Section One: Programme Commentary, RAG and Resources Update

 

The Programme Commentary

Overall progress within the Programme is as follows :

  • RES069 - Deployment Review sign off complete, chasing final sign off from Dev Tech, Closure report delayed due to PM on Annual Leave
  • RIS005 - Agreed change of milestones with Project Sponsor however there has been a request from IS Applications Governance process to gain agreement from Production Management. Concerns that the Terms and Conditions remain unsigned after 2 months 
  • RIS006 - Deployment to Live completed on 30th May
  • RIS007 - Milestone and budget review following un suspension. TomCat upgrade completed
  • RIS008 - Progress with Business Requirements and As-IS and To-be processes

Discussion around new  'in year' project to cover Worktribe upgrade to v3.1 in advance of new patching process and change freeze restrictions in September, review of budget required to facilitate the commencement of this project.

Concerns around RIS007 budget position for 19/20 project activity, Programme manager is reviewing with Head of PMO and Head of Production Management to clarify funding for next year.

For information only, STU252 project has now completed and project is now closed.

Please find link to REF2021 Portfolio page.

 

Overall Programme RAG: AMBER

 

Forward Look and RAG

 

 

Resource Position

 

 

 

 Section Two: Projects Not Started

Project Info Project Manager's Commentary
N/A All projects starts, suspended or withdrawn

 

Section Three: Projects in Progress

 

Project Info Project Manager's Commentary

RES069 PURE UPGRADE TO NEW PROJECT MODEL

Compliance / Core & Sponsor Funded

Milestones

Milestone Due Date
Closure 14-Jun_2019

RAG Status:  

AMBER

 

 

Report by Karen Stirling for May 2019

Activities completed
  • Completed final production handover activities 
  • Review of remaining JIRAs and re- allocation where required to RIS007
  • Deployment Sign off review completed chasing final sign off from Dev Tec h resource

Issues

  • Due to PM annual leave project closure delayed to June, milestone requires to be extended to mid June.
  • Additional 4 days effort required to complete project this was due to extra effort required during deployment to resolve capacity issue
Next Steps
  • Draft Completion Report
  • Agree Project closure

The project status is AMBER as closure milestone requires to be moved out by 3 weeks due to PM annual leave.

 

 

RIS005  Ethics Tool Procurement

Discretionary / Sponsor Funded

Milestones:

Milestone Due Date
Procurement Complete 15-Jun-2019
Project Closure Complete 30-Jun-2049

RAG Status :

AMBER

 

 

Report by Karen Stirling for May 2019

Achievements in Last Period Draft 
  • Terms and Conditions still being progressed by Procurement and Legal
  • Revised milestones agreed by Project Sponsor
Issues
  •  
  • Remaining milestones have been agreed to be removed and earlier closure date by Project Sponsor however on submission to IS Applications Governance this was not approved as they have asked for review by Senior Supplier and Production Management. As this project does not have a Senior Supplier role the Project Manager will review with Head of Production Management and resubmit revised milestones
  • Concerns around Terms and Conditions timescales to complete and also impact of non development of accessibility requirements by supplier, this has been flagged to Project Sponsor and Procurement Manager
Next Steps
  • Confirmation of Terms and Conditions agreed
  • Completion report

The project status is AMBER this is due to the revised project milestones e.g. earlier closure date not  approved at Internal IS Application review, stating agreement required from Production Management for removing implementation stage of project.

 

 

 

 

 

RIS006 Worktribe Upgrade V3

Compliance / Core Funded

Milestones:

Milestones

Worktribe v3 DSOR Complete 10-Jun-2019
Closure 21-Jun-2019

RAG Status :

GREEN

 

Report by David Watters for May 2019

Achievements to date

  • Acceptance stage signed off
  • Preparations made for go live
  • Upgrade deployed into Live & checks passed

Issues

  • PICCL for (5) extra days submitted and approved

Next Steps

  • Sign off live deployment
  • Project closure

The project status is GREEN

 

 

 

.

RIS007 PURE Upgrades v5.13 to 5.15

Compliance / Core Funded

Milestones:

Milestone Due Date
Upgrade to Pure 5.13.4 DEV Complete 05-Jun-19
Upgrade to Pure 5.13.4 TEST Complete 09-Jul-19
Upgrade to Pure 5.13.4 LIVE Complete 31-Jul-19
Upgrade to Pure 5.13.4 DSOR 14-Aug-19
Upgrade to Pure 5.14 DEV Complete (PLACEHOLDER) 21-Aug-19
Upgrade to Pure 5.14 TEST Complete (PLACEHOLDER) 23-Aug-19
Upgrade to 5.14 LIVE Complete (PLACEHOLDER) 05-Sep-19
Upgrade to 5.14 DSOR Complete (LIVE) (PLACEHOLDER) 12-Sep-19
Upgrade to 5.15 DEV Complete 18-Sep-19
Upgrade to 5.15 TEST Complete 09-Oct-19
Upgrade to 5.15 LIVE Complete 31-Oct-19
Upgrade to 5.15 DSOR Complete (LIVE) 28-Nov-19
Closure 17-Dec-19

RAG Status: 

AMBER

 

Report by Ian Mitchell for May 2019

Achievements in Last Period
  • Milestone and scope changes (GDPR work and Cloud Portal work) approved by WIS 17 May.
  • Re-estimate of project including additional scope item submitted to WIS 31 May .  Additional information in project page (https://secure.projects.ed.ac.uk/project/ris007/status/9).
  • Work in Tomcat upgrade has completed .

Issues

  • Project budget re-estimation yet to be confirmed.
  • Resources yet to be confirmed.  Development Service Resource Co-ordinator asked for update 4 June 2016.

Next Steps 

  • 5.13 DEV upgrade is in progress, due complete 5 June.
  • Thereafter Test platform will be upgraded to 5.13.

The project status is AMBER due to the following:

  • Budget increase requested 31 May due to re-estimation and scope increase (PureINT Interface de-commissioning work).
  • Scope has increased to cover additional work.
  • Resources not yet confirmed.

RIS008 REF2021 Data Requirements Analysis

Discretionary / Sponsor Funded

Milestones:

Milestone Date  
Delivery Business requirements and Options Paper (II) 28-June-2019 No
Closure Review 12-July-2019 No

 

RAG Status : 

GREEN

Report by Tim Gray for May 2019

Achievements in Last Period
  • Business analysis hand over completed 
  • As-Is and To-0Be processes refined with feedback from GaSP
  • Business Requirements progressed
  • The process of refining the ToBe processes, which will include the requirements, is taking longer than expected. A revised plan which includes interactions for this refinement has been agreed. As a result, the project budget and plan has been revised and approved.

Issues

  • The As-Is processes, requirements and revised options paper have not yet been circulated to Core Systems and Enterprise Data Warehouse teams. There is the risk that this could result in considerable discussion and points of view that require more time to clarify.

Next Steps 

  • Progress and complete To Be business processes
  • Business Requirements document to be finalised
  • Revised Options paper produced including revised costings
  • Enterprise Architecture produced

 

The project status remains at GREEN

 

 

 

 

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary
RIS003 Pure Upgrade v5.10 to v5.12

Report by Kim Keenan

Completion Report

This project closed 17th August 2018

 

RIS004 Worktribe Upgrades - Readiness for GDPR

 Report by Kim Keenan

Completion report

This project closed 21st September 2018

AP89-027 GDPR for Pure

Update by Karen Stirling

PICCL

This proposal was withdrawn 29th March 2019

AP89-026 Support for REF

Update by Karen Stirling

PICCL

This proposal was withdrawn 29th March 2019

AP078-29 PURE Research Explorer- replace with new module from Elsevier Update by Karen Stirling

PICCL

This proposal was withdrawn 29th March 2019