Report for November 2018

Report Date
November 2018

Report compiled by Muriel Mewissen (IS Apps Programme Manager)

for Jim McGeorge (USG), Kate Brook (D&A), Jenny Shaw (D&A), Stefan Kaempf (IS Applications), Ian Sutherland (SRA), Jim Galbraith (GaSP) and other interested business area owners.
 

Section One: Programme Commentary, RAG and Resources Update

Commentary

During November, the planning for USG012 ThankQ Upgrade had to be delayed while awaiting confirmation on the procurement decision and timeframe to replace ThankQ. The procurement of a new application has been agreed and the scope of this project will be changed to deliver any essential upgrades to support the current solution for the next two years. 

A new timeline has been agreed for USG011 Legal Services SharePoint Site with delivery planed for March 2019 and closure in April 2019.

The overall USG Other Programme status is GREEN.

Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.

 

Forward Look - November 2018

 

Resources to end November 2018

The budget for session 2018/19 is now confirmed as 210 days:

  • 106 days for USG portfolio projects
  • 104 days for the USG portfolio management

 

Section Two: Projects Not Started

Project Info Programme Manager's Commentary
AP89-930 Clearing 2019 To be started in March 2019.

 

Section Three: Projects in Progress

 

Project Info

Project Managers Commentary

USG011 Legal Services SharePoint Site

 

Category: Discretionary

Milestones

Target Date Title
21-Dec-2018 UAT Complete
28-Feb-2019 Migration
29-Mar-2019 Go Live
12-Apr-2019 Closure Report
RAG Status

AMBER

Report by Geoff Cropley for November 2018

Achievements in Last Period

  • Delivery milestone has been missed as the result of SharePoint resource contention from higher priority projects.  A re-planning exercise has been completed, see PICCL 9: Delayed Delivery and Closure, to identify revised delivery and closure milestones.
  • Support for SharePoint work for this the project is contributed by Service Management. There are three days left available in the budget to complete project closure activities. 

Issues

  • None

Next steps

  • Complete bug fixing and minor changes
  • Schedule a further round of UAT

 

USG012 ThankQ Upgrade

 

Category: Discretionary

Milestones

Target Date Title
25-Jan-2019 Planning sign off
RAG Status

GREEN

Report by Chris Konczak for November 2018

Achievements in Last Period

  • Draft of NCA for two year extension for access group (ThankQ Supplier) submitted for approval

Issues

  • Development & Alumni have confirmed they will go out to open procurement for replacement to ThankQ starting in January 2019. Impact of this decision is that the scope for USG012 will be reduced to essential infrastructure changes to support the existing version of ThankQ (client server v 8.5) for the next two years. The planning was delayed until this decision was confirmed, see PICCL 1:  Change of planning milestone.

Next Steps​

  • Agree new scope with the business
  • Commence with brief write up

 

Section Four: Closed or Withdrawn Projects

Project Info Project Manager's Commentary
USG010 Clearing 2018 This project was started in March 2018 and was closed on the 21 September 2018. The Completion Report is available to view.
Programme Status
Has formal escalation taken place?
No

Documentation

Not available.