Report for December 2019
- Report Date
- December 2019
***DRAFT***
Report compiled by Muriel Mewissen (IS Apps Programme Manager) for Jim McGeorge (USG), Kate Brook (D&A), Jenny Shaw (D&A), Gillian Simmons (SRA), Jim Galbraith (GaSP) and other interested business area owners.
Section One: Programme Commentary, RAG and Resources Update
Commentary
During Decber
All projects are reporting a GREEN RAG status. The overall USG Other Programme status is GREEN.
Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.
Forward Look - December 2019
Resources to end December 2019
The budget for session 2019/20 is currently 285 days:
- 160 days for USG portfolio projects
- 90 days for the USG portfolio management
- 35 days of Core funded contingency
Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
|---|---|
| AP90-038 Clearing 2019 | To be started in March 2020. |
Section Three: Projects in Progress
|
Project Info |
Project Managers Commentary | ||||||||||||||
|
USG012 ThankQ Infrastructure Upgrade
Category: Discretionary
These milestones are now out of date - once we know how to proceed with the procurement we can reschedule the dates
RAG StatusRED |
Report by Sue Woodger for December 2019Achievements this period
Issues
See notes of meeting 5 December and piccl 10 Next Steps
Commentary: Project is RED as no supplier passed the mandatory question sets therefore we have no suppliers to take into the next round of evaluation. Impact: Procurement has been put on hold until we can find a way forward. Plan: Has been escalated to Gavin McLachlan on how to take forward |
||||||||||||||
|
USG014 Development and Alumni CRM Procurement
Category: Discretionary
RAG StatusGREEN |
Report by Ben Armstrong for November 2019Achievements this periodIssuesNext Steps |
Section Four: Closed or Withdrawn Projects
| Project Info | Project Manager's Commentary |
|---|---|
| USG013 Clearing 2019 | This project was started in March 2019 and was closed on the 25 October 2019. The Closure Report is available to view. |