May 2018

Report Date
May 2018

SMI Programme Report compiled by Colin Watt (IS Apps Programme Manager) for Programme Owners Neil  Bruce and Alex Carter

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update

 

 

Overall Programme RAG: AMBER

 

Forward Look and RAG

 

 

Resource Summary

 

Section Two: Projects Not Started

No Projects outstanding.

 

Section Three: Projects in Progress

 

Project Info Project Managers Commentary

SMI018 (AP67-042)

UniDesk Annual Upgrade

Category: Compliance

Milestones

Milestones

05-Jun-2018 Reporting Server Deploy to LIVE
08-Jun-2018 Deployment Sign Off
22-Jun-2018 Closure

 

 

 

RAG Status: 

RED

 

Report by Chris Konczak for May 2018

Achievements in Last Period

  • Ulster LIVE authentication completed
  • Ulster LIVE deployment (to v5.7) completed
  • Abertay deployment completed
  • Reporting server TEST build completed
  • Ulster LIVE deployment (to v7) completed
  • Stirling deployment completed
  • Napier deployment completed

Issues

  • Budget to be resolved with portfolio owner as we are still unclear where the extra days are coming from. Meeting set up on 06/06/18 with project manager, programme manager, programme owner and portfolio owner to discuss.

Next Steps​

  • Decommissioning old servers
  • Reporting server deployment to LIVE
  • Project closure

Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

SMI013 (AP56-009)

UniDesk Annual Upgrade

 

Closure Approved 03/11/17
AttachmentSize
Image icon smi-flook-may2018.jpg85.35 KB
Image icon smi-resource-may2018.jpg89.17 KB