May 2013

Report Date
May 2013

Report compiled by Franck Bergeret (IS Apps Programme Manager) for Ian Pirie (Programme Owner)

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section One: Programme Commentary, RAG and Resources Update

During May, SSG006 (ESS photos for students) was closed and its remaining budget was used to fund the SSG004 Phase 1 completion, as well as carrying out further enhancements (under new project SSG010).

SSG004 (ESS Small Scale Enhancements) and SSG007 (Small Group Functions) codes were successfully deployed to the Training environment (TRN) and both projects can now be closed.

SSG008 (ESS functions for PGT) build has been completed and is being tested.

SSG009 (ESS architecture review): the project team has completed the first 3 meetings to review the current architecture of the Personal Tutor System, the St Andrews assessment build application and the School of Physics in-year assessment system.

SSG010 (ESS Small Enhancements) is at anlysis/design phase. 

 

The suspension of ESS Photos for Students (SSG006) and the use of its remaining budget has now enabled to support the overspend of Small Group Enhancements (SSG007), and to carry out further enhancements (SSG010). SSG008 (PGT for PT) is 17 days under as the build effort was less than the estimates. 

 Section Two: Projects Not Started

 

Project InfoProgramme Manager's Commentary

AP23-012

Training Records for Research Legislation

Compliance

Planning August 2013

Delivery Uncertain, possibly December 2013

RAG Status

GREEN

Plan

Biological Services have requested that this project be deferred to the start of the next academic year in August 2013. This project is to be deferred as planned carry-over for 13/14 during the mid-year review in January 2013. 

 

Dependencies

This is dependent on the UK Government enacting the legislation to correspond to the European legislation which came into force on 01-Jan-2013. This project cannot start until the UK Government requirements are known.

Outcome to be deferred until final decision is made about the ESS funding for 13/14.

AP23-037

MVM Ringfenced Balance Days

Very Important

Planning TBC

Delivery TBC

RAG Status

RED

Plan

15d of the remaining 70d balance has been transferred to Research for work on Roslin Mouse Database Migration, leaving 55d.

The meeting planned for January with MVM to clarify what is likely to come is now expected to take place in April. The main focus is expected on MI for the rest of this year and there may also be some work assisting with a procurement exercise. Following the meeting it should be possible to identify what is required, and to be able to return this to green. Action remains with the Head of Service Management to schedule the meeting.

The RAG remains RED as it's not clear if the remaining scope can be delivered within the remaining budget and timescales, as MI resources are planned for other projects.

Dependencies

Definition and sign-off of requirements by MVM.

Outcome: MVM confirmed that this project will not go ahead. Tthe days will be made available to other programmes. 

 

Section Three: Projects in Progress

 

Project InfoProject Managers Commentary

SSG004 (AP12-928)

ESS Small Enhancements

Category: Funded

Milestones

 

Target dateTitleComplete
07-Jun-2013Project ClosureNo

RAG Status

GREEN

Report by Laura Bell for May 2013

Achievements in Last Period

Project aims for May were to:

  • Complete deployment of changes to TRN - the deployment was delayed to 24th May
  • Complete project closure; report issued and awaiting sign off

Issues

  • N/A

Next Steps

Project aims for May are to:

  • Complete project closure  

SSG007 (AP23-051)

ESS Small Group Functions

Category: Funded

Milestones

Target dateTitle
05-June-2013Phase1 DSOR : Deployment Sign Off Review
10-June-2013Close

RAG Status

GREEN

Report by Franck Bergeret for May 2013

Achievements in Last Period

  • Following the deployment of the code to Live on 26/4, all the ESS code (including ColdFusion code from previous SSG projects) was deployed to TRN (Training) environment and signed off. 

Issues

  • N/A

Next Steps

  • Deployment Sign Off (DSOR) and Close project

SSG008 (AP23-051)

ESS Functions for PGT

Category: Funded

Milestones

 

RAG Status

GREEN

Report by Franck Bergeret for May 2013

Achievements in Last Period

  • Build review completed.
  • Integration Test completed

 Issues

  • N/A

Next Steps

  • Function Testing
  • User Acceptance Testing

SSG009 (AP23-051)

ESS Architecture Review

Category: Funded

Milestones

31-May-20131 Review current architecture of Personal Tutors system
31-May-20132. Review St. Andrews system
31-May-20133.Review School of Physics & Astronomy system
27-Jun-20134 Review JASIG Student Success Plan
28-Jun-20135.Architecture for in-year assessments
31-Jul-2013Close

 

RAG Status

GREEN

Report by Franck Bergeret for May 2013

Achievements in Last Period

Issues

  • N/A 

Next Steps

  • Produce and review report for the first three deliverables
  • Meeting to review JASIG Student Success Plan software (4th Deliverable)

SSG010

ESS Small Enhancements

Category: Funded

Milestones

 

Target dateTitle
17-May-2013Project Brief - End of Planning
10-Jun-2013PPDR - Design Review
10-Jun-2013PPAR - Analysis Review
28-Jun-2013PPBR - Build Review
17-Jul-2013ASOR - User Acceptance Review

RAG Status

GREEN

Report by Laura Bell for May 2013

Achievements in Last Period

  • Project initiated
  • Scope and plan of delivery agreed; Project Brief signed off
  • Analysis commenced

Issues

None

Next Period

  • Complete analysis and sign off design
  • Complete Build

Section Four: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary

SSG001 (AP12-928)

Initial ESS IT Tools

Category: Discretionary, Funded

Report by Sheila Fraser

This project was closed on 19-Feb-13.

Please see the Completion Report for further information.

SSG005 (AP23-051)

ESS Meetings in Calendar

Category: Funded

Report by Franck Bergeret

This project was closed on 03-Apr-13.

Please see the Completion Report for further information

SSG006 (AP23-051)

ESS Photos for Students

Category: Funded

Report by Laura Bell

This project was closed on 15-May-2013.

Please see Completion Report for further information.

 

 

 

Documentation

Not available.