Report for December 2018

Report Date
December 2018

Report compiled by Karen Stirling, RIS Programme Manager for Dominic Tate  (Programme Owner), Damon Querry, Lorna Thomson, Liz Welch, Gary Halliday, Laura Petrie, Pauline Jones, Susan Cooper

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section One: Programme Commentary, RAG and Resources Update

 

Programme Commentary

Overall RIS programme is progressing  with the following  projects : -

  • RES069 - PURE Upgrade to New Project Model - resource conflict has been resolved and JIRAs prioritised, however budget remains an issue and additional day to be approved.
  • RIS005 - Ethics Tool Procurement - ITT in progress with clarifications been reviewed and responded to
  • RIS006 - Worktribe Upgrade v3 - hotfix deployed and updates to v3 being planned for January for Dev and Test
  • RIS007 - Pure Upgrades v5.13 to v5.15 - high dependency on RES069 and potential for project to be suspended until March 2019
  • RIS008 - REF2021 Data Requirements Analysis - project has started with initial workshops arranged for January

Fixed Term Project Manager has been confirmed with a start of date of 10th January 2019. Kim Keenan will continue in role for 2 year fixed period therefore no handover process required, allowing project to continue under current arrangements.

The key project for project team to concentrate on delivery is RES069, regular meetings arranged with Programme manager, Project manager, Business lead and Senior Supplier in progress to flag up concerns , risks and issues to help progress project to delivery.

Please find link to REF2021 Portfolio page.

 

Overall Programme RAG: GREEN

 

Forward Look and RAG

 

 

Resource Position

 

 

 

 

 

 Section Two: Projects Not Started

Project Info Project Manager's Commentary
AP078-29 PURE Research Explorer- replace with new module from Elsevier Project not started yet, earliest start date would be March 2019
AP89-026 Support for REF Project not started yet
AP89-027 GDPR for Pure Project not started yet, possible start date February 2019

 

Section Three: Projects in Progress

 

Project Info Project Manager's Commentary

RES069 PURE UPGRADE TO NEW PROJECT MODEL

Compliance / Core & Sponsor Funded

Milestones

Milestone Due Date
PURE V5.12.4 & UPM Complete (DEV) 01-02-2019
Integration - Upgrade to Pure v5.12.4 & UPM Complete (TEST) 21-02-2019
Upgrade to PURE 5.12.4 & UPM Complete (LIVE) 08-03-2019
DSOR 5.12.4 & UPM Complete 22-03-2019
Closure 12-04-2019

 

RAG Status:  AMBER

 

 

Report by Kim Keenan for December 2018

Activities completed
  • Outstanding JIRA's have been prioritised accordingly
  • Resource conflict agreement gained for Software Development and Dev Technology resource presented to WIS
  • Revised milestone agreed following prioritisation of outstanding JIRAs
  • Project Plan has been revised accordingly

Issues

There are key issue to report at this stage:
  • Project Issue 20 raised to confirm resource conflict and approval of revised milestones and adjusted budget days
Next Steps
  • Complete Development work
  • Complete testing on fixed JIRA's
  • Revise deployment plan
  • Secure DEV Tec resource to deploy the UPM into DEV

The project status is AMBER

RAG Commentary
Resource conflict agreed and developer resource allocated to prioritised JIRAs. Project milestones have been agreed by project team and additional funding being approved. With resource secured the project team expect to deliver the project in March 2019 which will allow the next Pure Upgrade (RIS007) to complete as planned without impacting on REF timelines.

 

 

 

 

RIS005  Ethics Tool Procurement

Discretionary / Sponsor Funded

Milestones:

Milestone Due Date
ITT Responses returned 25-Jan-2019
ITT Evaluation Complete 01-Mar-2019
Procurement Complete 29-Mar-2019
Build & Configure Complete (DEV) 16-Jul-2019
Acceptance Complete (TEST) 27-Aug-2019
Deployment Complete 05-Sep-2019
DSOR 19-Sep-2019
Project Closure Complete 17-Oct-2019

RAG Status : GREEN

 

 

Report by Kim Keenan for December 2018

Achievements in Last Period
  • Evaluation team have been establised and meetings have been set up for evaluation

  • Supplier Demonstrations have been scheduled with the business and the potental vendors have been advised of these dates

  • Clarification questions have been received and responded by the business

 

Issues

There are no issues to report at this stage

Next Steps
  • Respond to any clarification questions that may be submitted
  • ITT Evaluation workshops set up for January
  • System Demonstration workshops set up for January

The project status is GREEN

RIS006 Worktribe Upgrade V3

Compliance / Core Funded

Milestones:

Milestone Due Date
Integration - Worktribe TEST upgraded to v3 (ASOR) Complete 01-Mar-2019
Worktribe Upgrade v3 Complete in LIVE 12-Mar-2019
Worktribe v3 DSOR Complete 26-Mar-2019
Closure 04-Apr-2019

RAG Status : GREEN

 

 

Report by Kim Keenan for December 2018

Achievements in Last Period
  • Hotfix 2.3.491 has been signed off (not within the scope of this project however it was a dependency prior to progressing with the version 3 upgrade)

  • WT Dev environment upgraded to v3

Issues

There are no issues to report at this stage.

Next Steps 

  • Worktribe v3 upgraded into TEST
  • Test Plan Developed
  • UAT commences
  • Revised project plan to be issued
  • PICCL to be presented to WIS for approval

The project status is GREEN

RIS007 PURE Upgrades v5.13 to 5.15

Compliance / Core Funded

Milestones:

Milestone Due Date
End of Planning 23-Nov-2018
Closure 26-Apr-2019

RAG Status: AMBER

 

Report by Kim Keenan for December 2018

Achievements in Last Period
  • Project Brief has been drafted but not circluated to delays with a dependency project RES069; the timescales cannot be defined whilst awaiting on the UPM progressing through all environments

  • The project team are aware of this and have been establised.

Issues

There is one issue to report at this stage:

PICCL 1: End of Planning Milestone not achieved and potential suspension of project until RES069 is completed.

Next Steps 
  • PICCL to be presented to WIS and the business with a view to suspend the project until RES069 is complete; estimated at least two months
  • RES069 is complete and PURE environments are available to upgrade
  • Project brief approved
  • Project Team established

The project status is AMBER:

 

RAG Commentary

There is a dependency upon the delivery of the UPM (RES069) prior to commencing future upgrades.  Until we have deployed the UPM throughout all environments, all environments are unavailable to begin the next upgrades.

 

RIS008 REF2021 Data Requirements Analysis

Discretionary / Sponsor Funded

Milestones:

Milestone Due Date
End of Planning 15-Dec-2019
Project Closure Complete 15-Apr-2019

RAG Status : AMBER

 

Report by Kim Keenan for December 2018

Achievements in Last Period
  • Project team has been established including Project Sponsor

  • Business Analyst has been assigned to the project

  • Enterprise Architect has been assigned to the project

Issues

There is one issue to report at this stage:

PICCL 1 : End of Planning Milestone not achieved due to key personnel being on annual leave for the festive period

Next Steps 

  • PICCL presented to Business and WIS for approval on revised dates
  • Project Brief approved.
  • Business Analysis commences
  • Initial Business Requirements Workshop scheduled for 14th January 2019

The project status is AMBER

RAG Commentary

The end of planning milestone has not been met due to annual leave commitments over the festive period however full plan including resourcing will be vaiid at next reporting period and the first Business Requirements workshop has been scheduled for 14th January 2019

 

Other Research projects outwith the RIS programme:

This is a research project that is held in the STU programme - now Sponsor funded by RIS programme owner

STU252 - Worktribe BI Suite universe- Research Management BI MI Enhancements 

Discretionary / Sponsor funded

Milestones

Provisional  milestones updated on Projects website, will need updated after re-plan, once scope change approved

Target Date Title
   

RAG Status : SUSPENDED

 

 

Report by Jamie Thin for December 2018
 
Achievements in Last Period
  • Project currently suspended
Issues
Next Steps 
  • Project will be withdrawn in due course during January 2019
  • The required documentation will be completed to allow project to be closed
 

 

 

 

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary
RIS003 Pure Upgrade v5.10 to v5.12

Report by Kim Keenan

Completion Report

This project closed 17th August 2018

 

RIS004 Worktribe Upgrades - Readiness for GDPR

 Report by Kim Keenan

Completion report

This project closed 21st September 2018