Report for January 2019

Report Date
January 2019

Report compiled by Karen Stirling, RIS Programme Manager for Dominic Tate  (Programme Owner), Damon Querry, Lorna Thomson, Liz Welch, Gary Halliday, Laura Petrie, Pauline Jones, Susan Cooper

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section One: Programme Commentary, RAG and Resources Update

 

Programme Commentary

Overall RIS programme is progressing  with the following  projects : -

  • RES069 - Developer resource engaged to complete outstanding priority JIRAs, agreement to move into Test environment, budget for additional days in progress
  • RIS005 - ITT being evaluated by project team
  • RIS006 - progressing to plan
  • RIS007 - Project brief delayed due to revised plan for RES069, however project brief now completed and being submitted for approval, suspend for 2 months whilst activity focuses on RES069
  • RIS008 - Planning milestone reviewed and re-planned due to festive break, workshops held and more in progress to gather business requirements

 

Other activity running alongside projects is engagement from Core Systems team, meeting held to discuss potential impacts of changes to Org Hierarchy. Programme team have highlighted the risk of RIS projects, REF 2021 preparations and impacts emerging from Core Systems that this will have a high impact on RIS team resources.

Please find link to REF2021 Portfolio page.

AP89-027 GDPR for Pure project - establish if this project is ready to start and what the scope and requirements are aligned to this.

 

Overall Programme RAG: GREEN

 

Forward Look and RAG

 

 

Resource Position

 

 

 

 

 

 Section Two: Projects Not Started

Project Info Project Manager's Commentary
AP078-29 PURE Research Explorer- replace with new module from Elsevier Project not started yet, earliest start date would be March 2019
AP89-026 Support for REF Project not started yet
AP89-027 GDPR for Pure Project not started yet, possible start date March 2019

 

Section Three: Projects in Progress

 

Project Info Project Manager's Commentary

RES069 PURE UPGRADE TO NEW PROJECT MODEL

Compliance / Core & Sponsor Funded

Milestones

Milestone Due Date
PURE V5.12.4 & UPM Complete (DEV) 01-02-2019
Integration - Upgrade to Pure v5.12.4 & UPM Complete (TEST) 21-02-2019
Upgrade to PURE 5.12.4 & UPM Complete (LIVE) 08-03-2019
DSOR 5.12.4 & UPM Complete 22-03-2019
Closure 12-04-2019

 

RAG Status:  AMBER

 

 

Report by Kim Keenan for January 2019

Activities completed
  • Outstanding JIRA's have been investigated and further testing is to be finalised
  • Agreement was made to progress into TEST environment to conduct full rollback and test of implementation plans

Issues

 There is one key issue to report at this stage:

  • Project Issue 20 raised to confirm resource conflict and approval of revised milestones and adjusted budget days within the project
Next Steps
  • Upgrade TEST to 5.12.4 including UPM and conversion jobs
  • Review implementation plan
  • Undertake UAT of the UPM
  • Submit PICCL 20 to the business and WIS for approval

The project status is AMBER

RAG Commentary
 
The effort for re-development was underestimated which has impacted the timescales and cost for the project.

 

 

 

 

RIS005  Ethics Tool Procurement

Discretionary / Sponsor Funded

Milestones:

Milestone Due Date
ITT Evaluation Complete 01-Mar-2019
Procurement Complete 29-Mar-2019
Build & Configure Complete (DEV) 16-Jul-2019
Acceptance Complete (TEST) 27-Aug-2019
Deployment Complete 05-Sep-2019
DSOR 19-Sep-2019
Project Closure Complete 17-Oct-2019

RAG Status : GREEN

 

 

Report by Kim Keenan for January 2019

Achievements in Last Period
  • ITT was published to the market and clarification questions answered from potential vendors

  • Tender responses received and issued to evaluation team

Issues

There are no issues to report at this stage

Next Steps
  • System Demonstration workshops set up for February 2019
  • Consensus meeting scheduled for February 2019
  • Award contract

The project status is GREEN

RIS006 Worktribe Upgrade V3

Compliance / Core Funded

Milestones:

Milestone Due Date
Integration - Worktribe TEST upgraded to v3 (ASOR) Complete 01-Mar-2019
Worktribe Upgrade v3 Complete in LIVE 12-Mar-2019
Worktribe v3 DSOR Complete 26-Mar-2019
Closure 04-Apr-2019

RAG Status : GREEN

 

 

Report by Kim Keenan for January 2019

Achievements in Last Period
  • WT TEST environment upgraded to v3

  • PICCL 5 approved at WIS for revised timescales

Issues

There are no issues to report at this stage

Next Steps 
  • Test Plan Developed
  • UAT commences
  • Revised project plan to be issued
  • PICCL to be presented to WIS for approval

 

The project status is GREEN

RIS007 PURE Upgrades v5.13 to 5.15

Compliance / Core Funded

Milestones:

Milestone Due Date
End of Planning 31-Jan-2019
Upgrade to Pure 5.13.4 DEV Complete 28-May-2019
Upgrade to Pure 5.13.4 TEST Complete 09-Jul-2019
Upgrade to Pure 5.13.4 DSOR 08-Aug-2019
Upgrade to Pure 5.13.4 LIVE Complete 08-Aug-2019
Upgrade to Pure 5.14 DEV Complete 21-Aug-2019
Upgrade to Pure 5.14 TEST Complete 10-Sep-2019
Upgrade to 5.14 DSOR Complete (LIVE) 07-Oct-2019
Upgrade to 5.14 LIVE Complete 07-Oct-2019
Upgrade to 5.15 DEV Complete 23-Oct-2019
Upgrade to 5.15 TEST Complete 13-Nov-2019
Upgrade to 5.15 DSOR Complete (LIVE) 10-Dec-2019
Upgrade to 5.15 LIVE Complete 10-Dec-2019
Closure 17-Dec-2019

 

RAG Status: AMBER

 

Report by Kim Keenan for January 2019

Achievements in Last Period
  • Project Brief has been approved by the stakeholders
Issues
  • There are no issues to report at this stage.
Next Steps 
  • Present Project Brief to WIS and Business for approval
  • Project plan revised accordingly in line with RES069 timescales
  • Project Team established

 

The project status is AMBER

 

RAG Commentary

There is a dependency upon the delivery of RES069 and confirmation of budget for 2019/2020 needs confirmation to proceed with the remaining upgrades.

 

 

RIS008 REF2021 Data Requirements Analysis

Discretionary / Sponsor Funded

Milestones:

 

Milestone Due Date
End of Planning 15-Feb-2019
Project Closure Complete 15-Apr-2019

RAG Status : AMBER

 

Report by Kim Keenan for January 2019

Achievements in Last Period
  • Business meeting held to determine their initial business requirements
  • Data has begun on hte

 

Issues

There is one issue to report at this stage:

PICCL 2: End of Planning Milestone not achieved due to festive period and securing time with all the key project team to have a project start up meeting.

Next Steps 

  • Business Analyst and Enterprise Architect to meet with the business to determine requirements
  • PICCL presented to Business and WIS for approval on revised dates
  • Project Brief approved.
  • Business Analysis continues in documenting

 

The project status is AMBER

RAG Commentary

End of planning milestone needs to be revised due to Business Requirements being extended

 

Other Research projects outwith the RIS programme:

This is a research project that is held in the STU programme - now Sponsor funded by RIS programme owner

STU252 - Worktribe BI Suite universe- Research Management BI MI Enhancements 

Discretionary / Sponsor funded

Milestones

Provisional  milestones updated on Projects website, will need updated after re-plan, once scope change approved

Target Date Title
   

RAG Status : SUSPENDED

 

 

Report by Jamie Thin for January 2019
 
Achievements in Last Period
  • Project currently suspended
Issues
  • Project manager working on SEP priority project therefore delay in withdrawing project
Next Steps 
  • Report to be completed to document lessons learned and feedback for data into Data Warehouse
  • Project will be withdrawn in due course during February 2019
 

 

 

 

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary
RIS003 Pure Upgrade v5.10 to v5.12

Report by Kim Keenan

Completion Report

This project closed 17th August 2018

 

RIS004 Worktribe Upgrades - Readiness for GDPR

 Report by Kim Keenan

Completion report

This project closed 21st September 2018