Report for November 2019
- Report Date
- November 2019
Report compiled by Karen Stirling, RIS Programme Manager for Dominic Tate (Programme Owner), Damon Querry, Lorna Thomson, Liz Welch, Dax Carroll, Jacq McMahon, Susan Cooper, Paul Reay
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
The Programme Commentary
Overall progress within the Programme is as follows :
- RIS005 - Closure in progress
- RIS007 - Pure Live environment has been successfully upgraded to 5.15.2-1 and also upgrade Java Open JDK, project closure now completed
- RIS008 - Finalising Options paper approval and prep for project closure
- RIS011 - Deployed Pure v5.16.1 into development environment - project only showing as RED due to project manager availability due to contract due to end in January. This is a wider project manager resource risk across Applications
- RIS012 - Milestone changes due to industrial action
For REF2021 interest projects have been added and a communication has been issued out to all project managers for any new projects to be included.
Please find link to REF2021 Portfolio page. Some interest projects have been added to the list and a further communication to project managers to highlight importance of REF2021 and to confirm if any other projects should be recorded.
Overall Programme RAG: GREEN
Forward Look and RAG
Resource Position
Section Two: Projects Not Started for 19/20
Project Info | Project Manager's Commentary |
Support for REF | Not started |
RIS014 REF2021 Data Requirements Implementation | Due to start 10th January 2020, PM has been assigned |
Section Three: Projects in Progress
Project Info | Project Manager's Commentary | ||||||||||||||||||||||||||
RIS005 Ethics Tool Procurement Discretionary / Sponsor Funded Milestones:
RAG Status : GREEN
|
Report by Karen Stirling for November 2019 Achievements in Last Period
Issues
Next Steps
The project status is GREEN as new closure date agreed
|
||||||||||||||||||||||||||
RIS007 PURE Upgrades v5.13 to 5.15 Compliance / Core Funded Milestones:
RAG Status: GREEN
|
Report by Karen Stirling for November 2019 Achievements in Last Period
Issues
Next Steps
The project status is GREEN
|
||||||||||||||||||||||||||
RIS008 REF2021 Data Requirements Analysis Discretionary / Sponsor Funded Milestones:
RAG Status : GREEN |
Report by Tim Gray for November 2019 Achievements in Last Period
Issues
Next Steps
The project status is GREEN
|
||||||||||||||||||||||||||
RIS011 Pure Upgrade v5.16 to v5.18 Compliance / Core Funded Milestones:
RAG Status: RED |
Report by Kevin Hone for November 2019 Achievements in Last Period
Issues
Next Steps
The project status is RED |
||||||||||||||||||||||||||
RIS012 Worktribe Upgrade v3.1 Compliance / Core Funded Milestones:
RAG Status: AMBER |
Report by David Watters for November 2019 Achievements in Last Period
Issues
Next steps
The project status is AMBER because the milestones have been modified. |
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
|
|
|
|
|
|
|
|
|
|
|
|
|