planning

 

RAG Status:  GREEN

Report by Richard Bailey for August 2018

Achievements in Last Period

  • Project Initiated
  • Stakeholders and Project Team identified / agreed

Issues

  • None

Next Steps​

  • Complete Project Brief / Planning / Estimate
  • Agree and set milestones
  • Agree and secure resource bookings
  • Define Project in ASTA
  • Start to coordinate works

 

SMI020

UniDesk for RCA

Category: Discretionary

Milestones

TBC

Target Datesort descending Title
14-Sep-2018           

End of Planning

 

RAG Status:  GREEN  

Report by Richard Bailey for August 2018

Achievements in Last Period

  • Project Initiated
  • Stakeholders and Project Team identified / agreed  

Issues

  • None

Next Steps​

  • Complete Project Brief / Planning / Estimate
  • Agree and set milestones
  • Agree and secure resource bookings
  • Define Project in ASTA
  • Start to coordinate works

 

Section Four: Closed or Withdrawn Projects

 