Report for February 2019
- Report Date
- February 2019
Report compiled by Karen Stirling, RIS Programme Manager for Dominic Tate (Programme Owner), Damon Querry, Lorna Thomson, Liz Welch, Gary Halliday, Laura Petrie, Pauline Jones, Susan Cooper
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
The Programme Commentary
Overall progress within the Programme is as follows :
- RES069 - Upgrade of model now in test environment and awaiting testing of 5.12.4, concerns that business resource may not be able to test and deployment to live therefore may have to move out and will have a knock on effect to RIS007 being unsuspended as currently scheduled until mid April 2019
- RIS005 - ITT evaluation period has now completed and contract award pending, additional funding may be required to cover PM resource once full implementation plan is produced and an agreed date confirmed.
- RIS006 - Progressing however some concerns around availability of testing resource due to commitments to Core Systems workshops therefore milestones may have to move
- RIS007 - This project is now suspended until mid April 2019 as it has a dependency on RES069 delivering new project model to Live
- RIS008 - project brief approved and analysis is underway however concerns around BA resource as currently on sick leave, review potential alternative options
Please find link to REF2021 Portfolio page.
AP89-027 GDPR for Pure project - agreed at previous Programme review that we will initiated this project however will review proposal document for any further information to be included to aid planning
Discussion underway around Pure Cloud Portal.
Overall Programme RAG: AMBER
Forward Look and RAG
Resource Position
Section Two: Projects Not Started
Project Info | Project Manager's Commentary |
AP078-29 PURE Research Explorer- replace with new module from Elsevier | Project not started yet, earliest start date would be March 2019 |
AP89-026 Support for REF | proposed at last Programme meeting to request placing this project and budget into 19/20 |
AP89-027 GDPR for Pure | Project not started yet, possible start date March 2019 |
Section Three: Projects in Progress
Project Info | Project Manager's Commentary | ||||||||||||||||||||||||||||
RES069 PURE UPGRADE TO NEW PROJECT MODEL Compliance / Core & Sponsor Funded Milestones
RAG Status: AMBER
|
Report by Kim Keenan for February 2019 Activities completed
Issues
Next Steps
The project status is AMBER on the basis that the business have not agreed a Go Live date and testing has not commenced yet.
|
||||||||||||||||||||||||||||
RIS005 Ethics Tool Procurement Discretionary / Sponsor Funded Milestones:
RAG Status : AMBER
|
Report by Kim Keenan for February 2019 Achievements in Last Period
Issues
Next Steps
The project status is AMBER this is due to the project being over budget, the original estimate was 50 days however this is now looking at 63 days which needs to be discussed with the Project Sponsor. |
||||||||||||||||||||||||||||
RIS006 Worktribe Upgrade V3 Compliance / Core Funded Milestones:
RAG Status : AMBER
|
Report by Kim Keenan for February 2019 Achievements in Last Period
Issues
Next Steps
The project status is AMBER - UAT has still to be completed and date for upgrade to Live to be agreed |
||||||||||||||||||||||||||||
RIS007 PURE Upgrades v5.13 to 5.15 Compliance / Core Funded Milestones:
RAG Status: SUSPENDED
|
Report by Kim Keenan for February 2019 Achievements in Last Period
Issues
Next Steps
The project status is SUSPENDED until mid April 19
|
||||||||||||||||||||||||||||
RIS008 REF2021 Data Requirements Analysis Discretionary / Sponsor Funded Milestones:
RAG Status : GREEN |
Report by Kim Keenan for February 2019 Achievements in Last Period
Issues
Next Steps
The project status is GREEN
|
||||||||||||||||||||||||||||
Other Research projects outwith the RIS programme: This is a research project that is held in the STU programme - now Sponsor funded by RIS programme owner STU252 - Worktribe BI Suite universe- Research Management BI MI Enhancements Discretionary / Sponsor funded Milestones Provisional milestones updated on Projects website, will need updated after re-plan, once scope change approved
RAG Status : SUSPENDED
|
Report by Jamie Thin for February 2019Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
RIS003 Pure Upgrade v5.10 to v5.12 |
Report by Kim Keenan This project closed 17th August 2018
|
RIS004 Worktribe Upgrades - Readiness for GDPR |
Report by Kim Keenan This project closed 21st September 2018 |
Attachment | Size |
---|---|
![]() | 107.93 KB |
![]() | 139.41 KB |