Report for May 2019
- Report Date
- May 2019
Report compiled by Karen Stirling, RIS Programme Manager for Dominic Tate (Programme Owner), Damon Querry, Lorna Thomson, Liz Welch, Dax Carroll, Laura Petrie, Pauline Jones, Susan Cooper
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
The Programme Commentary
Overall progress within the Programme is as follows :
- RES069 - Deployment Review sign off complete, chasing final sign off from Dev Tech, Closure report delayed due to PM on Annual Leave
- RIS005 - Agreed change of milestones with Project Sponsor however there has been a request from IS Applications Governance process to gain agreement from Production Management. Concerns that the Terms and Conditions remain unsigned after 2 months
- RIS006 - Deployment to Live completed on 30th May
- RIS007 - Milestone and budget review following un suspension. TomCat upgrade completed
- RIS008 - Progress with Business Requirements and As-IS and To-be processes
Discussion around new 'in year' project to cover Worktribe upgrade to v3.1 in advance of new patching process and change freeze restrictions in September, review of budget required to facilitate the commencement of this project.
Concerns around RIS007 budget position for 19/20 project activity, Programme manager is reviewing with Head of PMO and Head of Production Management to clarify funding for next year.
For information only, STU252 project has now completed and project is now closed.
Please find link to REF2021 Portfolio page.
Overall Programme RAG: AMBER
Forward Look and RAG
Resource Position
Section Two: Projects Not Started
Project Info | Project Manager's Commentary |
N/A | All projects starts, suspended or withdrawn |
Section Three: Projects in Progress
Project Info | Project Manager's Commentary | ||||||||||||||||||||||||||||
RES069 PURE UPGRADE TO NEW PROJECT MODEL Compliance / Core & Sponsor Funded Milestones
RAG Status: AMBER
|
Report by Karen Stirling for May 2019 Activities completed
Issues
Next Steps
The project status is AMBER as closure milestone requires to be moved out by 3 weeks due to PM annual leave.
|
||||||||||||||||||||||||||||
RIS005 Ethics Tool Procurement Discretionary / Sponsor Funded Milestones:
RAG Status : AMBER
|
Report by Karen Stirling for May 2019 Achievements in Last Period Draft
Issues
Next Steps
The project status is AMBER this is due to the revised project milestones e.g. earlier closure date not approved at Internal IS Application review, stating agreement required from Production Management for removing implementation stage of project.
|
||||||||||||||||||||||||||||
RIS006 Worktribe Upgrade V3 Compliance / Core Funded Milestones: Milestones
RAG Status : GREEN
|
Report by David Watters for May 2019 Achievements to date
Issues
Next Steps
The project status is GREEN
. |
||||||||||||||||||||||||||||
RIS007 PURE Upgrades v5.13 to 5.15 Compliance / Core Funded Milestones:
RAG Status: AMBER
|
Report by Ian Mitchell for May 2019 Achievements in Last Period
Issues
Next Steps
The project status is AMBER due to the following:
|
||||||||||||||||||||||||||||
RIS008 REF2021 Data Requirements Analysis Discretionary / Sponsor Funded Milestones:
RAG Status : GREEN |
Report by Tim Gray for May 2019 Achievements in Last Period
Issues
Next Steps
The project status remains at GREEN
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
RIS003 Pure Upgrade v5.10 to v5.12 |
Report by Kim Keenan This project closed 17th August 2018
|
RIS004 Worktribe Upgrades - Readiness for GDPR |
Report by Kim Keenan This project closed 21st September 2018 |
AP89-027 GDPR for Pure |
Update by Karen Stirling This proposal was withdrawn 29th March 2019 |
AP89-026 Support for REF |
Update by Karen Stirling This proposal was withdrawn 29th March 2019 |
AP078-29 PURE Research Explorer- replace with new module from Elsevier | Update by Karen Stirling
This proposal was withdrawn 29th March 2019 |