Report for May 2019

Report Date
May 2019
Report compiled by Muriel Mewissen (IS Apps Programme Manager) for Jim McGeorge (USG), Kate Brook (D&A), Jenny Shaw (D&A), Gillian Simmons (SRA), Jim Galbraith (GaSP) and other interested business area owners.
 

Section One: Programme Commentary, RAG and Resources Update

Commentary

During May, work progressed across the programme, with planning for both USG012 ThankQ Infrastructure Upgrade and USG013 Clearing 2019 in the approval stage.

USG012 ThankQ Infrastructure Upgrade continues to report an AMBER RAG status following delay in completing planning. The timeline is under revision. All other projects are GREEN.

The overall USG Other Programme status is GREEN.

Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.

 

Forward Look - May 2019

 

Resources to end May 2019

The budget for session 2018/19 is now confirmed as 210 days:

  • 106 days for USG portfolio projects
  • 104 days for the USG portfolio management

 

Section Two: Projects Not Started

All projects for this session have been started.

 

Section Three: Projects in Progress

 

Project Info

Project Managers Commentary

USG012 ThankQ Infrastructure Upgrade

 

Category: Discretionary

Milestones

Planning sign off 12-Jun-2019
Infrastructure set up complete 21-Jun-2019
Integration testing complete 28-Jun-2019
Acceptance Sign Off 12-Jul-2019
Deploy to LIVE 16-Jul-2019
Deployment Sign Off Review 30-Jul-2019
Closure 02-Aug-2019
RAG Status

AMBER

Report by Chris Konczak for May 2019

Achievements in Last Period

  • Agreement that Access Group are to perform the application install and data migration. They have been booked to begin on 24/06/2019.
  • UoE to provide and configure the VM servers
  • Project brief re-written for our current plan
  • Project milestones have been replanned and resourcing has been secured.

Issues

  • Project planning milestone to be approved

Next Steps​

  • Change planning milestone
  • Project brief to be circulated for approval
  • Circulate for final signoff
  • Analysis completed of VM spec
  • Order VMs for TEST and LIVE
  • Access to commence the application install and database migration 

USG013 Clearing 2019

 

Category: Compliance

Milestones

Target Date Title
21-Jun-2019

End of Planning

RAG Status

GREEN

Report by Victoria Weinsberg for May 2019

Achievements in Last Period

  • Kick Off Meeting with SRA & Colleges took place in order to discuss potential changes and additional requirements
  • Project Brief drafted

Issues

  • Project Brief final sign off and approval delayed due outstanding discussions with regard to Telephone licenses required, final requirement definition and absences of responsible parties.
  • SharePoint Development might primarily be conductible in June due to the limited availability of the resources from July onwards

Next Steps​

  • Finalisation of requirements, submission and sign off of project brief
  • Kick off for SharePoint Development
  • Regular Meetings to start taking place from Mid June 2019 fortnightly

USG014 Development and Alumni CRM Procurement

 

Category: Discretionary

Milestones

Target Date Title
30-May-2019 Supplier PIN related demos completed
28-Jun-2019 Market Engagement completed
12-Jul-2019 Procurement Strategy, including Core Systems approval
09-Aug-2019 Requirements Specification
04-Nov-2019 Contract Award completed
29-Nov-2019 Delivery (Contract signed)
31-Jan-2020 Closure
RAG Status

GREEN

Report by Ben Armstrong for May 2019

Achievements in Last Period

  • Completed project planning stage
  • Reviewed PIN notes of interest from suppliers; decided which suppliers to invite to system demonstrations
  • Completed five system demonstrations with suppliers from May 28th - 30th

Issues

  • None

Next Steps​

  • Complete market engagement
  • Write options paper to inform procurement strategy and seek approval from Core Systems Board and other project stakeholders
  • Begin to draft procurement strategy

 

Section Four: Closed or Withdrawn Projects

Project Info Project Manager's Commentary
USG011 Legal Services SharePoint Site This project was started in February 2018 and was closed on the 26 April 2019. The Closure Report is available to view.
USG010 Clearing 2018 This project was started in March 2018 and was closed on the 21 September 2018. The Completion Report is available to view.
Programme Status
Has formal escalation taken place?
No

Documentation

Not available.