Report for October 2019
- Report Date
- October 2019
Report compiled by Karen Stirling, RIS Programme Manager for Dominic Tate (Programme Owner), Damon Querry, Lorna Thomson, Liz Welch, Dax Carroll, Jacq McMahon, Susan Cooper, Paul Reay
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
The Programme Commentary
Overall progress within the Programme is as follows :
- RIS005 - SSO set up delayed awaiting date confirmation from business team
- RIS007 - UAT completed and preparations for deployment on 19th November
- RIS008 - Delay in receiving feedback from Core Systems on the Options Paper. While this has now been resolved, the project manager would like this noted in the October report.
- RIS011 - Project brief has been issued out for review and comment ready for submission for approval, now approved
- RIS012 - Test environment has been upgraded but milestone extended to cover further testing and SSO setup changes
University Industrial Strike action may impact delivery date for RIS012 revised deployment date being reviewed, this risk is to be added to relevant projects such as RIS011 however dev and test environments should not be impacted as per communications with Matt Beilby - Go CAB.
For REF2021 interest projects have been added and a communication has been issued out to all project manager for any new projects to be included.
Please find link to REF2021 Portfolio page. Some interest projects have been added to the list and a further communication to project managers to highlight importance of REF2021 and to confirm if any other projects should be recorded.
Overall Programme RAG: GREEN
Forward Look and RAG
Resource Position
Section Two: Projects Not Started for 19/20
Project Info | Project Manager's Commentary |
Support for REF | Not started |
REF2021 Data Requirements Implementation | Not started, expected start date mid November 2019 |
Section Three: Projects in Progress
Project Info | Project Manager's Commentary | ||||||||||||||||||||||||||||
RIS005 Ethics Tool Procurement Discretionary / Sponsor Funded Milestones:
RAG Status : AMBER
|
Report by Karen Stirling for October 2019 Achievements in Last Period
Issues
Next Steps
The project status is AMBER as SSO set up date to be confirmed by business team and amend closure date to end of November
|
||||||||||||||||||||||||||||
RIS007 PURE Upgrades v5.13 to 5.15 Compliance / Core Funded Milestones:
RAG Status: GREEN
|
Report by Karen Stirling for October 2019 Achievements in Last Period
Issues
Next Steps
The project status is GREEN
|
||||||||||||||||||||||||||||
RIS008 REF2021 Data Requirements Analysis Discretionary / Sponsor Funded Milestones:
RAG Status : AMBER |
Report by Tim Gray for October 2019 Achievements in Last Period
Issues
Next Steps
The project status is AMBER to highlight the delay in receiving feedback from Core Systems on the Options Paper. While this has now been resolved, the project manager would like this noted in the October report.
|
||||||||||||||||||||||||||||
RIS011 Pure Upgrade v5.16 to v5.18 Compliance / Core Funded Milestones:
RAG Status: GREEN |
Report by Kevin Hone for October 2019 Achievements in Last Period:
Issues:
Next Steps:
The project status is GREEN
|
||||||||||||||||||||||||||||
RIS012 Worktribe Upgrade v3.1 Compliance / Core Funded Milestones:
RAG Status: AMBER
|
Report by David Watters for October 2019 Achievements in Last Period
Issues
Next steps
The project status is AMBER because the milestones have been modified. |
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
|
|
|
|
|
|
|
|
|
|
|
|
|
Attachment | Size |
---|---|
![]() | 75.46 KB |
![]() | 87.99 KB |