Report for August 2019

Report Date
August 2019

Report compiled by Karen Stirling, RIS Programme Manager for Dominic Tate  (Programme Owner), Damon Querry, Lorna Thomson, Liz Welch, Dax Carroll, Laura Petrie, Jacqui McMahon, Susan Cooper

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section One: Programme Commentary, RAG and Resources Update

 

The Programme Commentary

Overall progress within the Programme is as follows :

  • RIS005 - working on closure report and gathering information on SSO
  • RIS007 - Java Upgrade and Pure 5.15.1 deployed to development however issues confirmed that we need to go to 5.15.2 through the environments 
  • RIS008 - Options appraisal being finalised from discussions with Core Systems
  • RIS012 - Project planning completed
  • RIS011 - Project Manager allocated for the project to commence in October

 

For REF2021 interest projects have been added and a communication has been issued out to all project manager for any new projects to be included.

 

Please find link to REF2021 Portfolio page. Some interest projects have been added to the list and a further communication to project managers to highlight importance of REF2021 and to confirm if any other projects should be recorded.

 

Overall Programme RAG: GREEN

 

Forward Look and RAG

 

 

Resource Position

 

 

 

 Section Two: Projects Not Started for 19/20

Project Info Project Manager's Commentary
Pure Upgrade v5.16 to v5.18 Not started expected start date early October 2019
Support for REF Not started
REF2021 Data Requirements Implementation Not started, expected start date October 2019

 

Section Three: Projects in Progress

 

Project Info Project Manager's Commentary

 

RIS005  Ethics Tool Procurement

Discretionary / Sponsor Funded

Milestones:

Milestone Due Date
Project Closure Complete 19-Sept-2019

RAG Status : AMBER

 

 

 

Report by Karen Stirling for August 2019

Achievements in Last Period draft
  • Initial Completion report drafted and issued to RIS team manager and Project Sponsor for review
  • Dev tech resource engaged to review single sign on with supplier
Issues
  • Remaining milestones have been agreed to be removed and earlier closure date by Project Sponsor however on submission to IS Applications Governance this was not approved as they have asked for review by  Production Management to have closure milestone agreed
  • As Project Sponsor on leave this month initial review of closure report delayed in issuing out to wider project team for comment
  • Dev Tech resource has still to contact Infonetica to confirm SSO requirements this is being chased
Next Steps
  • Provision of single sign on information
  • Completion report completed and project closure approval

The project status is AMBER as project closure report review delayed due to unavailability of key resource and also waiting for SSO information between Infonetica and Dev Tech resource. Revised milestone to be agreed for closure.

 

RIS007 PURE Upgrades v5.13 to 5.15

Compliance / Core Funded

Milestones:

Upgrade to 5.15.2 DEV Complete 18-Sep-2019
Upgrade to 5.15 TEST Complete 09-Oct-2019
Upgrade to 5.15 ASOR 17-Oct-2019
Upgrade to 5.15 LIVE Complete 31-Oct-2019
Upgrade to 5.15 DSOR Complete (LIVE) 28-Nov-2019
Closure 17-Dec-2019

 

RAG Status: 

GREEN

 

Report by Karen Stirling for August 2019

Achievements in Last Period 

  • Pure 5.13.4 Live upgrade and Tomcat upgrade completed successful on 8th August
  • Commenced prep work for Cloud portal
  • Data refresh for Dev and Test completed from Live for next upgrade activity
  • ROS Tables removed from Dev, Test and Live
  • Java Upgrade and Pure 5.15.1 upgrade completed for Dev

Issues

  • Deployment of 5.15.1 allows the RIS team to prep training with business users however as expected some issues encountered and not suitable for this version to be taken through test to live.
  • Key issues is rendering of UI
  • Revise dates for delivery to Test and Live dependent on availability of 5.12.2 code from Elsevier
  • Submit revised milestones to WIS for approval

Next Steps 

  • Upgrade Dev environment to Pure 5.15.2
  • Upgrade Test environment to Pure 5.15.2 and Java Upgrade
  • Commence UAT
  • Prep for Cloud Portal

 

The project status is GREEN 

 

 

RIS008 REF2021 Data Requirements Analysis

Discretionary / Sponsor Funded

Milestones:

Milestone Date
Delivery Business requirements and Options Paper (II) 20-Sep-2019
Closure Review 04-Oct-2019

 

RAG Status : 

GREEN

Report by Tim Gray for August 2019

Achievements in Last Period
  • The remaining project milestones replanned at the start of the month. 
  • The follow-up meeting with Core Systems team held and agreement reached on processes to be investigated for verifying historical data. This will involve building a prototype for capturing screen data from Oracle HR
  • Bookings for next stages secured.

Issues

  • Documents have not been circulated to a wider audience due to waiting on information form Core Systems
  • Although some progress has been made this month, after the meeting with core systems some additional work will now be undertaken. The output of this investigative work will feed into the options paper. When this is completed, wider circulation will start.
  • As this is taking longer, there is an increasing risk that the implementation time is decreasing.  Although not a direct risk to this project, a risk has been captured in the risk log

Next Steps 

  • Complete investigation/prototype
  • Update Options paper with outcomes
  • Circulate BRD/Options Appraisal to wider stakeholders for comment

 

 

The project status is GREEN

 

RIS012 Worktribe Upgrade v3.1

Compliance / Core Funded

Milestones:

Build Build complete (DEV) 12-Sep-2019
Accept Integration & Acceptance complete 03-Oct-2019
Deliver Delivery 10-Oct-2019
Deliver Delivery sign-off 22-Oct-2019
Close Project closure 31-Oct-2019

 

 

RAG Status: GREEN

 

Report by David Watters for August 2019

Achievements

  • Project brief completed and signed off

Issues

  • None

Next steps

  • Establish work on Shibboleth solution
  • Schedule next stages with business partners and vendor

 

 

The project status is GREEN

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary
                                                                                                

                                                                                                                      

 

 

 

 

 

 

 

 

 

 

 

 

AttachmentSize
Image icon fl-ris-aug19.jpg101.19 KB
Image icon figs-ris-aug19.jpg82.61 KB

Documentation

Not available.