Report for February 2019
- Report Date
- February 2019
Report compiled by Muriel Mewissen (IS Apps Programme Manager) for Jim McGeorge (USG), Kate Brook (D&A), Jenny Shaw (D&A), Stefan Kaempf (IS Applications), Ian Sutherland (SRA), Jim Galbraith (GaSP) and other interested business area owners.
Section One: Programme Commentary, RAG and Resources Update
Commentary
During February, planning for USG012 ThankQ Upgrade continues to be slow and reports an AMBER RAG status due to technical input being required to additional scope. USG011 Legal Services SharePoint Site is paused while awaiting development by Service Management on SharePoint planned for 8 March.
The overall USG Other Programme status is GREEN.
Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.
Forward Look - February 2019

Resources to end February 2019
The budget for session 2018/19 is now confirmed as 210 days:
- 106 days for USG portfolio projects
- 104 days for the USG portfolio management
Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
|---|---|
| AP89-930 Clearing 2019 | To be started in March 2019. |
Section Three: Projects in Progress
|
Project Info |
Project Managers Commentary | ||||||||||
|
USG011 Legal Services SharePoint Site
Category: Discretionary
RAG StatusGREEN |
Report by Geoff Cropley for February 2019Achievements
Issues
Next steps
|
||||||||||
|
Category: Discretionary
RAG StatusAMBER |
Report by Chris Konczak for February 2019Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Manager's Commentary |
|---|---|
| USG010 Clearing 2018 | This project was started in March 2018 and was closed on the 21 September 2018. The Completion Report is available to view. |