Report for April 2019

Report Date
April 2019
Report compiled by Muriel Mewissen (IS Apps Programme Manager) for Jim McGeorge (USG), Kate Brook (D&A), Jenny Shaw (D&A), Gillian Simmons (SRA), Jim Galbraith (GaSP) and other interested business area owners.
 

Section One: Programme Commentary, RAG and Resources Update

Commentary

During April, work in USG011 Legal Services SharePoint Site formally completed on 19 April and the project was closed on 26 April 2019. The Closure Report is now available to view.

The new project to replace the D& A ThankQ platform, USG014 Development and Alumni CRM Procurement, officially started on 19 April 2019. Good progress have been made with the Prior Information Notice (PIN) already published, and planning completed.

The project to upgrade the ThankQ server, USG012 ThankQ Upgrade, is reporting an AMBER RAG status following delays in obtaining estimation figures from the technical development team and pressure on PM limiting availability which has been resolved. All other projects are GREEN.

The overall USG Other Programme status is GREEN.

Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.

 

Forward Look - April 2019

 

Resources to end April 2019

The budget for session 2018/19 is now confirmed as 210 days:

  • 106 days for USG portfolio projects
  • 104 days for the USG portfolio management

 

Section Two: Projects Not Started

All projects for this session have been started.

 

Section Three: Projects in Progress

 

Project Info

Project Managers Commentary

USG011 Legal Services SharePoint Site

 

Category: Discretionary

Milestones

 

RAG Status

BLUE

Report by Geoff Cropley for April 2019

Achievements

  • Project delivered with closure formally approved on the 26 April 2019.

  • The Closure Report is available to view.

Next steps

  • None

USG012 ThankQ Upgrade

 

Category: Discretionary

Milestones

Target Date Title
28-Feb-2019 Planning sign off
RAG Status

AMBER

Report by Chris Konczak for April 2019

Achievements in Last Period

  • No progress

Issues

  • Dev Tech were booked to complete an analysis phase but due to a lack of their availability this has not been completed.
  • Project has not been able to progress due to lack of Project Manager availability (now resolved)

Next Steps​

  • Analysis to be completed
  • PICCL the planning milestone change
  • Update the project brief
  • Circulate for final signoff.

USG013 Clearing 2019

 

Category: Compliance

Milestones

Target Date Title
06-May-2019

End of Planning

RAG Status

GREEN

Report by Victoria Weinsberg for April 2019

Achievements

  • Securing SharePoint Development Resource for 10 days in the time between May - Aug 2019
  • College Representatives and new Communication Rep clarified

Issues

  • n/a

Next steps

  • Meeting with College Representatives, SRA, PM and SharePoint Development Resource Mid May
  • Regular Meetings to start taking place from Mid June 2019 forthnightly
  • Completion of Planning  

USG014 Development and Alumni CRM Procurement

 

Category: Discretionary

Milestones

Target Date Title
30-Apr-2019 Planning
30-May-2019 Supplier PIN related demos completed
28-Jun-2019 Market Engagement completed
12-Jul-2019 Procurement Strategy, including Core Systems approval
09-Aug-2019 Requirements Specification
04-Nov-2019 Contract Award completed
29-Nov-2019 Delivery (Contract signed)
31-Jan-2020 Closure
RAG Status

GREEN

Report by Ben Armstrong for April 2019

Achievements this period

  • Held a project kick-off meeting to run through project objectives and organisation
  • Project brief circulated and signed off by project stakeholders
  • Prior Information Notice (PIN) issued on Public Contracts Scotland site; this includes a high level requirements summary

Issues

  • None noted

Next Steps

  • Complete project planning stage
  • Review PIN notes of interest from suppliers; decide which suppliers to invite to system demonstrations
  • Complete system demonstrations with suppliers (slots booked for May 28th - 30th)

 

Section Four: Closed or Withdrawn Projects

Project Info Project Manager's Commentary
USG011 Legal Services SharePoint Site This project was started in February 2018 and was closed on the 26 April 2019. The Closure Report is available to view.
USG010 Clearing 2018 This project was started in March 2018 and was closed on the 21 September 2018. The Completion Report is available to view.
Programme Status
Has formal escalation taken place?
No

Documentation

Not available.