Report for January 2019
- Report Date
- January 2019
Report compiled by Karen Stirling, RIS Programme Manager for Dominic Tate (Programme Owner), Damon Querry, Lorna Thomson, Liz Welch, Gary Halliday, Laura Petrie, Pauline Jones, Susan Cooper
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Programme Commentary
Overall RIS programme is progressing with the following projects : -
- RES069 - Developer resource engaged to complete outstanding priority JIRAs, agreement to move into Test environment, budget for additional days in progress
- RIS005 - ITT being evaluated by project team
- RIS006 - progressing to plan
- RIS007 - Project brief delayed due to revised plan for RES069, however project brief now completed and being submitted for approval, suspend for 2 months whilst activity focuses on RES069
- RIS008 - Planning milestone reviewed and re-planned due to festive break, workshops held and more in progress to gather business requirements
Other activity running alongside projects is engagement from Core Systems team, meeting held to discuss potential impacts of changes to Org Hierarchy. Programme team have highlighted the risk of RIS projects, REF 2021 preparations and impacts emerging from Core Systems that this will have a high impact on RIS team resources.
Please find link to REF2021 Portfolio page.
AP89-027 GDPR for Pure project - establish if this project is ready to start and what the scope and requirements are aligned to this.
Overall Programme RAG: GREEN
Forward Look and RAG
Resource Position
Section Two: Projects Not Started
Project Info | Project Manager's Commentary |
AP078-29 PURE Research Explorer- replace with new module from Elsevier | Project not started yet, earliest start date would be March 2019 |
AP89-026 Support for REF | Project not started yet |
AP89-027 GDPR for Pure | Project not started yet, possible start date March 2019 |
Section Three: Projects in Progress
Project Info | Project Manager's Commentary | ||||||||||||||||||||||||||||||
RES069 PURE UPGRADE TO NEW PROJECT MODEL Compliance / Core & Sponsor Funded Milestones
RAG Status: AMBER
|
Report by Kim Keenan for January 2019 Activities completed
Issues There is one key issue to report at this stage:
Next Steps
The project status is AMBER
|
||||||||||||||||||||||||||||||
RIS005 Ethics Tool Procurement Discretionary / Sponsor Funded Milestones:
RAG Status : GREEN
|
Report by Kim Keenan for January 2019 Achievements in Last Period
IssuesThere are no issues to report at this stage Next Steps
The project status is GREEN |
||||||||||||||||||||||||||||||
RIS006 Worktribe Upgrade V3 Compliance / Core Funded Milestones:
RAG Status : GREEN
|
Report by Kim Keenan for January 2019 Achievements in Last Period
IssuesThere are no issues to report at this stage Next Steps
The project status is GREEN |
||||||||||||||||||||||||||||||
RIS007 PURE Upgrades v5.13 to 5.15 Compliance / Core Funded Milestones:
RAG Status: AMBER
|
Report by Kim Keenan for January 2019 Achievements in Last Period
Issues
Next Steps
The project status is AMBER
RAG Commentary There is a dependency upon the delivery of RES069 and confirmation of budget for 2019/2020 needs confirmation to proceed with the remaining upgrades.
|
||||||||||||||||||||||||||||||
RIS008 REF2021 Data Requirements Analysis Discretionary / Sponsor Funded Milestones:
RAG Status : AMBER
|
Report by Kim Keenan for January 2019 Achievements in Last Period
Issues There is one issue to report at this stage: PICCL 2: End of Planning Milestone not achieved due to festive period and securing time with all the key project team to have a project start up meeting. Next Steps
The project status is AMBER RAG Commentary End of planning milestone needs to be revised due to Business Requirements being extended
|
||||||||||||||||||||||||||||||
Other Research projects outwith the RIS programme: This is a research project that is held in the STU programme - now Sponsor funded by RIS programme owner STU252 - Worktribe BI Suite universe- Research Management BI MI Enhancements Discretionary / Sponsor funded Milestones Provisional milestones updated on Projects website, will need updated after re-plan, once scope change approved
RAG Status : SUSPENDED
|
Report by Jamie Thin for January 2019Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
RIS003 Pure Upgrade v5.10 to v5.12 |
Report by Kim Keenan This project closed 17th August 2018
|
RIS004 Worktribe Upgrades - Readiness for GDPR |
Report by Kim Keenan This project closed 21st September 2018 |
Attachment | Size |
---|---|
![]() | 191.94 KB |
![]() | 114.03 KB |