Report for December 2018
- Report Date
- December 2018
Report compiled by Karen Stirling, RIS Programme Manager for Dominic Tate (Programme Owner), Damon Querry, Lorna Thomson, Liz Welch, Gary Halliday, Laura Petrie, Pauline Jones, Susan Cooper
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Programme Commentary
Overall RIS programme is progressing with the following projects : -
- RES069 - PURE Upgrade to New Project Model - resource conflict has been resolved and JIRAs prioritised, however budget remains an issue and additional day to be approved.
- RIS005 - Ethics Tool Procurement - ITT in progress with clarifications been reviewed and responded to
- RIS006 - Worktribe Upgrade v3 - hotfix deployed and updates to v3 being planned for January for Dev and Test
- RIS007 - Pure Upgrades v5.13 to v5.15 - high dependency on RES069 and potential for project to be suspended until March 2019
- RIS008 - REF2021 Data Requirements Analysis - project has started with initial workshops arranged for January
Fixed Term Project Manager has been confirmed with a start of date of 10th January 2019. Kim Keenan will continue in role for 2 year fixed period therefore no handover process required, allowing project to continue under current arrangements.
The key project for project team to concentrate on delivery is RES069, regular meetings arranged with Programme manager, Project manager, Business lead and Senior Supplier in progress to flag up concerns , risks and issues to help progress project to delivery.
Please find link to REF2021 Portfolio page.
Overall Programme RAG: GREEN
Forward Look and RAG
Resource Position
Section Two: Projects Not Started
Project Info | Project Manager's Commentary |
AP078-29 PURE Research Explorer- replace with new module from Elsevier | Project not started yet, earliest start date would be March 2019 |
AP89-026 Support for REF | Project not started yet |
AP89-027 GDPR for Pure | Project not started yet, possible start date February 2019 |
Section Three: Projects in Progress
Project Info | Project Manager's Commentary | ||||||||||||||||||
RES069 PURE UPGRADE TO NEW PROJECT MODEL Compliance / Core & Sponsor Funded Milestones
RAG Status: AMBER
|
Report by Kim Keenan for December 2018 Activities completed
Issues There are key issue to report at this stage:
Next Steps
The project status is AMBER
|
||||||||||||||||||
RIS005 Ethics Tool Procurement Discretionary / Sponsor Funded Milestones:
RAG Status : GREEN
|
Report by Kim Keenan for December 2018 Achievements in Last Period
IssuesThere are no issues to report at this stage Next Steps
The project status is GREEN |
||||||||||||||||||
RIS006 Worktribe Upgrade V3 Compliance / Core Funded Milestones:
RAG Status : GREEN
|
Report by Kim Keenan for December 2018 Achievements in Last Period
IssuesThere are no issues to report at this stage. Next Steps
The project status is GREEN |
||||||||||||||||||
RIS007 PURE Upgrades v5.13 to 5.15 Compliance / Core Funded Milestones:
RAG Status: AMBER
|
Report by Kim Keenan for December 2018 Achievements in Last Period
IssuesThere is one issue to report at this stage: PICCL 1: End of Planning Milestone not achieved and potential suspension of project until RES069 is completed. Next Steps
The project status is AMBER:
RAG Commentary There is a dependency upon the delivery of the UPM (RES069) prior to commencing future upgrades. Until we have deployed the UPM throughout all environments, all environments are unavailable to begin the next upgrades.
|
||||||||||||||||||
RIS008 REF2021 Data Requirements Analysis Discretionary / Sponsor Funded Milestones:
RAG Status : AMBER
|
Report by Kim Keenan for December 2018 Achievements in Last Period
Issues There is one issue to report at this stage: PICCL 1 : End of Planning Milestone not achieved due to key personnel being on annual leave for the festive period Next Steps
The project status is AMBER RAG Commentary The end of planning milestone has not been met due to annual leave commitments over the festive period however full plan including resourcing will be vaiid at next reporting period and the first Business Requirements workshop has been scheduled for 14th January 2019
|
||||||||||||||||||
Other Research projects outwith the RIS programme: This is a research project that is held in the STU programme - now Sponsor funded by RIS programme owner STU252 - Worktribe BI Suite universe- Research Management BI MI Enhancements Discretionary / Sponsor funded Milestones Provisional milestones updated on Projects website, will need updated after re-plan, once scope change approved
RAG Status : SUSPENDED
|
Report by Jamie Thin for December 2018Achievements in Last Period
IssuesNext Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
RIS003 Pure Upgrade v5.10 to v5.12 |
Report by Kim Keenan This project closed 17th August 2018
|
RIS004 Worktribe Upgrades - Readiness for GDPR |
Report by Kim Keenan This project closed 21st September 2018 |