Report for June 2018
- Report Date
- June 2018
Report compiled by Karen Stirling, RIS Programme Manager for Dominic Tate (Programme Owner), Damon Querry, Lorna Thomson, Liz Welch, Gary Halliday, Laura Petrie, Pauline Jones, Susan Cooper
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Programme Commentary
The overall programme is progressing with the following projects : -
- RES069 - Resource is now not available until September and request to suspend project until end of August has been submitted for WIS approval
- RIS003 - PURE now upgraded 5.11.2 in LIVE and next upgrade has been deployed to development
- RIS004 - Worktribe hot fix now deployed to Live and v2.5 deployed to dev and test
- RIS005 - Ethics Tool procurement now in planning stage
There is a planning project which aligns to PURE Cloud Portal however as advised by Elseveir this is not available until 5.13 propose to move this 10 day project into 18/19.
Programme status currently AMBER as project milestones are moving further into 18/19 for RES069 and RIS003 due to the dependency between the projects and concerns regarding sponsored funded budgets for resource is increasing. 3 year planning proposals have still to be confirmed to allow projects to start for financial year 18/19.
Project manager resource has been extended to end of September and looking to have confirmation of further funding to be made available
Overall Programme RAG: AMBER
Forward Look and RAG
Resource Position
Section Two: Projects Not Started
Project Info | Project Manager's Commentary |
AP078-29 PURE Research Explorer- replace with new module from Elsevier | Project not started yet, need to agree timescales for project commencing, this is for decommissioning effort |
Section Three: Projects in Progress
Project Info | Project Manager's Commentary | ||||||||||||||||||||||||||||||
RES069 PURE Upgrade to new Project Model Compliance / Core & Sponsor Funded Milestones
RAG Status: RED
|
Report by Kim Keenan for June 2018 Achievements in Last Period
IssuesThere has been one issue to report at this stage Next steps
The project status is RED Issue – The project has lost Software Development resource to several projects which has directly stopped any further development until the resource returns to the project. The impact is that the original timeline of project completion in 17/18 is no longer achievable and there is no budget allocated to complete the project in the next financial year. We have replanned the project timelines which includes suspending the project until September once resource is available to complete the development work. The revised timeline has been agreed with the Project Sponsor and key stakeholders. The issue of the 18/19 budget will be discussed with the ISG Portfolio Manager and Programme Owner (L&UC) during July. No action by SMT is required.
|
||||||||||||||||||||||||||||||
RIS003 PURE Upgrades v5.10 to v 5.12 Compliance / Core Funded Milestones:
RAG Status : AMBER
|
Report by Kim Keenan for June 2018 Achievements in Last Period
IssuesThere has been one issue raised this period: Next Steps
The project status is AMBER Re-planning exercise has been undertaken due to losing resource on RES069 and not being able to deliver the UPM with the 5.11.3 release
|
||||||||||||||||||||||||||||||
RIS004 Worktribe Upgrades - Readiness for GDPR Compliance / Sponsor Funded Milestones:
RAG Status : AMBER
|
Report by Kim Keenan for June 2018 Achievements in Last Period
Issues
Next Steps
The project status is AMBER - The testing for the hotfix within the TEST environment has not been completed and signed off within the timescales agreed in the project plan. In addition to this, the Go Live date has had to be cancelled due to an issue that has arisen and a lack of resource to undertake testing due to staff illness. |
||||||||||||||||||||||||||||||
RIS005 Ethics Tool Procurement Discretionary / Sponsor Funded Milestones:
RAG Status : GREEN
|
Report by Kim Keenan for June 2018 Achievements in Last Period
IssuesThere are no issues to report at this stage Next Steps
The project status is GREEN |
||||||||||||||||||||||||||||||
Other Research projects outwith the RIS programme: This is a research project that is held in the STU programme - now Sponsor funded by RIS programme owner STU252 - Worktribe BI Suite universe- Research Management BI MI Enhancements Discretionary / Sponsor funded Milestones Provisional milestones updated on Projects website, will need updated after re-plan, once scope change approved
RAG Status : RED
|
Report by Jamie Thin for June 2018Achievements in Last Period
Issues
Next Steps
The project status is RED Issue - Original scope can't be delivered within current budget - either cut scope to fit budget, or project sponsor will need to provide additional funding for R&D to investigate options for providing own data back to IGMM and Roslin, in a format they can run their own reports
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
RES070 Worktribe upgrade v2.3 & Apprenticeship Levy Compliance |
Report by Ben Armstrong This project closed on 11th Aug 2017 |
RES060 PGR feed to PURE Compliance |
Report by Jamie Thin This project closed on 8th September 2017 |
AP78-048 PURE - REF 2020 - IS Apps effort to support REF return Compliance |
PICCL by Karen Stirling This project withdrawn on 8th December 2017 Information detailed within PICCL |
RES062 PURE Upgrade to ORACLE 12c Compliance |
Report by Chris Konzcak This project closed on 8th December 2017 |
RES063 Research Information Management - Small Enhancements Discretionary |
Report by Karen Stirling This project closed on 6th April 2018 |
RIS001 Pure Annual Upgrade Compliance |
Report by Kim Keenan This project closed on 6th April 2018 |
RES066 Migrate RSO Contracts and Legal Services DB to IS Apps server Compliance |
Report by Anne Mathison This project closed on 20th April 2018 |
RES057 PURE - Worktribe Project Feed to PURE (RES057) with new Project model Compliance |
PICCL by Karen Stirling This project withdrawn on 27th April 2018 Information detailed within PICCL |
Attachment | Size |
---|---|
![]() | 205.3 KB |
![]() | 136.64 KB |