Report for June 2018

Report Date
June 2018

Report compiled by Karen Stirling, RIS Programme Manager for Dominic Tate  (Programme Owner), Damon Querry, Lorna Thomson, Liz Welch, Gary Halliday, Laura Petrie, Pauline Jones, Susan Cooper

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section One: Programme Commentary, RAG and Resources Update

 

Programme Commentary

 

The overall programme is progressing  with the following  projects : -

  • RES069 - Resource is now not available until September and request to suspend project until end of August has been submitted for WIS approval
  • RIS003 - PURE now upgraded 5.11.2 in LIVE and next upgrade has been deployed to development
  • RIS004 - Worktribe hot fix now deployed to Live and v2.5 deployed to dev and test
  • RIS005 - Ethics Tool procurement now in planning stage

There is a planning project which aligns to PURE Cloud Portal however as advised by Elseveir this is not available until 5.13 propose to move this 10 day project into 18/19.

Programme status currently AMBER as project milestones are moving further into 18/19 for RES069 and RIS003 due to the dependency between the projects and concerns regarding sponsored funded budgets for resource is increasing. 3 year planning proposals have still to be confirmed to allow projects to start for financial year 18/19.

 

Project manager resource has been extended to end of September and looking to have confirmation of further funding to be made available

Overall Programme RAG: AMBER

 

Forward Look and RAG

 

 

Resource Position

 

 

 

 

 

 Section Two: Projects Not Started

Project Info Project Manager's Commentary
AP078-29 PURE Research Explorer- replace with new module from Elsevier Project not started yet, need to agree timescales for project commencing, this is for decommissioning effort

 

Section Three: Projects in Progress

 

Project Info Project Manager's Commentary

 

RES069 PURE Upgrade to new Project Model

Compliance / Core & Sponsor Funded

Milestones

Target Datesort descending Title
19-Sep-2018 Build
22-Nov-2018 Integration
03-Dec-2018 Deployment Sign-off
17-Dec-2018 Closure

RAG Status: RED

 

 

Report by Kim Keenan for June  2018

Achievements in Last Period
  • Meeting held with business stakeholders to review current position of the delivery of UPM - it has been agreed to raise a PICCL to raise the project from High to Highest
Issues

There has been one issue to report at this stage

RES069 Issue 10

Next steps
  • PICCL presented to WIS for project prioritisation consideration and approval
  • Dependency upon RIS003 continues to implement 5.12.1 through to 5.12.2 with UPM enabled
  • Revise project plan with adjusted milestones

The project status is RED

Issue – The project has lost Software Development resource to several projects which has directly stopped any further development until the resource returns to the project. The impact is that the original timeline of project completion in 17/18 is no longer achievable and there is no budget allocated to complete the project in the next financial year. We have replanned the project timelines which includes suspending the project until September once resource is available to complete the development work. The revised timeline has been agreed with the Project Sponsor and key stakeholders. The issue of the 18/19 budget will be discussed with the ISG Portfolio Manager and Programme Owner (L&UC) during July. No action by SMT is required.

 

 

RIS003 PURE Upgrades v5.10 to v 5.12

Compliance / Core Funded

Milestones:

Target Datesort descending Title
09-Jul-2018 Upgrade Live environment to 5.11.2 complete
17-Jul-2018 5.12.1 Testing and Acceptance Complete (DEV)
17-Jul-2018 Upgrade Dev environment to 5.12.1 complete
06-Aug-2018 5.12.1 Testing and Acceptance Complete (TEST)
06-Aug-2018 Upgrade Test environment to 5.12.1 complete
20-Aug-2018 5.12.1 Testing and Acceptance Complete (LIVE)
20-Aug-2018 Upgrade Live environment to 5.12.1 complete
30-Aug-2018 Upgrade Pure 5.12.2 into DEV
30-Aug-2018 5.12.2 Testing and Acceptance Complete (DEV)
08-Oct-2018 Upgrade Test environment to 5.12.2 complete
08-Oct-2018 5.12.2 Testing and Acceptance Complete (TEST)
07-Nov-2018 5.12.2 Testing and Acceptance Complete (LIVE)
07-Nov-2018 Upgrade Live environment to 5.12.2 complete
22-Nov-2018 Project Closure

RAG Status : AMBER

 

 

Report by Kim Keenan for June 2018

Achievements in Last Period
  • Testing has been completed by the business and signed off for 5.11.2 into the Live environment

  • GoCab have approved the implementation for the 9th July 2018

  • Service Alert has been raised

  • Communication has been issued to Pure Governance Group and the business advising of the upgrade and downtime

  • Re-planning exercise has been undertaken due to losing resource on RES069 and not being able to deliver the UPM with the 5.11.3 release

  • PURE 5.12 is now available

 

Issues

There has been one issue raised this period:

RIS003 Issue 7

 
Next Steps
  • PURE 5.11.2 will be deployed to LIVE
  • Test Plan to be developed and test owners assigned for 5.12.1
  • PICCL to be submitted to WIS - reflecting the decision to move forward with 5.12.1 whilst awaiting RES069 resource to complete UPM
  • Resolve data issues with e-fin
The project status is AMBER Re-planning exercise has been undertaken due to losing resource on RES069 and not being able to deliver the UPM with the 5.11.3 release

 

RIS004  Worktribe Upgrades - Readiness for GDPR

Compliance / Sponsor Funded

Milestones:

Target Datesort descending Title
26-Jul-2018 2.5.91 upgrade Testing Signed Off (TEST)
26-Jul-2018 2.5.91 upgrade complete (TEST)
06-Aug-2018 2.5.91 upgrade Testing Signed Off (LIVE)
06-Aug-2018 2.5.91 upgrade complete (LIVE)
20-Aug-2018 Project Closure

 

RAG Status : AMBER

 

Report by Kim Keenan for June 2018

Achievements in Last Period
  • Worktribe workfix 2.3.17 has been implemented into the LIVE environment

  • Test Plan has been produced for 2.4 through to 2.5

  • Test Workshop has been scheduled for the 4th July 2018 with the business

  • Worktribe Upgrade 2.5 has been implemented into the DEV environment and testing has been signed off

Issues
  • There is one issue recorded which relates to the delay in implementing the hotfix into the LIVE environment

RIS004 Issue No. 2

Next Steps
  • Worktribe 2.5.91 upgrade applied to TEST
  • Worktribe UAT of 2.5.91 is undertaken
The project status is AMBER - The testing for the hotfix within the TEST environment has not been completed and signed off within the timescales agreed in the project plan.  In addition to this, the Go Live date has had to be cancelled due to an issue that has arisen and a lack of resource to undertake testing due to staff illness.

 

RIS005  Ethics Tool Procurement

Discretionary / Sponsor Funded

Milestones:

Target Datesort descending Title
13-Jul-2018 Project planning complete
30-Nov-2018 Delivery
14-Dec-2018 Closure

 

RAG Status : GREEN

 

 

Report by Kim Keenan for June 2018

Achievements in Last Period
  • Project Website area has been set up

  • Project team established

  • Asta set up

  • Procurement are engaged

Issues

There are no issues to report at this stage

Next Steps
  • Project brief produced and approved
  • Business requirements produced and signed off
The project status is GREEN

Other Research projects outwith the RIS programme:

This is a research project that is held in the STU programme - now Sponsor funded by RIS programme owner

STU252 - Worktribe BI Suite universe- Research Management BI MI Enhancements 

Discretionary / Sponsor funded

Milestones

Provisional  milestones updated on Projects website, will need updated after re-plan, once scope change approved

Target Date Title
   

RAG Status :

RED

 

Report by Jamie Thin for June 2018
 

Achievements in Last Period

  • Project on hold awaiting decision from Business lead re. proposed scope change
  • Business lead has agreed Project should be formally suspended while the RIS team evaluate the use of Power BI against the raw BI Data extract as alternative to the STU252 Star schema and BI Suite Universe
  • Alternative technical solutions to apply org unit permissions reviewed - none are operationally attractive
  • Other project tasks on hold , pending outcome of discussion on scope

Issues

  • Open - No agreement on Scope change re. Org unit permissions
    • Initial proposal of providing no org unit data restrictions have been rejected by Business lead
    • Workaround explored with IS Service Management of applying row level permissions, but doesn't look like it would work for  IGMM and Roslin, and complex data structures with collaborative projects with multiple budgets for each Org unit
  • Open : Resource conflict in IS Project services - PM has limited time to push scope change to conclusion while focusing on higher priority Service Excellence Exam Timetabling project

Next Steps 

  • Propose suspend the project until either scope change is agreed by the business lead , or project sponsor provides more funding to do some R&D and see if it is possible to complete project closer to original scope , or risk project being closed without delivering a working BI Suite universe.
  • Re-plan with revised scope 
  • R&D to investigate other possible solutions for providing  IGMM and Roslin with their own data in an easy format to report against
  • Deliver remaining JIRAS incl STU252-52 (0.5d effort) 
  • UAT acceptance sign-off
  • Handover to BAU  - Confirm policy decision with IS Service Management re. IS L&UC RIS team access to Universe Designer 
    • propose limited access to Universe Designer for RIS team - so RIS can locally make some simple changes  eg.  rename data items and add 'tool-tip' descriptions of each object 
  • Deploy BI Suite Universe to LIVE, switch on daily package to refresh STAR schema in LIVE
  • Deployment review
  • Project Closure

The project status is RED Issue - Original scope can't be delivered within current budget - either cut scope to fit budget, or project sponsor will need to provide additional funding for R&D to investigate options for providing own data back to IGMM and Roslin, in a format they can run their own reports

 

 

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary

RES070

Worktribe upgrade v2.3 & Apprenticeship Levy

Compliance

Report by Ben Armstrong

This project closed on 11th Aug 2017

Completion report

RES060

PGR feed to PURE

Compliance

Report by Jamie Thin

This project closed on 8th September 2017

Completion report

AP78-048

PURE - REF 2020 - IS Apps effort to support REF return

Compliance

PICCL by Karen Stirling

This project withdrawn on 8th December 2017

 Information detailed within  PICCL

RES062

PURE Upgrade to ORACLE 12c

Compliance

Report by Chris Konzcak

This project closed on 8th December 2017

Completion report

RES063

Research Information Management - Small Enhancements

Discretionary

Report by Karen Stirling

This project closed on 6th April 2018

Completion Report

RIS001

Pure Annual Upgrade

Compliance

Report by Kim Keenan

This project closed on 6th April 2018

Completion Report

RES066

Migrate RSO Contracts and Legal Services  DB to IS Apps server

Compliance

Report by Anne Mathison

This project closed on 20th April 2018

Completion Report

RES057

PURE - Worktribe Project Feed to PURE (RES057) with new Project model

Compliance

PICCL by Karen Stirling

This project withdrawn on 27th April 2018

Information detailed within PICCL

Documentation

Not available.