Report for April 2019
- Report Date
- April 2019
Report compiled by Karen Stirling, RIS Programme Manager for Dominic Tate (Programme Owner), Damon Querry, Lorna Thomson, Liz Welch, Gary Halliday, Laura Petrie, Pauline Jones, Susan Cooper
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
The Programme Commentary
Overall progress within the Programme is as follows :
- RES069 - Implementation to Live completed 24/04/19, reviewing final activity in lead up to closing project
- RIS005 - Limited involvement, new milestones to be agreed to close project. However concerns that terms and conditions still not concluded
- RIS006 - UAT carried out and new dates agreed for deployment to live
- RIS007 - Project has been run-suspended and new PM allocated
- RIS008 - progressing with an initial options paper circulated to key stakeholders
Discussion around new 'in year' project to cover Worktribe upgrade to v3.1 in advance of new patching process and change freeze restrictions in September, review of budget required to facilitate the commencement of this project.
Please find link to REF2021 Portfolio page.
Overall Programme RAG: AMBER
Forward Look and RAG
Resource Position
Section Two: Projects Not Started
Project Info | Project Manager's Commentary |
N/A | All projects starts, suspended or withdrawn |
Section Three: Projects in Progress
Project Info | Project Manager's Commentary | ||||||||||||||||||||||||||||
RES069 PURE UPGRADE TO NEW PROJECT MODEL Compliance / Core & Sponsor Funded Milestones
RAG Status: GREEN
|
Report by Karen Stirling for April 2019 Activities completed
Issues
Next Steps
The project status is GREEN
|
||||||||||||||||||||||||||||
RIS005 Ethics Tool Procurement Discretionary / Sponsor Funded Milestones:
RAG Status : AMBER
|
Report by Karen Stirling for April 2019 Achievements in Last Period
Issues
Next Steps
The project status is AMBER this is due to the project being over budget, project implementation milestones to be withdrawn and revised closure date agreed.
|
||||||||||||||||||||||||||||
RIS006 Worktribe Upgrade V3 Compliance / Core Funded Milestones: Milestones
RAG Status : AMBER
|
Report by David Watters for April 2019 Achievements to date
Issues
Next Steps
The project status is AMBER due to milestones to be revised
. |
||||||||||||||||||||||||||||
RIS007 PURE Upgrades v5.13 to 5.15 Compliance / Core Funded Milestones:
RAG Status: GREEN |
Report by Ian Mitchell for April 2019 Achievements in Last Period
Issues
Next Steps
The project status is GREEN
|
||||||||||||||||||||||||||||
RIS008 REF2021 Data Requirements Analysis Discretionary / Sponsor Funded Milestones:
RAG Status : AMBER |
Report by Tim Gray for April 2019 Achievements in Last Period
Issues
Next Steps
The project status remains at AMBER due to revised milestones.
|
||||||||||||||||||||||||||||
Other Research projects outwith the RIS programme: This is a research project that is held in the STU programme - now Sponsor funded by RIS programme owner STU252 - Worktribe BI Suite universe- Research Management BI MI Enhancements Discretionary / Sponsor funded Milestones Provisional milestones updated on Projects website, will need updated after re-plan, once scope change approved
RAG Status : SUSPENDED
|
Report by Jamie Thin for April 2019Achievements in Last Period
Issues
Next Steps
This project is Suspended
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
RIS003 Pure Upgrade v5.10 to v5.12 |
Report by Kim Keenan This project closed 17th August 2018
|
RIS004 Worktribe Upgrades - Readiness for GDPR |
Report by Kim Keenan This project closed 21st September 2018 |
AP89-027 GDPR for Pure |
Update by Karen Stirling This proposal was withdrawn 29th March 2019 |
AP89-026 Support for REF |
Update by Karen Stirling This proposal was withdrawn 29th March 2019 |
AP078-29 PURE Research Explorer- replace with new module from Elsevier | Update by Karen Stirling
This proposal was withdrawn 29th March 2019 |
Attachment | Size |
---|---|
![]() | 134.01 KB |
![]() | 91.86 KB |