Report for September 2018

Report Date
September 2018

Report compiled by Karen Stirling, RIS Programme Manager for Dominic Tate  (Programme Owner), Damon Querry, Lorna Thomson, Liz Welch, Gary Halliday, Laura Petrie, Pauline Jones, Susan Cooper

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section One: Programme Commentary, RAG and Resources Update

 

Programme Commentary

Overall RIS programme is progressing  with the following  projects : -

  • RES069 - PURE Upgrade to New Project Model
  • RIS004 - Worktribe Upgrades - Readiness for GDPR  now closed
  • RIS005 - Ethics Tool procurement, business requirements gathering
  • RIS006 - Worktribe Upgrade v3 has been initiated and planning in progress
  • RIS003 - Now Closed

Confirmation and approval provided by Jeremy Upton, LUC to fund additional PM contract effort until December 2018.

Agreement for RIS007 Pure upgrades v5.13 to 5.15 to start early November 2018

 

Overall Programme RAG: GREEN

 

Forward Look and RAG

 

 

Resource Position

 

 

 

 

 

 Section Two: Projects Not Started

Project Info Project Manager's Commentary
AP078-29 PURE Research Explorer- replace with new module from Elsevier Project not started yet, move to 18/19
RIS007 (AP89-024) Pure  Upgrade v5.13 to v5.15 Project not started yet - planning to initiate early November 18
AP89-026 Support for REF Project not started yet
AP89-027 GDPR for Pure Project not started yet

 

Section Three: Projects in Progress

 

Project Info Project Manager's Commentary

RES069 PURE UPGRADE TO NEW PROJECT MODEL

Compliance / Core & Sponsor Funded

Milestones

Milestone Due Date
5.12.2 & UPM Testing Complete (DEV) 31-Oct-2018
PURE V5.12.4 & UPM Complete (DEV) 09-Nov-2018
Integration - Upgrade to Pure v5.12.4 & UPM Complete (TEST) 27-Nov-2018
Upgrade to PURE 5.12.4 & UPM Complete (LIVE) 13-Dec-2018
DSOR 5.12.4 & UPM Complete 01-Feb-2019
Closure 14-Feb-2019

RAG Status: AMBER

 

 

Report by Kim Keenan for September 2018

Activities completed
  • Project has been unsuspended
  • All resource has been secured to undertake the project tasks
  • PURE DEV has been upgraded to 5.12.2-1 with UPM enabled
  • UPM build has re-commenced and conversion jobs have been run and errors currently being investigated
Issues

There are two issues to report at this stage:

  • The UPM was not enabled in 5.12.2-1, a temporary fix has been put in place to avoid slippage however the project will need to upgrade to 5.12.4 (UPM enabled) for deployment - PICCL 13
  • The allocated budget for the delivery of the UPM has exceeded it's tolerance and therefore extra budget is required - PICCL 14
Next Steps
  • Testing of UPM in 5.12.2-1 complete (DEV)
  • Implementation plan defined for 5.12.4

The project status is AMBER

 

 

 

RIS004  Worktribe Upgrades - Readiness for GDPR

Compliance / Sponsor Funded

Milestones:

All milestones have now been closed.

 

RAG Status : BLUE

 

Report by Kim Keenan for September 2018

Achievements in Last Period
  • DSOR has been signed off

  • Project has now been formally closed

Issues

There are no outstanding issues within the project

Next Steps

The project is now closed so there are no further steps to be undertaken.

The project status is BLUE

 

 

RIS005  Ethics Tool Procurement

Discretionary / Sponsor Funded

Milestones:

Milestone Due Date
Business Analysis Complete 28-Sep-2018
ITT Responses returned 02-Nov-2018
ITT Evaluation Complete 07-Dec-2018
Procurement Complete 25-Jan-2019
Build & Configure Complete (DEV) 14-May-2019
Acceptance Complete (TEST) 25-Jun-2019
Deployment Complete 04-Jul-2019
DSOR 18-Jul-2019
Project Closure Complete 15-Aug-2019

 

RAG Status : GREEN

 

 

Report by Kim Keenan for September 2018

Achievements in Last Period
  • Procurement strategy has been developed and awaiting approval from Project Sponsor once weightings have been finalised

  • Business requirements have been defined further

  • EQIA and DPIA are now out for approval

  • Project Brief was approved by WIS

  • Demo by epi-Gensys was undertaken by the business

Issues

There are no issues to report at this stage

Next Steps
  • Business requirements approved with appropriate weightings applied
  • ITT documentation finalised
  • Issue ITT
  • Procurement Strategy approved
The project status is GREEN

RIS006 Worktribe Upgrade V3

Compliance / Core Funded

Milestones:

Milestone Due Date
Planning complete 28-Sep-2018
Deployment 30-Nov-2018
Closure 14-Dec-2018

RAG Status : GREEN

 

 

Report by Kim Keenan for September 2018

Achievements in Last Period
  • Project Website area has been set up

  • Project team established

  • Asta set up

  • Worktribe have been engaged and release notes have been provided

Issues

There are no issues to report at this stage

Next Steps
  • Project brief approved
  • Test Plan established
  • Worktribe upgrade DEV and TEST to v3
The project status is GREEN

Other Research projects outwith the RIS programme:

This is a research project that is held in the STU programme - now Sponsor funded by RIS programme owner

STU252 - Worktribe BI Suite universe- Research Management BI MI Enhancements 

Discretionary / Sponsor funded

Milestones

Provisional  milestones updated on Projects website, will need updated after re-plan, once scope change approved

Target Date Title
   

RAG Status : SUSPENDED

 

 

Report by Jamie Thin for September 2018
 
Achievements in Last Period
  • Project suspended
Issues
Next Steps 
Milestones

 

 

 

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary
RIS003 Pure Upgrade v5.10 to v5.12

Report by Kim Keenan

Completion Report

This project closed 17th August 2018

 

RIS004 Worktribe Upgrades - Readiness for GDPR

 Report by Kim Keenan

Completion report

This project closed 21st September 2018