Report for April 2019

Report Date
April 2019

Report compiled by Karen Stirling, RIS Programme Manager for Dominic Tate  (Programme Owner), Damon Querry, Lorna Thomson, Liz Welch, Gary Halliday, Laura Petrie, Pauline Jones, Susan Cooper

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section One: Programme Commentary, RAG and Resources Update

 

The Programme Commentary

Overall progress within the Programme is as follows :

  • RES069 - Implementation to Live completed 24/04/19, reviewing final activity in lead up to closing project
  • RIS005 - Limited involvement, new milestones to be agreed to close project. However concerns that terms and conditions still not concluded
  • RIS006 - UAT carried out and new dates agreed for deployment to live
  • RIS007 - Project has been run-suspended and new PM allocated
  • RIS008 - progressing with an initial options paper circulated to key stakeholders

Discussion around new  'in year' project to cover Worktribe upgrade to v3.1 in advance of new patching process and change freeze restrictions in September, review of budget required to facilitate the commencement of this project.

 

Please find link to REF2021 Portfolio page.

 

Overall Programme RAG: AMBER

 

Forward Look and RAG

 

 

Resource Position

 

 

 

 Section Two: Projects Not Started

Project Info Project Manager's Commentary
N/A All projects starts, suspended or withdrawn

 

Section Three: Projects in Progress

 

Project Info Project Manager's Commentary

RES069 PURE UPGRADE TO NEW PROJECT MODEL

Compliance / Core & Sponsor Funded

Milestones

Milestone Due Date
DSOR 5.12.4 & UPM Complete 03-May-2019
Closure 17-May-2019

RAG Status:  GREEN

 

 

Report by Karen Stirling for April 2019

Activities completed
  • Web Services sign off achieved for  UAT
  • Acceptance sign off for deployment to Live
  • Go CAB approval given
  • Live deployment preparations completed, including Service Alert, Implementation plan and deployment resource confirmed, also 3rd party supplier support for weekend implementation
  • Revised milestones and additional budget approved
  • Deployment of UPM and 5.12.4 to Live completed and signed off on 24th April following successful run of Award and Project Synch overnight jobs

Issues

  • RIS Programme Manager has stepped into project manager role assisting with preparations in advance of implementation and during Live deployment
  • During implementation all activities were completed successfully until final 2 steps of plan - Award and Projects syncs. As we required development resource to investigate we delayed final activity until Monday morning to investigate. Issue was due to lack of space in database to update tables. Restore of database following update of additional capacity and rerun of steps allowed the implementation to complete late Monday and syncs jobs were allowed to run overnight.
Next Steps
  • Complete final production handover activities 
  • Review of remaining JIRAs and re- allocation where required to RIS007
  • Deployment Sign off review
  • Completion Report

The project status is GREEN

 

 

RIS005  Ethics Tool Procurement

Discretionary / Sponsor Funded

Milestones:

Milestone Due Date
Procurement Complete 29-Mar-2019
Build & Configure Complete (DEV) to be withdrawn
Acceptance Complete (TEST) to be withdrawn
Deployment Complete to be withdrawn
DSOR to be withdrawn
Project Closure Complete TBC

RAG Status : AMBER

 

 

Report by Karen Stirling for April 2019

Achievements in Last Period
  • Terms and Conditions being progressed 
  • Feedback from suppliers regarding accessibility changes
Issues
  • Limited activity on project due to PM on sick leave and Programme Manager aligned to other priority RIS projects
  • Project Sponsor confirmed no requirement for PM for implementation therefore project will commence closure activity
  • Single sign on to be managed via UNIDESK request once supplier provides details
  • Remaining milestones will be withdrawn and new closure date agreed
  • Concerns around Terms and Conditions timescales to complete and also impact of non development of accessibility requirements by supplier
Next Steps
  • Confirmation of Terms and Conditions agreed
  • Completion report

The project status is AMBER this is due to the project being over budget, project implementation milestones to be withdrawn and revised closure date agreed.

 

 

 

RIS006 Worktribe Upgrade V3

Compliance / Core Funded

Milestones:

Milestones

Worktribe Upgrade v3 Complete in LIVE 15-May-2019
Worktribe v3 DSOR Complete 28-May-2019
Closure 21-Jun-2019

RAG Status : AMBER

 

Report by David Watters for April 2019

Achievements to date

  • Test Plans finalised
  • UAT  carried out

Issues

  • Outstanding milestones to be agreed
  • PICCL to be drafted to change the milestones to incorporate date changes

Next Steps

  • Preparations for deployment to LIVE
  • Go Live for upgrades
  • Project closure

The project status is AMBER due to milestones to be revised

 

 

.

RIS007 PURE Upgrades v5.13 to 5.15

Compliance / Core Funded

Milestones:

Milestone Due Date
Upgrade to Pure 5.13.4 DEV Complete 28-May-2019
Upgrade to Pure 5.13.4 TEST Complete 09-Jul-2019
Upgrade to Pure 5.13.4 DSOR 08-Aug-2019
Upgrade to Pure 5.13.4 LIVE Complete 08-Aug-2019
Upgrade to Pure 5.14 DEV Complete 21-Aug-2019
Upgrade to Pure 5.14 TEST Complete 10-Sep-2019
Upgrade to 5.14 DSOR Complete (LIVE) 07-Oct-2019
Upgrade to 5.14 LIVE Complete 07-Oct-2019
Upgrade to 5.15 DEV Complete 23-Oct-2019
Upgrade to 5.15 TEST Complete 13-Nov-2019
Upgrade to 5.15 DSOR Complete (LIVE) 10-Dec-2019
Upgrade to 5.15 LIVE Complete 10-Dec-2019
Closure 17-Dec-2019

 

RAG Status: 

GREEN

Report by Ian Mitchell for  April 2019

Achievements in Last Period
  • Project unsuspended and planning resumed following RES069 completion.
  • Initial meeting held with Damon Querry.

 

Issues
  • No major issues

 

Next Steps 
  • Project team meeting scheduled 10 May to determine next steps.

 

The project status is GREEN

 

 

 

 

 

RIS008 REF2021 Data Requirements Analysis

Discretionary / Sponsor Funded

Milestones:

Milestone Date  
Enterprise Architecutre Document 22-Mar-2019 Withdrawn
Options Paper Complete 22-Mar-2019 Yes
Delivery Business requirements and Options Paper (II) 17-May-2019 No
Closure Review 31-May-2019 No

 

RAG Status : AMBER

Report by Tim Gray for April  2019

Achievements in Last Period
  • New Project Manager has taken over
  • Milestones replanned
  • Enterprise Architecture in progress
  • Initial Options Paper drafted and circulated to key stakeholders
  • As is processed documented and shared with the project team

Issues

  • With the delays due to sickness, the project is playing catch up. 
  • The business analyst is going on leave then fully booked on other work, so a new BA will pick up this work next month

Next Steps 

  • Business analysis to be handed over due to annual leave
  • To Be business processes to be defined and documented
  • Business Requirements Document to be finalised
  • Revised Options paper produced
  • Enterprise Architecture produced
  • Revised costing of options

The project status remains at AMBER due to revised milestones.

 

 

 

 

Other Research projects outwith the RIS programme:

This is a research project that is held in the STU programme - now Sponsor funded by RIS programme owner

STU252 - Worktribe BI Suite universe- Research Management BI MI Enhancements 

Discretionary / Sponsor funded

Milestones

Provisional  milestones updated on Projects website, will need updated after re-plan, once scope change approved

Target Date Title
   

RAG Status : SUSPENDED

 

 

Report by Jamie Thin for April 2019
 
Achievements in Last Period
  • Project currently suspended
  • Closure/withdrawal meeting held in March to agree project closure
Issues
  • Project manager working on SEP priority project, therefore, delay in closing project
  • Application Management requested that final tidy up activity be undertaking e.g. TAD prior to closure
Next Steps 
  • Project will be withdrawn in due course during April 2019

This project is Suspended

 

 

 

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary
RIS003 Pure Upgrade v5.10 to v5.12

Report by Kim Keenan

Completion Report

This project closed 17th August 2018

 

RIS004 Worktribe Upgrades - Readiness for GDPR

 Report by Kim Keenan

Completion report

This project closed 21st September 2018

AP89-027 GDPR for Pure

Update by Karen Stirling

PICCL

This proposal was withdrawn 29th March 2019

AP89-026 Support for REF

Update by Karen Stirling

PICCL

This proposal was withdrawn 29th March 2019

AP078-29 PURE Research Explorer- replace with new module from Elsevier Update by Karen Stirling

PICCL

This proposal was withdrawn 29th March 2019

Documentation

Not available.