Report for March 2019
- Report Date
- March 2019
Report compiled by Karen Stirling, RIS Programme Manager for Dominic Tate (Programme Owner), Damon Querry, Lorna Thomson, Liz Welch, Gary Halliday, Laura Petrie, Pauline Jones, Susan Cooper
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
The Programme Commentary
Overall progress within the Programme is as follows :
- RES069 - UAT signed off with exception of Web Services expected 8/04/19, preparations underway for deployment to Live being planned for weekend 19/21 April.
- RIS005 - Contract Awarded, terms and conditions being formalised
- RIS006 - Organising user acceptance testing and revising milestones for project deployment to live early May
- RIS007 - Project currently suspended, expecting this to be restarted mid April. Implications on budget for next financial year will be reviewed on reinstatement of project.
- RIS008 - Progress in producing documentation, early sight of draft options paper to aid discussions around funding for implementation project
All projects have been impacted due to the unavailability of assigned project manager who has been on leave (annual and sick) leave since 8th March, the current projects have been allocated to other project managers in the interim until return date has been confirmed, please note these projects are in addition to their own current workload. Options for resourcing are being explored by RIS Programme Manager and ISG Portfolio Manager
- RIS006 - David Watters
- RIS008 - Tim Gray
- RES069 / RIS005 - Karen Stirling
Due to the issues with resourcing the programme currently has an AMBER status
Please find link to REF2021 Portfolio page.
Overall Programme RAG: AMBER
Forward Look and RAG
Resource Position
Section Two: Projects Not Started
Project Info | Project Manager's Commentary |
N/A | All projects starts, suspended or withdrawn |
Section Three: Projects in Progress
Project Info | Project Manager's Commentary | ||||||||||||||||||||||||||||
RES069 PURE UPGRADE TO NEW PROJECT MODEL Compliance / Core & Sponsor Funded Milestones
RAG Status: AMBER
|
Report by Karen Stirling for March 2019 Activities completed
Issues
Next Steps
The project status is AMBER due to milestones and budgets being reviewed and implementation date being revised to mid April.
|
||||||||||||||||||||||||||||
RIS005 Ethics Tool Procurement Discretionary / Sponsor Funded Milestones:
RAG Status : AMBER
|
Report by Karen Stirling for March 2019 Achievements in Last Period
Issues
Next Steps
The project status is AMBER this is due to the project being over budget and milestones to be reviewed and aligned with PM resource requirements |
||||||||||||||||||||||||||||
RIS006 Worktribe Upgrade V3 Compliance / Core Funded Milestones:
RAG Status : AMBER
|
Report by David Watters for March 2019 Achievements to date
Issues
Next Steps
The project status is AMBER - User testing delay in starting due to PM unavailable, milestones to be updated. |
||||||||||||||||||||||||||||
RIS007 PURE Upgrades v5.13 to 5.15 Compliance / Core Funded Milestones:
RAG Status: SUSPENDED
|
Report by Karen Stirling for March 2019 Achievements in Last Period
Issues
Next Steps
The project status is SUSPENDED until mid April 19
|
||||||||||||||||||||||||||||
RIS008 REF2021 Data Requirements Analysis Discretionary / Sponsor Funded Milestones:
RAG Status : AMBER |
Report by Karen Stirling for March 2019 Achievements in Last Period
Issues
Next Steps
The project status is AMBER due to limited project resource available during March, and milestones require to be reviewed and approved.
|
||||||||||||||||||||||||||||
Other Research projects outwith the RIS programme: This is a research project that is held in the STU programme - now Sponsor funded by RIS programme owner STU252 - Worktribe BI Suite universe- Research Management BI MI Enhancements Discretionary / Sponsor funded Milestones Provisional milestones updated on Projects website, will need updated after re-plan, once scope change approved
RAG Status : SUSPENDED
|
Report by Jamie Thin for March 2019Achievements in Last Period
Issues
Next Steps
This project is Suspended
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
RIS003 Pure Upgrade v5.10 to v5.12 |
Report by Kim Keenan This project closed 17th August 2018
|
RIS004 Worktribe Upgrades - Readiness for GDPR |
Report by Kim Keenan This project closed 21st September 2018 |
AP89-027 GDPR for Pure |
Update by Karen Stirling This proposal was withdrawn 29th March 2019 |
AP89-026 Support for REF |
Update by Karen Stirling This proposal was withdrawn 29th March 2019 |
AP078-29 PURE Research Explorer- replace with new module from Elsevier | Update by Karen Stirling
This proposal was withdrawn 29th March 2019 |