Report for November 2018
- Report Date
- November 2018
Report compiled by Karen Stirling, RIS Programme Manager for Dominic Tate (Programme Owner), Damon Querry, Lorna Thomson, Liz Welch, Gary Halliday, Laura Petrie, Pauline Jones, Susan Cooper
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Programme Commentary
Overall RIS programme is progressing with the following projects : -
- RES069 - PURE Upgrade to New Project Model - this project is now RED due to a number of issues raised in DEV, problems with code delivered by Supplier and resource conflicts. Also impacting the planning of RIS007 Pure Upgrades 5.13 to 5.15, this has been escalated to senior managers for discussion and aid resolution.
- RIS006 - Worktribe Upgrade v3 - being impacted by BAU hotfix implementation
- RIS005 - Ethics Tool Procurement - ITT submitted and out to tender 7 notes of interest so far
- RIS008 - REF2021 Data Requirements Analysis - project has been initiated and funded via Digital Transformation
PRAF approved, vacancy advertised with Closing date 30th November,shortlisting completed and interviews will take place on 12th December. Until this is completed and starting date agreed we will require an extension to current contract PM especially to cover live deployment of UPM during January / February 2019.
Please find link to REF2021 Portfolio page.
A new risk has been raised to highlight potential business resource limitation and impacts when Core Systems programme commences implementation delivery which may have an impact on project / programme delivery as resource commitment unclear at present.
Overall Programme RAG: GREEN
Forward Look and RAG
Resource Position
Section Two: Projects Not Started
Project Info | Project Manager's Commentary |
AP078-29 PURE Research Explorer- replace with new module from Elsevier | Project not started yet, earliest start date would be March 2019 |
AP89-026 Support for REF | Project not started yet |
AP89-027 GDPR for Pure | Project not started yet, possible start date February 2019 |
Section Three: Projects in Progress
Project Info | Project Manager's Commentary | ||||||||||||||||||
RES069 PURE UPGRADE TO NEW PROJECT MODEL Compliance / Core & Sponsor Funded Milestones
RAG Status: RED
|
Report by Kim Keenan for November 2018 Activities completed
IssuesThere are three issues to report at this stage:
Next Steps
The project status is RED
|
||||||||||||||||||
RIS005 Ethics Tool Procurement Discretionary / Sponsor Funded Milestones:
RAG Status : GREEN
|
Report by Kim Keenan for November 2018 Achievements in Last Period
Issues
Next Steps
The project status is GREEN |
||||||||||||||||||
RIS006 Worktribe Upgrade V3 Compliance / Core Funded Milestones:
RAG Status : GREEN
|
Report by Kim Keenan for November 2018 Achievements in Last Period
Issues
Next Steps
The project status is GREEN |
||||||||||||||||||
RIS007 PURE Upgrades v5.13 to 5.15 Compliance / Core Funded Milestones:
RAG Status: AMBER
|
Report by Kim Keenan for November 2018 Achievements in Last Period
IssuesThere is one issue to report at this stage: PICCL 1: End of Planning Milestone not achieved Next Steps
The project status is AMBER |
||||||||||||||||||
RIS008 REF2021 Data Requirements Analysis Discretionary / Sponsor Funded Milestones:
RAG Status : GREEN
|
Report by Kim Keenan for November 2018 Achievements in Last Period
Issues
Next Steps
The project status is GREEN |
||||||||||||||||||
Other Research projects outwith the RIS programme: This is a research project that is held in the STU programme - now Sponsor funded by RIS programme owner STU252 - Worktribe BI Suite universe- Research Management BI MI Enhancements Discretionary / Sponsor funded Milestones Provisional milestones updated on Projects website, will need updated after re-plan, once scope change approved
RAG Status : SUSPENDED
|
Report by Jamie Thin for November 2018Achievements in Last Period
IssuesNext Steps
Milestones
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
RIS003 Pure Upgrade v5.10 to v5.12 |
Report by Kim Keenan This project closed 17th August 2018
|
RIS004 Worktribe Upgrades - Readiness for GDPR |
Report by Kim Keenan This project closed 21st September 2018 |