Report for May 2019
- Report Date
- May 2019
Report compiled by Muriel Mewissen (IS Apps Programme Manager) for Jim McGeorge (USG), Kate Brook (D&A), Jenny Shaw (D&A), Gillian Simmons (SRA), Jim Galbraith (GaSP) and other interested business area owners.
Section One: Programme Commentary, RAG and Resources Update
Commentary
During May, work progressed across the programme, with planning for both USG012 ThankQ Infrastructure Upgrade and USG013 Clearing 2019 in the approval stage.
USG012 ThankQ Infrastructure Upgrade continues to report an AMBER RAG status following delay in completing planning. The timeline is under revision. All other projects are GREEN.
The overall USG Other Programme status is GREEN.
Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.
Forward Look - May 2019

Resources to end May 2019
The budget for session 2018/19 is now confirmed as 210 days:
- 106 days for USG portfolio projects
- 104 days for the USG portfolio management
Section Two: Projects Not Started
All projects for this session have been started.
Section Three: Projects in Progress
|
Project Info |
Project Managers Commentary | ||||||||||||||||
|
USG012 ThankQ Infrastructure Upgrade
Category: Discretionary
RAG StatusAMBER |
Report by Chris Konczak for May 2019Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||
|
Category: Compliance
RAG StatusGREEN |
Report by Victoria Weinsberg for May 2019Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||
|
USG014 Development and Alumni CRM Procurement
Category: Discretionary
RAG StatusGREEN |
Report by Ben Armstrong for May 2019Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Manager's Commentary |
|---|---|
| USG011 Legal Services SharePoint Site | This project was started in February 2018 and was closed on the 26 April 2019. The Closure Report is available to view. |
| USG010 Clearing 2018 | This project was started in March 2018 and was closed on the 21 September 2018. The Completion Report is available to view. |