Report for October 2018

Report Date
October 2018

Report compiled by Muriel Mewissen (IS Apps Programme Manager)

for Jim McGeorge (USG), Kate Brook (D&A), Jenny Shaw (D&A), Stefan Kaempf (IS Applications), Ian Sutherland (SRA), Jim Galbraith (GaSP) and other interested business area owners.
 

Section One: Programme Commentary, RAG and Resources Update

Commentary

During October, the planning for USG012 ThankQ Upgrade is progressing to plan. However, the developments for Legal Services SharePoint Site continue to be hampered by lack of resources availability in the SharePoint service management team. The project is waiting for resources to be confirmed in order to reschedule the delivery and closure milestones. The project status is AMBER.

The overall USG Other Programme status is GREEN.

Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.

 

Forward Look - October 2018

 

Resources to end October 2018

The budget for session 2018/19 is now confirmed as 210 days:

  • 106 days for USG portfolio projects
  • 104 days for the USG portfolio management

 

Section Two: Projects Not Started

Project Info Programme Manager's Commentary
AP89-930 Clearing 2019 To be started in March 2019.

 

Section Three: Projects in Progress

 

Project Info

Project Managers Commentary

USG011 Legal Services SharePoint Site

 

Category: Discretionary

Milestones

Target Date Title
18-Jul-2018 UAT Complete
TBC Migration
TBC Go Live
TBC Closure Report
RAG Status

AMBER

Report by Geoff Cropley for October 2018

Achievements

  • User acceptence testing (UAT) has completed and a system demonstration to the stakeholder was positively received.  A number of bug fixes are required and some minor changes are required prior to system migration.  Further testing will be scheduled when these changes are complete. More significant changes will be handled as service requests when live. High level forcast migration dates is mid-November.  This needs to be confirmed when key resource is available week commencing 8th October.  
  • Following the project delays,  work to complete the migration to live will continue and this will be funded by the remaining project days and from the service budget. Where necessary the sponsor may be asked for additional funding to complete the tasks.
  • An issue has been opened to reflect this position.

Issues

  • None

Next steps

  • Complete bug fixing and minor changes
  • Schedule a further round of UAT
  • Migration re-plan expected week commencing 8th October
  • Raise change request to move project end dates

 

USG012 ThankQ Upgrade

 

Category: Discretionary

Milestones

Target Date Title
23-Nov-2018 Planning
RAG Status

GREEN

Report by Chris Konczak for October 2018

Achievements this Period

  • Meeting held with business and supplier to scope project.
  • Procurement meeting held with development and Alumni to discuss cloud hosting solution

Issues

  • None

Next Steps

  • Complete brief and circulate brief for approval

 

Section Four: Closed or Withdrawn Projects

Project Info Project Manager's Commentary
USG010 Clearing 2018 This project was started in March 2018 and was closed on the 21 September 2018. The Completion Report is available to view.
Programme Status
Has formal escalation taken place?
No

Documentation

Not available.