Report for August 2018

Report Date
August 2018

Report compiled by Karen Stirling, RIS Programme Manager for Dominic Tate  (Programme Owner), Damon Querry, Lorna Thomson, Liz Welch, Gary Halliday, Laura Petrie, Pauline Jones, Susan Cooper

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section One: Programme Commentary, RAG and Resources Update

 

Programme Commentary

Overall RIS programme is progressing  with the following  projects : -

  • RES069 - Project now unsuspended ready for resource to re-engage with project activity in September
  • RIS003 - PURE 5.12.1-4 has been deployed LIVE environment on 20th August. Unspent budget if 20 days to be returned to Programme.
  • RIS004 - Worktribe v2.5 LIVE upgrade completed on  30 August - issue with feeds now resolved, project currently over budget
  • RIS005 - Ethics Tool procurement now progressing business requirements gathering, concerns around level of integration required. Original requirement for EASE only however discussions now highlighting integration with Worktribe and EUCLID. Risk to highlight that this will incur higher project costs externally and internally
  • RIS006 Agreement to initiate the next Worktribe Upgrade v3

At the last Programme review meeting, IS Applications 3 year planning budgets now confirmed, no additional funding being made available via GASP or L&UC there will be constraints on budgets for 18/19. It is also important to note that the programme has an allocated Project Manager whose contract expires end of September so budget being progressed to continue with this resource.

As most of current projects in progress are noted as GREEN and IS Applications core funding approved the current status of the programme is GREEN although there remains concerns around LUC funding can be agreed by RIS Programme Owner.

 

Overall Programme RAG: GREEN

 

Forward Look and RAG

 

 

Resource Position

 

 

 

 

 

 Section Two: Projects Not Started

Project Info Project Manager's Commentary
AP078-29 PURE Research Explorer- replace with new module from Elsevier Project not started yet, move to 18/19
AP89-024 Pure  Upgrade v5.13 to v5.15 Project not started yet
RIS006 AP89-025 Worktribe Upgrade v3 Project to be initiated in September on closure of RIS004
AP89-026 Support for REF Project not started yet
AP89-027 GDPR for Pure Project not started yet

 

Section Three: Projects in Progress

 

Project Info Project Manager's Commentary

RES069 PURE UPGRADE TO NEW PROJECT MODEL

Milestone Due Date
Testing of 5.12.2.1 functionality signed off 19-Sep-2018
5.12.2 & UPM Testing Complete (DEV) 31-Oct-2018
PURE V5.12.4 & UPM Complete (DEV) 09-Nov-2018
Integration - Upgrade to Pure v5.12.4 & UPM Complete (TEST) 27-Nov-2018
Upgrade to PURE 5.12.4 & UPM Complete (LIVE) 13-Dec-2018
DSOR 5.12.4 & UPM Complete 01-Feb-2019
Closure 14-Feb-2019

RE Upgrade to new Project Model

Compliance / Core & Sponsor Funded

Milestones

RAG Status: GREEN

 

 

Report by Kim Keenan for August 2018

Achievements in Last Period
  • Project was suspended due to lack of Software Development resource
  • Project was raised from High to Highest
  • Project was unsuspended to recommence project delivery
Issues

 There are no issues to report at this stage.

Next steps
  • Incorporate upgrade activities of PURE 5.12.2-1 into this project
  • Dependency upon RIS003 continues to implement 5.12.1 through to 5.12.2 with UPM enabled
  • Revise project plan with adjusted milestones

The project status is GREEN

 

 

 

RIS003 PURE Upgrades v5.10 to v 5.12

Compliance / Core Funded

Milestones:

RAG Status : BLUE

 

 

Report by Kim Keenan for August 2018

Achievements in Last Period
  • PURE upgrade 5.12.1-4 has now been successfully deployed to LIVE
  • The upgrade of 5.12.2-1 have been transferred to RES069 for the UPM

  • PURE environments have been handed over to RES069

  • Project Closure report has been approved by WIS

Issues

All issues within this project have now been resolved.

Next Steps

There are no next steps to take due to the project being closed.

The project status is BLUE

 

RIS004  Worktribe Upgrades - Readiness for GDPR

Compliance / Sponsor Funded

Milestones:

Target Datesort descending Title
21-Sept-2018 Project Closure

 

RAG Status : AMBER

 

Report by Kim Keenan for August 2018

Achievements in Last Period
  • Worktribe 2.5 has been deployed into LIVE prior to the Change Freeze being invoked

  • Interfaces have been repointed to VRS, E-Fin and HR Systems

  • Project Closure activities have commenced

Issues

 There is one issue recorded which relates to the additional funding required in the next financial year, project is currently over expected 10 days budget for 18/19

Next Steps
  • DSOR meeting scheduled for 13th September 2018
  • Interfaces repointed and tested to VRS, E-Fin and HR systems
  • PICCL for additional funding to be approved by Project Sponsor
  • Project Closure

The project status is AMBER

 

 

RIS005  Ethics Tool Procurement

Discretionary / Sponsor Funded

Milestones:

Milestone Due Date
Business Analysis Complete 28-Sep-2018
ITT Responses returned 02-Nov-2018
ITT Evaluation Complete 07-Dec-2018
Procurement Complete 25-Jan-2019
Build & Configure Complete (DEV) 14-May-2019
Acceptance Complete (TEST) 25-Jun-2019
Deployment Complete 04-Jul-2019
DSOR 18-Jul-2019
Project Closure Complete 15-Aug-2019

 

RAG Status : GREEN

 

 

Report by Kim Keenan for August 2018

Achievements in Last Period
  • Procurement strategy has been developed

  • Follow up Business requirements workshop held with the Project Team whereby requirements were clearly defined as desirable or mandatory

  • Secondary potential supplier has been identified - epi-Genesys (Demo to follow)

  • Project Brief was approved by WIS

  • PICCL with revised timescales to acccomodate realistic procurement timescales

Issues

 There are no issues to report at this stage

Next Steps
  • Business requirements approved
  • ITT documentation prepared
  • epi-Gensys demo
  • Procurement Strategy approved
The project status is GREEN

Other Research projects outwith the RIS programme:

This is a research project that is held in the STU programme - now Sponsor funded by RIS programme owner

STU252 - Worktribe BI Suite universe- Research Management BI MI Enhancements 

Discretionary / Sponsor funded

Milestones

Provisional  milestones updated on Projects website, will need updated after re-plan, once scope change approved

Target Date Title
   

RAG Status : SUSPENDED

 

 

Report by Jamie Thin for August 2018
 
Achievements in Last Period
  • Project suspended
  • Business lead has agreed Project should be formally suspended while the RIS team evaluate the use of Power BI against the raw BI Data extract as alternative to the STU252 Star schema and BI Suite Universe
  • Alternative technical solutions to apply org unit permissions to the BI Suite universe reviewed - none are operationally attractive
  • Other project tasks on hold , pending outcome of discussion on scope and priorities
  • Business lead has discusses priorities with the key business users at the operational group
Issues
  • Open - No agreement on Scope change re. Org unit permissions
    • Initial proposal of providing no org unit data restrictions have been rejected by Business lead
    • Workaround explored with IS Service Management of applying row level permissions, but doesn't look like it would work for  IGMM and Roslin, and complex data structures with collaborative projects with multiple budgets for each Org unit
Next Steps 
  • Agree suspension period and criteria for either withdrawing the project or reducing scope and completing the revised scope.
  • Propose review within 3-months time by  end of Oct 2018 - Decision point for Business lead and Project sponsor
  • --
  • If project re-started :
    • Re-plan with revised scope 
    • R&D to investigate other possible solutions for providing  IGMM and Roslin with their own data in an easy format to report against
    • Deliver remaining JIRAS incl STU252-52 (0.5d effort) 
    • UAT acceptance sign-off
    • Handover to BAU  - Confirm policy decision with IS Service Management re. IS L&UC RIS team access to Universe Designer 
      • propose limited access to Universe Designer for RIS team - so RIS can locally make some simple changes  eg.  rename data items and add 'tool-tip' descriptions of each object 
    • Deploy BI Suite Universe to LIVE, switch on daily package to refresh STAR schema in LIVE
    • Deployment review
    • Project Closure
Milestones

Provisional  milestones updated on Projects website, will need updated after re-plan, once scope change approved

 

 

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary

RES069 PURE Upgrade to new Project Model

Report by Kim Keenan

Completion Report

This project closed 30th August 2018

Documentation

Not available.