Report for October 2019

Report Date
October 2019

Report compiled by Karen Stirling, RIS Programme Manager for Dominic Tate  (Programme Owner), Damon Querry, Lorna Thomson, Liz Welch, Dax Carroll, Jacq McMahon, Susan Cooper, Paul Reay

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section One: Programme Commentary, RAG and Resources Update

 

The Programme Commentary

Overall progress within the Programme is as follows :

  • RIS005 - SSO set up delayed awaiting date confirmation from business team
  • RIS007 - UAT completed and preparations for deployment on 19th November 
  • RIS008 - Delay in receiving feedback from Core Systems on the Options Paper. While this has now been resolved, the project manager would like this noted in the October report.
  • RIS011 - Project brief has been issued out for review and comment ready for submission for approval, now approved
  • RIS012 - Test environment has been upgraded but milestone extended to cover further testing and SSO setup changes

 

University Industrial Strike action may impact delivery date for RIS012 revised deployment date being reviewed, this risk is to be added to relevant projects such as RIS011 however dev and test environments should not be impacted as per communications with Matt Beilby - Go CAB.

 

For REF2021 interest projects have been added and a communication has been issued out to all project manager for any new projects to be included.

 

Please find link to REF2021 Portfolio page. Some interest projects have been added to the list and a further communication to project managers to highlight importance of REF2021 and to confirm if any other projects should be recorded.

 

Overall Programme RAG: GREEN

 

Forward Look and RAG

 

 

Resource Position

 

 

 

 Section Two: Projects Not Started for 19/20

Project Info Project Manager's Commentary
Support for REF Not started
REF2021 Data Requirements Implementation Not started, expected start date mid November 2019

 

Section Three: Projects in Progress

 

Project Info Project Manager's Commentary

 

RIS005  Ethics Tool Procurement

Discretionary / Sponsor Funded

Milestones:

Milestone Due Date
Project Closure Complete TBC

RAG Status : AMBER

 

 

 

Report by Karen Stirling for October 2019

Achievements in Last Period 
  • Documentation received for Single Sign on and Dev Tech resource assigned 
  • New domain name confirmed by ITI
  • Agreed that a mini TAD should be created - effort for set up and document is 1 day
Issues
  • Business contact has advised that following workshop on 31/10/2019 they are not ready for SSO to be set up in Live, date for when set up required is to be confirmed by business team
  • Revised closure milestone to be agreed 
Next Steps
  • Confirmation of SSO date to be provided
  • SSO set up completed
  • Completion report completed and project closure approval

The project status is AMBER as SSO set up date to be confirmed by business team and amend closure date to end of November

 

RIS007 PURE Upgrades v5.13 to 5.15

Compliance / Core Funded

Milestones:

Upgrade to 5.15 ASOR 12-Nov-2019
Upgrade to 5.15 LIVE Complete 19-Nov-2019
Upgrade to 5.15 DSOR Complete (LIVE) 03-Dec-2019
Closure 10-Dec-2019

 

RAG Status: GREEN

 

 

Report by Karen Stirling for October 2019

Achievements in Last Period 
  • Upgrade Dev environment to Pure 5.15.2 completed
  • Upgrade Test environment to Pure 5.15.2 and Java Upgrade completed
  • Commence and completed UAT
  • Prep for Cloud Portal - schedule meeting with Elsevier end of October / early November
  • Go CAB approval
  • IS Alert published
Issues
  • UWP testing to be completed - this should not prevent deployment to Live
  • RIS Business Lead advised there are a number of issues however they are happy to sign off and deploy with these issues as they have workarounds in place and application needs to move the next upgrade for some of these issues to be resolved by supplier. Business Lead is acceptance of any risk.
  • For awareness the EASE upgrade project is deploying on 20th November however we don't expect any impact from reviewing with project manager for this project but will raise with Go CAB.
  • Review budget as activity is reduced
Next Steps 
  • Acceptance Sign Off
  • Cloud Portal meeting with supplier 6th November
  • Deploy Java and Pure v5.15.2-1 to Live scheduled 19th November 
  • Deployment review sign off

 

The project status is GREEN 

 

RIS008 REF2021 Data Requirements Analysis

Discretionary / Sponsor Funded

Milestones:

Milestone Date
Delivery Business requirements and Options Paper (II) 20-Sep-2019
Closure Review 04-Oct-2019

 

RAG Status : AMBER

Report by Tim Gray for October 2019

Achievements in Last Period
  • The prototype development was completed using a trial version of WinAutomation
  • Licence for WinAutomation purchased
  • Meeting held with a representative from Core Systems, feedback incorporated into Options Paper
  • Milestones replanned and approved
Issues
  • There was a significant delay in feedback from Core Systems. Further distribution had been embargoed until feedback had been received. At the end of this reporting period feedback was received and some changes made. This delay resulted in the need to replan the milestones (see RIS Project Log Item 8). This impact of this is a delay to the implementation, this, in turn, is compensated by the reduced time and effort required to implement this solution.
  • The time to develop the prototype was more than initially allocated resulting in the project requiring more budget. However, the prototype will significantly reduce the time need during the subsequent implementation project. This is recorded in the project log above.
Next Steps 
  • Circulate Options Paper to a wider audience
  • Move the project to closure

 

The project status is AMBER to highlight the delay in receiving feedback from Core Systems on the Options Paper. While this has now been resolved, the project manager would like this noted in the October report.

 

RIS011 Pure Upgrade v5.16 to v5.18

Compliance / Core Funded

Milestones:

Milestone

Due Date

Planning Complete

08-Nov-2019

Upgraded DEV to Pure v5.16.1       

22-Nov-2019

Upgraded DEV to Pure v5.16.2

20-Dec-2019

Upgraded TEST to Pure v5.16

28-Jan-2020

Upgraded LIVE to Pure v5.16

31-Jan-2020

Upgraded DEV to Pure v5.17

13-Mar-2020

Upgraded TEST to Pure v5.17

17-Apr-2020

Upgraded LIVE to Pure v5.17

22-Apr-2020

Upgrade DEV to Pure v5.18

10-Jul-2020

Upgraded TEST to Pure v5.18

14-Aug-2020

Upgraded LIVE to Pure v5.18

19-Aug-2020

DSOR Sign-off

20-Aug-2020

Project Closure

02-Sep-2020

 

RAG Status:  GREEN

 

Report by Kevin Hone for October 2019

Achievements in Last Period:
  • Project initiated

  • Project Brief written and issued for review

Issues:
  • None

Next Steps:

  • Preparations for deployment of v5.16.1 to the development environment

 

The project status is GREEN

 

RIS012 Worktribe Upgrade v3.1

Compliance / Core Funded

Milestones:

Accept Integration & Acceptance complete 19-Nov-2019
Deliver Delivery of upgrade 26-Nov-2019
Deliver Delivery sign-off (Upgrade) 03-Dec-2019
Deliver Delivery of SSO changes 05-Dec-2019
Deliver Delivery sign-off (SSO) 12-Dec-2019
Close Project closure 19-Dec-2019

RAG Status:  AMBER

 

Report by David Watters for October 2019

Achievements in Last Period
  • TEST environment upgraded to v3.1 (auto-patching now in place)
  • Agreement on changes to Shibboleth reached
Issues
  • Milestones replanned to allow greater time for UAT and SSO changes
Next steps
  • Carry out UAT and sign off test upgrade
  • Schedule LIVE upgrade with business partners and vendor

 

The project status is AMBER because the milestones have been modified.

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary
                                                                                                

                                                                                                                      

 

 

 

 

 

 

 

 

 

 

 

 

AttachmentSize
Image icon ris_forward_look_oct19.jpg75.46 KB
Image icon ris_rsource_oct_19.jpg87.99 KB
Programme Status
RAG Status
Overall
GREEN
Has formal escalation taken place?
No
RAG Commentary
All projects underway as per forward look and budget within programme is as expected at this stage in the financial year

Documentation

Not available.