Report for September 2019
- Report Date
- September 2019
Report compiled by Karen Stirling, RIS Programme Manager for Dominic Tate (Programme Owner), Damon Querry, Lorna Thomson, Liz Welch, Dax Carroll, Jacq McMahon, Susan Cooper
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
The Programme Commentary
Overall progress within the Programme is as follows :
- RIS005 - Waiting for details from supplier for SSO set up
- RIS007 - Currently user acceptance testing underway for v5.15.2-1
- RIS008 - Options paper submitted to Applications Director, activity progressing with prototype
- RIS012 - Development environment updated to v3.1
- RIS011 - Project Manager allocated for the project to commence in mid October
For REF2021 interest projects have been added and a communication has been issued out to all project manager for any new projects to be included.
Please find link to REF2021 Portfolio page. Some interest projects have been added to the list and a further communication to project managers to highlight importance of REF2021 and to confirm if any other projects should be recorded.
Overall Programme RAG: GREEN
Forward Look and RAG
Resource Position
Section Two: Projects Not Started for 19/20
Project Info | Project Manager's Commentary |
Pure Upgrade v5.16 to v5.18 | Not started expected start date mid October 2019 |
Support for REF | Not started |
REF2021 Data Requirements Implementation | Not started, expected start date October 2019 |
Section Three: Projects in Progress
Project Info | Project Manager's Commentary | ||||||||||||
RIS005 Ethics Tool Procurement Discretionary / Sponsor Funded Milestones:
RAG Status : AMBER
|
Report by Karen Stirling for September 2019 Achievements in Last Period
Issues
Next Steps
The project status is AMBER amend closure date to end of October
|
||||||||||||
RIS007 PURE Upgrades v5.13 to 5.15 Compliance / Core Funded Milestones:
RAG Status: GREEN
|
Report by Karen Stirling for September 2019 Achievements in Last Period
Issues
Next Steps
The project status is GREEN
|
||||||||||||
RIS008 REF2021 Data Requirements Analysis Discretionary / Sponsor Funded Milestones:
RAG Status : GREEN |
Report by Tim Gray for September 2019 Achievements in Last Period
Issues
Next Steps
The project status is GREEN
|
||||||||||||
RIS012 Worktribe Upgrade v3.1 Compliance / Core Funded Milestones:
RAG Status: GREEN
|
Report by David Watters for September 2019 Achievements
Issues
Next steps
The project status is GREEN |
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
|
|
|
|
|
|
|
|
|
|
|
|
|
Attachment | Size |
---|---|
![]() | 80.53 KB |
![]() | 83.33 KB |