Report for November 2018

Report Date
November 2018

Report compiled by Karen Stirling, RIS Programme Manager for Dominic Tate  (Programme Owner), Damon Querry, Lorna Thomson, Liz Welch, Gary Halliday, Laura Petrie, Pauline Jones, Susan Cooper

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section One: Programme Commentary, RAG and Resources Update

 

Programme Commentary

Overall RIS programme is progressing  with the following  projects : -

  • RES069 - PURE Upgrade to New Project Model - this project is now RED due to a number of issues raised in DEV, problems with code delivered by Supplier and resource conflicts. Also impacting the planning of RIS007 Pure Upgrades 5.13 to 5.15, this has been escalated to senior managers for discussion and aid resolution.
  • RIS006 - Worktribe Upgrade v3 - being impacted by BAU hotfix implementation
  • RIS005 - Ethics Tool Procurement - ITT submitted and out to tender 7 notes of interest so far
  • RIS008 - REF2021 Data Requirements Analysis - project has been initiated and funded via Digital Transformation

PRAF approved, vacancy advertised with Closing date 30th November,shortlisting completed and interviews will take place on 12th December. Until this is completed and starting date agreed we will require an extension to current contract PM especially to cover live deployment of UPM during January / February 2019.

Please find link to REF2021 Portfolio page.

A new risk has been raised to highlight potential business resource limitation and impacts when Core Systems programme commences implementation delivery which may have an impact on project / programme delivery as resource commitment unclear at present.

 

Overall Programme RAG: GREEN

 

Forward Look and RAG

 

 

Resource Position

 

 

 

 

 

 Section Two: Projects Not Started

Project Info Project Manager's Commentary
AP078-29 PURE Research Explorer- replace with new module from Elsevier Project not started yet, earliest start date would be March 2019
AP89-026 Support for REF Project not started yet
AP89-027 GDPR for Pure Project not started yet, possible start date February 2019

 

Section Three: Projects in Progress

 

Project Info Project Manager's Commentary

RES069 PURE UPGRADE TO NEW PROJECT MODEL

Compliance / Core & Sponsor Funded

Milestones

Milestone Due Date
PURE V5.12.4 & UPM Complete (DEV) 23-Nov-2018
Integration - Upgrade to Pure v5.12.4 & UPM Complete (TEST) 13-Dec-2018
Upgrade to PURE 5.12.4 & UPM Complete (LIVE) 22-Jan-2019
DSOR 5.12.4 & UPM Complete 01-Feb-2019
Closure 21-Feb-2019

 

RAG Status:  RED

 

 

Report by Kim Keenan for November 2018

Activities completed
  • Rollback of application (post-Elsevier changes)
  • Further development changes and SAT within DEV to resolve bug issues with conversion jobs
  • Outstanding JIRA's have been prioritised accordingly
Issues
There are three issues to report at this stage:
  • The development work has not been completed and requires additional effort which has impacted project timescales and with no Software Development resource available a resource conflict will need to be submitted to WIS for approval - PICCL 18
  • There is no Development Technology resource available until early January 2019 due to accrued annual leave - PICCL 19
  • The project has had to rollback the application on several occassions due to functionality not being available or bugs being present.  This was investigated by Elsevier and whilst releases were provided this still did not resolve all issues until the latest version within DEV; this has impacted on budget resourcing and the project plan - PICCL 21
Next Steps
  • Resource conflicts presented to WIS for Software Development and Development Technology to secure resource
  • Scope of the development to be defined and approved for delivery of the UPM
  • Project to be re-planned and PICCL to be submitted to business and WIS for approval

The project status is RED

 

 

 

 

RIS005  Ethics Tool Procurement

Discretionary / Sponsor Funded

Milestones:

Milestone Due Date
ITT Responses returned 25-Jan-2019
ITT Evaluation Complete 01-Mar-2019
Procurement Complete 29-Mar-2019
Build & Configure Complete (DEV) 16-Jul-2019
Acceptance Complete (TEST) 27-Aug-2019
Deployment Complete 05-Sep-2019
DSOR 19-Sep-2019
Project Closure Complete 17-Oct-2019

RAG Status : GREEN

 

 

Report by Kim Keenan for November 2018

Achievements in Last Period
  • Business requirements have been finalised and weightings approved

  • Procurement Strategy has been approved

  • ITT has been published

Issues
  • . There are no issues to report at this stage
Next Steps
  • Respond to any clarification questions that may be submitted
  • ITT Evaluation workshops set up for January
  • System Demonstration workshops set up for January
The project status is GREEN

RIS006 Worktribe Upgrade V3

Compliance / Core Funded

Milestones:

Milestone Due Date
DEV environment upgraded to Worktribe v3 11-Dec-2018
Integration - Worktribe TEST upgraded to v3 (ASOR) Complete 14-Feb-2019
Worktribe Upgrade v3 Complete in LIVE 06-Mar-2019
Worktribe v3 DSOR Complete 20-Mar-2019
Closure 02-Apr-2019

RAG Status : GREEN

 

 

Report by Kim Keenan for November 2018

Achievements in Last Period
  • Hotfix 2.5.491 has been implemented into LIVE

  • Revised Project Plan has been approved by the business and WIS

  • Resource has been secured from IS Apps for revised dates

Issues
  • There are no issues to report at this stage.

Next Steps 

  • Worktribe v3 upgraded into DEV
  • Worktribe v3 upgraded into TEST
  • Test Plan Developed

The project status is GREEN

RIS007 PURE Upgrades v5.13 to 5.15

Compliance / Core Funded

Milestones:

Milestone Due Date
End of Planning 23-Nov-2018
Closure 26-Apr-2019

RAG Status: AMBER

 

Report by Kim Keenan for November 2018

Achievements in Last Period
  • Project Brief has been drafted
Issues

There is one issue to report at this stage:

PICCL 1: End of Planning Milestone not achieved

Next Steps 
  • Project brief approved
  • Project plan revised accordingly
  • Project Team established

The project status is AMBER

RIS008 REF2021 Data Requirements Analysis

Discretionary / Sponsor Funded

Milestones:

Milestone Due Date
End of Planning 07-Dec-2018
Project Closure Complete 15-Apr-2019

RAG Status : GREEN

 

Report by Kim Keenan for November 2018

Achievements in Last Period
  • Project Website area has been set up

  • Asta set up

Issues
  • There are no issues to report at this stage
Next Steps 
  • Project brief approved
  • Project Team established

The project status is GREEN

Other Research projects outwith the RIS programme:

This is a research project that is held in the STU programme - now Sponsor funded by RIS programme owner

STU252 - Worktribe BI Suite universe- Research Management BI MI Enhancements 

Discretionary / Sponsor funded

Milestones

Provisional  milestones updated on Projects website, will need updated after re-plan, once scope change approved

Target Date Title
   

RAG Status : SUSPENDED

 

 

Report by Jamie Thin for November 2018
 
Achievements in Last Period
  • Project currently suspended
Issues
Next Steps 
  • Project will be withdrawn in due course
  • The required documentation will be completed to allow project to be closed
Milestones

 

 

 

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary
RIS003 Pure Upgrade v5.10 to v5.12

Report by Kim Keenan

Completion Report

This project closed 17th August 2018

 

RIS004 Worktribe Upgrades - Readiness for GDPR

 Report by Kim Keenan

Completion report

This project closed 21st September 2018