Report for October 2018

Report Date
October 2018

Report compiled by Karen Stirling, RIS Programme Manager for Dominic Tate  (Programme Owner), Damon Querry, Lorna Thomson, Liz Welch, Gary Halliday, Laura Petrie, Pauline Jones, Susan Cooper

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section One: Programme Commentary, RAG and Resources Update

 

Programme Commentary

Overall RIS programme is progressing  with the following  projects : -

  • RES069 - PURE Upgrade to New Project Model - resource conflict resolved with new milestones and additional budget agreed
  • RIS005 - Ethics Tool procurement- Due to a delay in finalising requirements and weightings for the ITT, PICCL 4 has been raised to amend the milestones to incorporate the delays encountered.
  • RIS006 - Worktribe Upgrade v3 planning has been approved however progress delayed due to Hotfix deployment (out with the scope of the project) UAT sign off not completed and will be impacted by the LIVE deployment of E-Financials over weekend of 09/11/18

New project initiated for RIS007 Pure upgrades v5.13 to v5.15

Confirmation and approval provided by Jeremy Upton, LUC to fund additional PM contract effort until December 2018. A PRAF has been submitted to IS to approve Fixed Term PM for the programme. Until this is approved and sourced we will require an extension to current contract PM especially to cover live deployment of UPM during January 2019.

Following the successful IS Applications Lunchtime Seminar session presented by Pauline Jones and Damon Querry, discussions around data analysis required for REF submission has been taking place. Alex Carter has approached programme to initiate a new project funded by Digital Transformation programme of 50 days for this analysis work to take place. Also high level review of impact of Core Systems has been discussed between Programme Manager and senior Business Analysis on Core Systems (Craig Middlemass), information to be shared.

Please find link to REF2021 Portfolio page

 

Overall Programme RAG: GREEN

 

Forward Look and RAG

 

 

Resource Position

 

 

 

 

 

 Section Two: Projects Not Started

Project Info Project Manager's Commentary
AP078-29 PURE Research Explorer- replace with new module from Elsevier Project not started yet, earliest start date would be March 2019
AP89-026 Support for REF Project not started yet
AP89-027 GDPR for Pure Project not started yet, possible start date February 2019

 

Section Three: Projects in Progress

 

Project Info Project Manager's Commentary

RES069 PURE UPGRADE TO NEW PROJECT MODEL

Compliance / Core & Sponsor Funded

Milestones

Milestone Due Date
PURE V5.12.4 & UPM Complete (DEV) 23-Nov-2018                             
Integration - Upgrade to Pure v5.12.4 & UPM Complete (TEST) 13-Dec-2018
Upgrade to PURE 5.12.4 & UPM Complete (LIVE) 22-Jan-2019
DSOR 5.12.4 & UPM Complete 01-Feb-2019
Closure 21-Feb-2019

 

RAG Status:  GREEN

 

 

Report by Kim Keenan for October 2018

Activities completed
  • UPM conversion jobs have run and daily check point meetings are underway
  • PURE 5.12.4 has been deployed into DEV and UPM conversions have begun
  • Errors within the financial breakdown and conversion jobs have been troubleshooted
  • Resource conflict for additional effort from Software Development has been secured for the following month
Issues

There is one issue to report at this stage:

  • The data conversion jobs within DEV require additional effort to resolve bugs, therefore PICCL 16 has been raised to extend the milestones
Next Steps
  • Testing of UPM in 5.12.4 complete (DEV)
  • Handover from Software Development to Development Technology complete
  • TEST upgraded to 5.12.4 with UPM enabled

The project status is GREEN

 

 

 

 

RIS005  Ethics Tool Procurement

Discretionary / Sponsor Funded

Milestones:

Milestone Due Date
Business Analysis Complete 19-Nov-2018
ITT Responses returned 25-Jan-2019
ITT Evaluation Complete 01-Mar-2019
Procurement Complete 29-Mar-2019
Build & Configure Complete (DEV) 16-Jul-2019
Acceptance Complete (TEST) 27-Aug-2019
Deployment Complete 05-Sep-2019
DSOR 19-Sep-2019
Project Closure Complete 17-Oct-2019

RAG Status : AMBER

 

 

Report by Kim Keenan for October 2018

Achievements in Last Period
  • Business requirements have been defined fruther and weightings applied

  • IS Apps requirements have been finalised for the ITT

  • Procurement strategy has been futher developed in line with weightings applied to each area

  • EQIA and DPIA have now been approved

Issues

Due to a delay in finalising requirements and weightings for the ITT, PICCL 4 has been raised to amend the milestones to incorporate the delays encountered.

Next Steps
  • PICCL 4 approved and project milestones adjusted accordingly.
  • ITT documentation finalised
  • Issue ITT
  • Procurement Strategy approved
The project status is AMBER

RIS006 Worktribe Upgrade V3

Compliance / Core Funded

Milestones:

Milestone Due Date Complete
DEV environment upgraded to Worktribe v3 28-Nov-2018 No
Integration - Worktribe TEST upgraded to v3 (ASOR) Complete 14-Feb-2019 No
Worktribe Upgrade v3 Complete in LIVE 06-Mar-2019 No
Worktribe v3 DSOR Complete 20-Mar-2019 No
Closure 27-Mar-2019 No

RAG Status : AMBER

 

 

Report by Kim Keenan for October 2018

Achievements in Last Period
  • Project Brief has been approved

  • Resource has been secured from IS Apps

Issues
  • There is one issue to report at this stage PICCL 2 - this PICCL seeks to extend the timescales due to a delay with implementing the Hotfix for 2.5 into LIVE (outwith the scope of this project) however until the Hotfix is implemented into all environments then the upgrade cannot proceed.
Next Steps 
  • PICCL 2 - revised timescales approved
  • Hotfix 2.5.491 deployed into LIVE (not within scope of this project)
  • Worktribe upgrade DEV and TEST to v3

The project status is AMBER

RIS007 PURE Upgrades v5.13 to 5.15

Compliance / Core Funded

Milestones:

Milestone Due Date
End of Planning 23-Nov-2018
Closure 26-Apr-2019

RAG Status: GREEN

 

Report by Kim Keenan for October 2018

Achievements in Last Period
  • Project Website area has been set up

  • Asta set up

Issues
  • There are no issues to report at this stage
Next Steps 
  • Project brief approved
  • Project Team established

The project status is GREEN

Other Research projects outwith the RIS programme:

This is a research project that is held in the STU programme - now Sponsor funded by RIS programme owner

STU252 - Worktribe BI Suite universe- Research Management BI MI Enhancements 

Discretionary / Sponsor funded

Milestones

Provisional  milestones updated on Projects website, will need updated after re-plan, once scope change approved

Target Date Title
   

RAG Status : SUSPENDED

 

 

Report by Jamie Thin for September 2018
 
Achievements in Last Period
  • Project suspended
Issues
Next Steps 
Milestones

 

 

 

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary
RIS003 Pure Upgrade v5.10 to v5.12

Report by Kim Keenan

Completion Report

This project closed 17th August 2018

 

RIS004 Worktribe Upgrades - Readiness for GDPR

 Report by Kim Keenan

Completion report

This project closed 21st September 2018