Report for June 2019

Report Date
June 2019
Report compiled by Muriel Mewissen (IS Apps Programme Manager) for Jim McGeorge (USG), Kate Brook (D&A), Jenny Shaw (D&A), Gillian Simmons (SRA), Jim Galbraith (GaSP) and other interested business area owners.
 

Section One: Programme Commentary, RAG and Resources Update

Commentary

During June, planning for USG013 Clearing 2019 was completed. We note a change of scope from last year clearing project USG010 Clearing 2018: There will be no central rUK clearing but Scottish Clearing will include an additional information line for prospective applicants.

USG012 ThankQ Infrastructure Upgrade was delayed as more technical input was required. This impacted on the timeline and required rescheduling of internal and supplier resources. As a result this project will extend into next session with closure schedule for early September. 

USG014 Development and Alumni CRM Procurement is progressing according to plan.

All projects are reporting a GREEN RAG status. The overall USG Other Programme status is GREEN.

Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.

 

Forward Look - June 2019

 

Resources to end June 2019

The budget for session 2018/19 is currently 270 days:

  • 166 days for USG portfolio projects
  • 104 days for the USG portfolio management

 

Section Two: Projects Not Started

All projects for this session have been started.

 

Section Three: Projects in Progress

 

Project Info

Project Managers Commentary

USG012 ThankQ Infrastructure Upgrade

 

Category: Discretionary

Milestones

Target Date Title
28-Jun-2019 Planning sign off
12-Jul-2019 Infrastructure set up complete
23-Aug-2019 Acceptance Sign Off
28-Aug-2019 Deploy to LIVE
16-Sep-2019 Deployment Sign Off Review
23-Sep-2019 Closure
RAG Status

GREEN

Report by Chris Konczak for June 2019

Achievements in Last Period

  • Milestone changes approved for Access to complete in August 2019
  • Brief updated and circulated for approvals
  • Analysis of VM specification requirements completed
  • VM Servers ordered and are available
  • Build of TEST and LIVE servers underway

Issues

  • TAD out of date which has delayed progress and required a re-booking of Access Group and IS Resources.

Next Steps​

  • Complete the build of the TEST and LIVE servers

USG013 Clearing 2019

 

Category: Compliance

Milestones

Target Date Title
21-Jun-2019 Information Pack - Sign Off
21-Jun-2019 Telephony Network - Sign Off
21-Jun-2019 Location / Room - Sign Off
28-Jun-2019 Call Center Staff Recruited
28-Jun-2019 SharePoint Site Up and Running
09-Jul-2019 Scottish Scripts and Call Flow Sign Off
12-Jul-2019 UAT Sign Off for SIMD Check Tool to University Web Site (For Prospective Applicants)
26-Jul-2019 Deploy SIMD Check Tool to University Web Site (For Prospective Applicants)
30-Jul-2019 Staff Communications Issued
31-Jul-2019 Telephony Set Up
02-Aug-2019 Telephony Testing
02-Aug-2019 Scottish Clearing Training Complete
02-Aug-2019 Readiness for Scottish Clearing Sign Off
05-Aug-2019 Telephony - Final Load Test
05-Aug-2019 A level / International Training Completed
06-Aug-2019 UCAS Clearing - Scotland

 12-Aug-2019

Readiness for A Level / International Clearing Sign Off
15-Aug-2019 UCAS Clearing rUK
19-Aug-2019 Remove Clearing Infrastructure
30-Aug-2019 Debrief / Closure Meeting
13-Sep-2019 Closure
RAG Status

GREEN

Report by Victoria Weinsberg for June 2019

Achievements in Last Period

  • First combined meeting for Embargo & Clearing with all Stakeholders took place in order to discuss further steps
  • Development of the SharePoint Site was initiated
  • All Meetings within the Clearing Period are set up
  • Project Brief was signed off

Issues

  • SharePoint Development might primarily be conductible in June due to the limited availability of the resources from July onwards

Next Steps​

  • Further clarification and finalisation of the required SharePoint Development required
  • Project Services Intern to start SharePoint training to potentially be able to cover

USG014 Development and Alumni CRM Procurement

 

Category: Discretionary

Milestones

Target Date Title
12-Jul-2019 Procurement Strategy, including Core Systems approval
09-Aug-2019 Requirements Specification
04-Nov-2019 Contract Award completed
29-Nov-2019 Delivery (Contract signed)
31-Jan-2020 Closure
RAG Status

GREEN

Report by Ben Armstrong for June 2019

Achievements this period

  • Completed market engagement
  • Drafted options paper to inform procurement strategy and seek approval from Core Systems Board and other project stakeholders

Issues

  • None noted

Next Steps

  • Present options paper to Core Systems Programme Board
  • Write procurement strategy
  • Begin to draft requirements specification

 

Section Four: Closed or Withdrawn Projects

Project Info Project Manager's Commentary
USG011 Legal Services SharePoint Site This project was started in February 2018 and was closed on the 26 April 2019. The Closure Report is available to view.
USG010 Clearing 2018 This project was started in March 2018 and was closed on the 21 September 2018. The Completion Report is available to view.
Programme Status
Has formal escalation taken place?
No

Documentation

Not available.