Report for September 2019

Report Date
September 2019

Report compiled by Karen Stirling, RIS Programme Manager for Dominic Tate  (Programme Owner), Damon Querry, Lorna Thomson, Liz Welch, Dax Carroll, Jacq McMahon, Susan Cooper

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section One: Programme Commentary, RAG and Resources Update

 

The Programme Commentary

Overall progress within the Programme is as follows :

  • RIS005 - Waiting for details from supplier for SSO set up
  • RIS007 - Currently user acceptance testing underway for v5.15.2-1
  • RIS008 - Options paper submitted to Applications Director, activity progressing with prototype
  • RIS012 - Development environment updated to v3.1
  • RIS011 - Project Manager allocated for the project to commence in mid October

 

For REF2021 interest projects have been added and a communication has been issued out to all project manager for any new projects to be included.

 

Please find link to REF2021 Portfolio page. Some interest projects have been added to the list and a further communication to project managers to highlight importance of REF2021 and to confirm if any other projects should be recorded.

 

Overall Programme RAG: GREEN

 

Forward Look and RAG

 

 

Resource Position

 

 

 

 Section Two: Projects Not Started for 19/20

Project Info Project Manager's Commentary
Pure Upgrade v5.16 to v5.18 Not started expected start date mid October 2019
Support for REF Not started
REF2021 Data Requirements Implementation Not started, expected start date October 2019

 

Section Three: Projects in Progress

 

Project Info Project Manager's Commentary

 

RIS005  Ethics Tool Procurement

Discretionary / Sponsor Funded

Milestones:

Milestone Due Date
Project Closure Complete 31/10/2019

RAG Status : AMBER

 

 

 

Report by Karen Stirling for September 2019

Achievements in Last Period
  • Initial Completion report reviewed by Project Sponsor 
  • Meeting held between Dev Tech resource and Infonetica regarding single sign on - documentation to be exchanged
  • New domain name requested from ITI
Issues
  • SSO required to be available for 31st October and closure date to be extended to cover this 
Next Steps
  • Provision of single sign on to test
  • Completion report completed and project closure approval

The project status is AMBER amend closure date to end of October

 

RIS007 PURE Upgrades v5.13 to 5.15

Compliance / Core Funded

Milestones:

Upgrade to 5.15 TEST Complete 05-Nov-2019
Upgrade to 5.15 ASOR 12-Nov-2019
Upgrade to 5.15 LIVE Complete 19-Nov-2019
Upgrade to 5.15 DSOR Complete (LIVE) 03-Dec-2019
Closure 10-Dec-2019

 

RAG Status: 

GREEN

 

Report by Karen Stirling for September 2019

Achievements in Last Period 

  • Upgrade Dev environment to Pure 5.15.2-1
  • Upgrade Test environment to Pure 5.15.2-1 and Java Upgrade
  • Commenced UAT within Business teams for 6 weeks
  • Prep for Cloud Portal

Issues

  • Due to delay in receiving 5.15.2-1 release project is 2 weeks behind schedule 
  • Business team require 6 weeks to complete UAT and tidy data
  • Revised milestones for remaining activity completed, resulting in Live deployment of Java and pure 5.15.2-1 now 19th November 2019
  • Review budget as activity is reduced

Next Steps 

  • Continue and complete UAT
  • Prep for Cloud Portal - schedule meeting with Elsevier end of October / early November
  • Prep for Live deployment

 

The project status is GREEN 

 

 

RIS008 REF2021 Data Requirements Analysis

Discretionary / Sponsor Funded

Milestones:

Milestone Date
Delivery Business requirements and Options Paper (II) 20-Sep-2019
Closure Review 04-Oct-2019

 

RAG Status : 

GREEN

Report by Tim Gray for September 2019

Achievements in Last Period
  • Prototype development has been progressed
  • Options Paper updated and sent to Applications Director 
  • Remaining milestones re-planned

Issues

  • Documents have not been circulated to a wider audience due to waiting on information form Core Systems
  • Pinning down the requirements for the prototype took much longer than anticipated. This was attributed to consideration given to various edge cases.

Next Steps 

  • Circulate Options Paper to wider audience
  • Move project to closure

The project status is GREEN

 

RIS012 Worktribe Upgrade v3.1

Compliance / Core Funded

Milestones:

Accept Integration & Acceptance complete 03-Oct-2019
Deliver Delivery 10-Oct-2019
Deliver Delivery sign-off 22-Oct-2019
Close Project closure 31-Oct-2019

 

 

RAG Status: GREEN

 

Report by David Watters for September 2019

Achievements

  • DEV environment upgraded to v3.1 (auto-patching now in place)
  • Discussions round changes to Shibboleth taking place

Issues

  • None

Next steps

  • Establish work on Shibboleth solution
  • Schedule TEST upgrade with business partners and vendor

 

 

The project status is GREEN

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary
                                                                                                

                                                                                                                      

 

 

 

 

 

 

 

 

 

 

 

 

Programme Status
Has formal escalation taken place?
No

Documentation

Not available.