Report for October 2018
- Report Date
- October 2018
Report compiled by Muriel Mewissen (IS Apps Programme Manager)
for Jim McGeorge (USG), Kate Brook (D&A), Jenny Shaw (D&A), Stefan Kaempf (IS Applications), Ian Sutherland (SRA), Jim Galbraith (GaSP) and other interested business area owners.
Section One: Programme Commentary, RAG and Resources Update
Commentary
During October, the planning for USG012 ThankQ Upgrade is progressing to plan. However, the developments for Legal Services SharePoint Site continue to be hampered by lack of resources availability in the SharePoint service management team. The project is waiting for resources to be confirmed in order to reschedule the delivery and closure milestones. The project status is AMBER.
The overall USG Other Programme status is GREEN.
Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.
Forward Look - October 2018

Resources to end October 2018

The budget for session 2018/19 is now confirmed as 210 days:
- 106 days for USG portfolio projects
- 104 days for the USG portfolio management
Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
|---|---|
| AP89-930 Clearing 2019 | To be started in March 2019. |
Section Three: Projects in Progress
|
Project Info |
Project Managers Commentary | ||||||||||
|
USG011 Legal Services SharePoint Site
Category: Discretionary
RAG StatusAMBER |
Report by Geoff Cropley for October 2018Achievements
Issues
Next steps
|
||||||||||
|
Category: Discretionary
RAG StatusGREEN |
Report by Chris Konczak for October 2018Achievements this Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Manager's Commentary |
|---|---|
| USG010 Clearing 2018 | This project was started in March 2018 and was closed on the 21 September 2018. The Completion Report is available to view. |
