Report for June 2019

Report Date
June 2019

Report compiled by Karen Stirling, RIS Programme Manager for Dominic Tate  (Programme Owner), Damon Querry, Lorna Thomson, Liz Welch, Dax Carroll, Laura Petrie, Pauline Jones, Susan Cooper

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section One: Programme Commentary, RAG and Resources Update

 

The Programme Commentary

Overall progress within the Programme is as follows :

  • RES069 - Closure report completed and signed off by project team, submitted for internal IS Apps approval
  • RIS005 - Terms and Conditions remain outstanding, therefore the supplier will not provide single sign on details until completed and revised milestone dates cannot be agreed until this information received 
  • RIS006 - Closure report completed and signed off by project team, submitted for internal IS Apps approval
  • RIS007 - Due to limited dev tech resource the milestones for the next upgrade to 5.13.4 will be pushed about by circa. 2 weeks
  • RIS008 - As-Is processes now signed off and BRD nearing completion. Concerns regarding access to read only data from Core Systems implementation, meeting to review arranged with Core Systems on 4th July 2019

Discussion around new  'in year' project to cover Worktribe upgrade to v3.1 in advance of new patching process and change freeze restrictions in September, agreed to start project this year from remaining programme funds.

 

Please find link to REF2021 Portfolio page.

 

Overall Programme RAG: AMBER

 

Forward Look and RAG

 

 

Resource Position

 

 

 

 Section Two: Projects Not Started

Project Info Project Manager's Commentary
N/A All projects starts, suspended or withdrawn

 

Section Three: Projects in Progress

 

Project Info Project Manager's Commentary

RES069 PURE UPGRADE TO NEW PROJECT MODEL

Compliance / Core & Sponsor Funded

Milestones

Milestone Due Date
N/A N/A

RAG Status:  

BLUE

 

 

Report by Karen Stirling for June 2019

Activities completed
  • Completion Report drafted, reviewed and updated following consultation with project team
  • Project closure agreed and report submitted to internal IS Apps approval

Issues

N/A

 

Next Steps
  • None

The project status is BLUE and project closed.

 

 

RIS005  Ethics Tool Procurement

Discretionary / Sponsor Funded

Milestones:

Milestone Due Date
Procurement Complete TBC
Project Closure Complete TBC

RAG Status :

AMBER

 

 

Report by Karen Stirling for June 2019

Achievements in Last Period 
  • Terms and Conditions are now with Supplier to sign off
Issues
  • Remaining milestones have been agreed to be removed and earlier closure date by Project Sponsor however on submission to IS Applications Governance this was not approved as they have asked for review by Senior Supplier and Production Management. As this project does not have a Senior Supplier role the Project Manager will review with Head of Production Management and resubmit revised milestones.
  • This will be dependent on the successful sign off of the Terms and Conditions which will allow single sign on information being shared with the project team
  • Terms and Conditions timescales to complete have been impacted due to discussions around accessibility and liability which Project Sponsor has confirmed should now allow these to be signed off early July.
  • Concerns that Procurement have not been communicating updates on progress
Next Steps
  • Confirmation of Terms and Conditions agreed
  • Provision of single sign on information
  • Completion report

The project status is AMBER this is due to the revised project milestones e.g. earlier closure date not  approved at Internal IS Application review, stating agreement required from Production Management for removing implementation stage of project. However this is dependent on Terms and Conditions being signed off and information regarding single sign on being provided by Supplier. Project Sponsor has advised expectation these will be signed off early July.

 

 

 

RIS006 Worktribe Upgrade V3

Compliance / Core Funded

Milestones:

Milestones

N/A N/A

RAG Status :

BLUE

 

Report by David Watters for June 2019

Achievements to date

  • Upgrade deployed to LIVE
  • Project closed

Issues

N/A

Next Steps

  • None

The project status is BLUE - closed

 

 

 

.

RIS007 PURE Upgrades v5.13 to 5.15

Compliance / Core Funded

Milestones:

Upgrade to Pure 5.13.4 TEST Complete 09-Jul-2019
Upgrade to Pure 5.13.4 ASOR 25-Jul-2019
Upgrade to Pure 5.13.4 LIVE Complete 31-Jul-2019
Upgrade to Pure 5.13.4 DSOR 14-Aug-2019
Upgrade to Pure 5.14 DEV Complete (PLACEHOLDER) 21-Aug-2019
Upgrade to Pure 5.14 TEST Complete (PLACEHOLDER) 23-Aug-2019
Upgrade to 5.14 LIVE Complete (PLACEHOLDER) 05-Sep-2019
Upgrade to 5.14 DSOR Complete (LIVE) (PLACEHOLDER) 12-Sep-2019
Upgrade to 5.15 DEV Complete 18-Sep-2019
Upgrade to 5.15 TEST Complete 09-Oct-2019
Upgrade to 5.15 ASOR 17-Oct-2019
Upgrade to 5.15 LIVE Complete 31-Oct-2019
Upgrade to 5.15 DSOR Complete (LIVE) 28-Nov-2019
Closure 17-Dec-2019

 

 

 

RAG Status: 

AMBER

 

Report by Ian Mitchell for June 2019

Achievements in Last Period
  • 5.13 DEV upgrade complete
  • Re-estimate of project including additional scope item approved by WIS
  • 5.13 TEST  - upgrade in progress at time of writing.
  • Resources confirmed for DevTech.

 

Issues

  • Delay in upgrade to 5.13 DEV has resulted in tight timescales which means 5.13 Live milestone being pushed back to 8 August (from 31 July).

 

Next Steps 

  • 5.13 TEST Tomcat upgrade, refresh and upgrade to commence 1 July, due complete 9 July.
  • Thereafter 5.13 Live upgrade will be commenced, with new milestone date request to WIS for 8 August.
  • ASORs requested by Suran Perera -  WIS submission made for 5 July for two ASOR milestones; 5.13 (25 Jul) and 5.15 (17 Oct).
  • Business has requested GDPR be de-scoped. WIS submission made for 5 July.
  • 5.13 Live milestone – WIS submission made for 5 July for milestone date change  to 8 August, from 31 July.

 

The project status is AMBER due to the following: continued limitation of DevTech resource availability to deal with any unplanned work

 

 

RIS008 REF2021 Data Requirements Analysis

Discretionary / Sponsor Funded

Milestones:

Milestone Date  
Delivery Business requirements and Options Paper (II) 28-June-2019 No
Closure Review 12-July-2019 No

 

RAG Status : 

AMBER

Report by Tim Gray for June 2019

Achievements in Last Period
  • AS IS processes signed off 
  • Business requirements document (BRD) in progress nearing completion. GaSP have confirmed the documented requirements are correct. 

Issues

  • Further REF guidelines from REF UK have issued more information about the auditing process. This will require access to current systems that will be impacted by the implementation to of the new core Finance/HR. We need to ensure access to the current, then legacy systems, in order to provide the required audit data for the REF submission. 
  • The Project Sponsor is only available until 15th July before going on maternity leave, this is putting additional time pressure on answering a multitude of questions in time to produce a revamped options appraisal. 

Next Steps 

  • Circulate BRD to wider stakeholders for comment and sign off
  • Hold discussions with Core Systems team regarding dates for legacy system access (see above)
  • Document TO BE processes based on signed off BRD
  • Create updated Options Appraisal document, circulate to stakeholders  
  • Move to Closure

The project status is AMBER  - Access to current HR system will be required into early to mid-2021 to provide data for the REF Audit process. The current dates for Core Systems implementation are an issue as availability after July 2020 is an unknown. The project team are meeting with Core Systems team to discuss on 4th July 2019.

 

 

 

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary
RIS003 Pure Upgrade v5.10 to v5.12

Report by Kim Keenan

Completion Report

This project closed 17th August 2018

 

RIS004 Worktribe Upgrades - Readiness for GDPR

 Report by Kim Keenan

Completion report

This project closed 21st September 2018

AP89-027 GDPR for Pure

Update by Karen Stirling

PICCL

This proposal was withdrawn 29th March 2019

AP89-026 Support for REF

Update by Karen Stirling

PICCL

This proposal was withdrawn 29th March 2019

AP078-29 PURE Research Explorer- replace with new module from Elsevier Update by Karen Stirling

PICCL

This proposal was withdrawn 29th March 2019

RES069 Pure upgrade to new Project Model

Report by Karen Stirling

Completion report

This project closed on 28th June 2019

RIS006 Worktribe upgrade v3.0

Report by David Watters

Completion report

This project was closed on 28th June 2019

Documentation

Not available.