Report for November 2019

Report Date
November 2019

Report compiled by Karen Stirling, RIS Programme Manager for Dominic Tate  (Programme Owner), Damon Querry, Lorna Thomson, Liz Welch, Dax Carroll, Jacq McMahon, Susan Cooper, Paul Reay

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section One: Programme Commentary, RAG and Resources Update

 

The Programme Commentary

Overall progress within the Programme is as follows :

  • RIS005 - Closure in progress
  • RIS007 - Pure Live environment has been successfully upgraded to 5.15.2-1 and also upgrade Java Open JDK, project closure now completed
  • RIS008 - Finalising Options paper approval and prep for project closure
  • RIS011 - Deployed Pure v5.16.1 into development environment - project only showing as RED due to project manager availability due to contract due to end in January. This is a wider project manager resource risk across Applications 
  • RIS012 - Milestone changes due to industrial action

 

For REF2021 interest projects have been added and a communication has been issued out to all project managers for any new projects to be included.

 

Please find link to REF2021 Portfolio page. Some interest projects have been added to the list and a further communication to project managers to highlight importance of REF2021 and to confirm if any other projects should be recorded.

 

Overall Programme RAG: GREEN

 

Forward Look and RAG

 

 

Resource Position

 

 

 

 Section Two: Projects Not Started for 19/20

Project Info Project Manager's Commentary
Support for REF Not started
RIS014 REF2021 Data Requirements Implementation Due to start 10th January 2020, PM has been assigned

 

Section Three: Projects in Progress

 

Project Info Project Manager's Commentary

 

RIS005  Ethics Tool Procurement

Discretionary / Sponsor Funded

Milestones:

Milestone Due Date
Project Closure Complete 13/12/2019

RAG Status : GREEN

 

 

 

Report by Karen Stirling for November 2019

Achievements in Last Period 

  • Limited activity due to discussion around when SSO required
  • Revised closure milestone agreed 

Issues

  • Business team and supplier not ready for SSO set up and not likely required until into 2020 therefore project sponsor has asked for this to be completed out with project
  • Discuss support to complete activity with Production and Development teams and to be completed under UNIDESK call therefore gaining agreement to project closure in December 

Next Steps

  • Completion report review with Procurement and gain sign off from key stakeholders

 

The project status is GREEN as new closure date agreed

 

RIS007 PURE Upgrades v5.13 to 5.15

Compliance / Core Funded

Milestones:

Closure 10-Dec-2019

 

RAG Status: GREEN

 

 

Report by Karen Stirling for November 2019

Achievements in Last Period 

  • UAT Completed and signed off
  • Prep for Cloud Portal - meeting with Elsevier held on 6th November 
  • Acceptance review and sign off approved
  • Deployment to Live completed successfully on 19th November - Pure live environment upgraded to 5.15.2-1 and Java Open JDK completed
  • No impact on application since deployment
  • Deployment Review sign off completed and approved

Issues

  • Review budget on closure and return days back to RIS Programme 
  • Agreement for Cloud Portal work to move to RIS011

Next Steps 

  • Complete Closure report and gain approval from project team
  • Submit for closure to be completed

 

The project status is GREEN 

 

RIS008 REF2021 Data Requirements Analysis

Discretionary / Sponsor Funded

Milestones:

Milestone Date
Delivery Business requirements and Options Paper (II) 13-Dec-2019
Closure Review 19-Oct-2019

 

RAG Status : GREEN

Report by Tim Gray for November 2019

Achievements in Last Period

  • Feedback from REF team received and partially incorporated into Options Paper
  • The final two milestones have again been replanned

Issues

  • There has been a slight delay in finalising the Options Paper due to the Data Analyst and paper author being on planned annual leave. 

Next Steps 

  • Complete feedback and circulate Options Paper for sign off to Core and REF Teams
  • Draft closure report
  • Closure project

The project status is GREEN

 

RIS011 Pure Upgrade v5.16 to v5.18

Compliance / Core Funded

Milestones:

Milestone

Due Date

Upgraded DEV to Pure v5.16.1       

22-Nov-2019

Upgraded DEV to Pure v5.16.2

20-Dec-2019

Upgraded TEST to Pure v5.16

28-Jan-2020

Upgraded LIVE to Pure v5.16

31-Jan-2020

Upgraded DEV to Pure v5.17

13-Mar-2020

Upgraded TEST to Pure v5.17

17-Apr-2020

Upgraded LIVE to Pure v5.17

22-Apr-2020

Upgrade DEV to Pure v5.18

10-Jul-2020

Upgraded TEST to Pure v5.18

14-Aug-2020

Upgraded LIVE to Pure v5.18

19-Aug-2020

DSOR Sign-off

20-Aug-2020

Project Closure

02-Sep-2020

 

RAG Status: 

RED

 

Report by Kevin Hone for November 2019

Achievements in Last Period

  • v5.16.1 was deployed to the development environment.
  • Initial meeting attended to consider future use of a cloud portal.

Issues

  • No forward plan for replacement of Project Manager due to leave in January (reason for reporting a RAG status of RED).

Next Steps

  • Preparations for deployment of v5.16.2 to the development environment with work to be undertaken by alternative resource.
  • Further discussions to be had with the 3rd party Elsevier on the use of a cloud portal.

The project status is RED

RIS012 Worktribe Upgrade v3.1

Compliance / Core Funded

Milestones:

Accept Integration & Acceptance complete 19-Nov-2019
Deliver Delivery of upgrade 10-Dec-2019
Deliver Delivery sign-off (Upgrade) 16-Dec-2019
Deliver Delivery of SSO changes 17-Dec-2019
Deliver Delivery sign-off (SSO) 09-Jan-2020
Close Project closure 17-Jan-2020

RAG Status:  

AMBER

Report by David Watters for November 2019

Achievements in Last Period

  • Integration testing sucessfully completed
  • User acceptance testing signed off

Issues

  • Milestones replanned because of industrial action

Next steps

  • Carry out LIVE upgrade with business partners and vendor
  • Implement SSO changes

 

The project status is AMBER because the milestones have been modified.

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary
                                                                                                

                                                                                                                      

 

 

 

 

 

 

 

 

 

 

 

 

AttachmentSize
Image icon ris_resource_nov_19.jpg82.13 KB
Image icon ris_forward_look_nov_19.jpg81.58 KB
Programme Status
RAG Status
Overall
GREEN
Has formal escalation taken place?
Yes
Escalated to
Portfolio Manager and Programme Owner
RAG Commentary
All projects underway as per forward look and budget within programme is as expected at this stage in the financial year. Some concerns have been raised over PM resourcing due to contractor resource due to leave in January 2020 and limited PM resource available to cover. This is being taken forward at Project Services level.

Documentation

Not available.