Report for October 2019
- Report Date
- October 2019
Report compiled by Muriel Mewissen (IS Apps Programme Manager) for Jim McGeorge (USG), Kate Brook (D&A), Jenny Shaw (D&A), Gillian Simmons (SRA), Jim Galbraith (GaSP) and other interested business area owners.
Section One: Programme Commentary, RAG and Resources Update
Commentary
During October, one project was successfully closed - USG013 Clearing 2019. In USG014 Development and Alumni CRM Procurement , the procurement is progressing well with the tender going live on Public Contracts Scotland site. Closure report is being reviewed witrh a slight delay due to availablibility in USG012 ThankQ Infrastructure Upgrade.
The overall USG Other Programme status is GREEN.
Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.
Forward Look - October 2019

Resources to end October 2019

The budget for session 2019/20 is currently 285 days:
- 160 days for USG portfolio projects
- 90 days for the USG portfolio management
- 35 days of Core funded contingency
Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
|---|---|
| AP90-038 Clearing 2019 | To be started in March 2020. |
Section Three: Projects in Progress
|
Project Info |
Project Managers Commentary | ||||||||||||
|
USG012 ThankQ Infrastructure Upgrade
Category: Discretionary
RAG StatusAMBER |
Report by Chris Konczak for October 2019Achievements in Last Period
Issues
Next Steps
|
||||||||||||
|
Category: Compliance
RAG StatusClosed |
Report by Victoria Weinsberg for October 2019Achievements in Last Period
Next Steps
|
||||||||||||
|
USG014 Development and Alumni CRM Procurement
Category: Discretionary
RAG StatusGREEN |
Report by Ben Armstrong for October 2019Achievements this period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Manager's Commentary |
|---|---|
| This project was started in March 2019 and was closed on the 25 October 2019. The Closure Report is available to view. |