Report for July 2019

Report Date
July 2019

Report compiled by Karen Stirling, RIS Programme Manager for Dominic Tate  (Programme Owner), Damon Querry, Lorna Thomson, Liz Welch, Dax Carroll, Laura Petrie, Pauline Jones, Susan Cooper

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section One: Programme Commentary, RAG and Resources Update

 

The Programme Commentary

Overall progress within the Programme is as follows :

  • RIS005 - Terms and Conditions now signed off as confirmed by Procurement, review SSO requirements to allow project closure to complete
  • RIS007 - UAT signed off and preparations for Live upgrade for Tomcat and Pure 5.13.4 scheduled for 8th August
  • RIS008 - Concerns remain around impact from Core Systems
  • RIS012 - Project has been initiated and planning in progress

 

For REF2021 a request was issued out to Core Systems project managers to confirm project codes to be added to portfolio page - no response to date, this has been raised to ISG PMO.

 

Please find link to REF2021 Portfolio page.

 

Overall Programme RAG: GREEN

 

Forward Look and RAG

 

 

Resource Position

 

 

 

 Section Two: Projects Not Started for 19/20

Project Info Project Manager's Commentary
Pure Upgrade v5.16 to v5.18 Not started
Support for REF Not started
REF2021 Data Requirements Implementation Not started

 

Section Three: Projects in Progress

 

Project Info Project Manager's Commentary

 

RIS005  Ethics Tool Procurement

Discretionary / Sponsor Funded

Milestones:

Milestone Due Date
Project Closure Complete 23-Aug-2019

RAG Status : AMBER

 

 

 

Report by Karen Stirling for July 2019

Achievements in Last Period 
  • Terms and Conditions and Contract now signed off with Supplier
  • Initial Completion report drafted and issued to RIS team manager and Project Sponsor for review
  • Dev tech resource engaged to review single sign on with supplier
Issues
  • Remaining milestones have been agreed to be removed and earlier closure date by Project Sponsor however on submission to IS Applications Governance this was not approved as they have asked for review by  Production Management to have closure milestone agreed
Next Steps
  • Provision of single sign on information
  • Completion report completed and project closure approval

The project status is AMBER this is due to the revised project milestones e.g. earlier closure date not  approved at Internal IS Application review, stating agreement required from Production Management for removing implementation stage of project, this can now take place as Terms and Conditions have been signed off and information regarding single sign being made available by Supplier. Revised milestone to be agreed for closure

 

 

 

 

RIS007 PURE Upgrades v5.13 to 5.15

Compliance / Core Funded

Milestones:

Upgrade to Pure 5.13.4 LIVE Complete 08-Aug 2019
Upgrade to Pure 5.13.4 DSOR 14-Aug-2019
Upgrade to Pure 5.15.1 DEV Complete  21-Aug-2019
Upgrade to 5.15.2 DEV Complete 18-Sep-2019
Upgrade to 5.15 TEST Complete 09-Oct-2019
Upgrade to 5.15 ASOR 17-Oct-2019
Upgrade to 5.15 LIVE Complete 31-Oct-2019
Upgrade to 5.15 DSOR Complete (LIVE) 28-Nov-2019
Closure 17-Dec-2019

 

RAG Status: 

GREEN

 

Report by Karen Stirling for July 2019

Achievements in Last Period

  • 5.13 TEST Tomcat upgrade, refresh and upgrade completed 9 July
  • UAT completed and signed off by business team
  • Preparation activity for live deployment - Go CAB, Service Alert and communication to users

Issues

  • Revised milestone for Live deployment to 8th August
  • Descoped GDPR activity
  • Reduction of budget for descope work and additional deployment agreed and approved

Next Steps 

  • 5.13.4 Live Tomcat upgrade scheduled for 8th August
  • Commence prep work for Cloud portal
  • Data refresh for Dev and Test from Live
  • Commence Java Upgrade in Dev and Pure 5.15.1 upgrade for Dev

 

The project status is GREEN 

 

 

RIS008 REF2021 Data Requirements Analysis

Discretionary / Sponsor Funded

Milestones:

Milestone Date
Delivery Business requirements and Options Paper (II) 09-Aug-2019
Closure Review 23-Aug-2019

 

RAG Status : 

GREEN

Report by Tim Gray for July 2019

Achievements in Last Period

  • Business requirements document (BRD) signed off by GaSP
  • Remaining milestones have been replanned

Issues

  • Documents have not been circulated to a wider audience due to waiting on information form Core Systems
  • The follow-up meeting with Core Systems team has been delayed due to a Systems meeting through the Finance Transformation Board.
  • BA has left the University, While this does not have a significant impact as the BRD is all but signed off, this will involve some additional tasks for the Data Architect. This has been planned in early August.  

Next Steps 

  • Circulate BRD to wider stakeholders for comment
  • Hold follow up meeting with Core Systems team 
  • Create updated Options Appraisal document, circulate to stakeholders  
  • Move to Closure

The project remains GREEN

 

RIS012 Worktribe Upgrade v3.1

Compliance / Core Funded

Milestones:

Stage Milestone Due Date
Plan Planning milestone 16-Aug-2019
Deliver Delivery 10-Oct-2019
Close Project closure 31-Oct-2019

 

 

RAG Status:

GREEN

Report by David Watters for July 2019

Achievements

  • Project initiated and PM assigned
  • Work started in project brief

Issues

  • None

Next steps

  • Complete project planning
  • Schedule next stages with business partners and vendor

 

The project status is GREEN

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary
RIS003 Pure Upgrade v5.10 to v5.12

Report by Kim Keenan

Completion Report

This project closed 17th August 2018

 

RIS004 Worktribe Upgrades - Readiness for GDPR

 Report by Kim Keenan

Completion report

This project closed 21st September 2018

AP89-027 GDPR for Pure

Update by Karen Stirling

PICCL

This proposal was withdrawn 29th March 2019

AP89-026 Support for REF

Update by Karen Stirling

PICCL

This proposal was withdrawn 29th March 2019

AP078-29 PURE Research Explorer- replace with new module from Elsevier Update by Karen Stirling

PICCL

This proposal was withdrawn 29th March 2019

RES069 Pure upgrade to new Project Model

Report by Karen Stirling

Completion report

This project closed on 28th June 2019

RIS006 Worktribe upgrade v3.0

Report by David Watters

Completion report

This project was closed on 28th June 2019

Documentation

Not available.