Report for September 2018

Report Date
September 2018

Report compiled by Muriel Mewissen (IS Apps Programme Manager)

for Jim McGeorge (USG), Kate Brook (D&A), Jenny Shaw (D&A), Stefan Kaempf (IS Applications), Ian Sutherland (SRA), Jim Galbraith (GaSP) and other interested business area owners.
 

Section One: Programme Commentary, RAG and Resources Update

Commentary

During September, the USG010 project which successfully delivered support for Clearing 2018 was completed and the Completion Report is available to view.

As expected the project to support clearing in session 2018/19 has also been confirmed and is now included in the programme.

USG011 Legal Services SharePoint Site has a RED RAG status because delivery has been delayed due to a resource conflict in the SharePoint service management team. The project schedule is being revised and new milestone dates are still TBC.

The overall USG Other Programme status is GREEN.

Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.

 

Forward Look - September 2018

 

Resources to end September 2018

The budget for session 2018/19 is now confirmed as 210 days:

  • 106 days for USG portfolio projects
  • 104 days for the USG portfolio management

 

Section Two: Projects Not Started

Project Info Programme Manager's Commentary
N/A Final plan for session 2018/19 is yet to be confirmed.

 

Section Three: Projects in Progress

 

Project Info

Project Managers Commentary

USG011 Legal Services SharePoint Site

 

Category: Discretionary

Milestones

Target Date Title
18-Jul-2018 UAT Complete
TBC Migration
TBC Go Live
TBC Closure Report
RAG Status

RED

Report by Geoff Cropley for September 2018

Achievements

  • User acceptance testing (UAT) has completed and a system demonstration to the stakeholder was positively received.  A number of bug fixes are required and some minor changes are required prior to system migration.  Further testing will be scheduled when these changes are complete. More significant changes will be handled as service requests when live. High level forecast migration dates is mid-November.  This needs to be confirmed when key resource is available week commencing 8th October.  
  • Following the project delays,  work to complete the migration to live will continue and this will be funded by the remaining project days and from the service budget. Where necessary the sponsor may be asked for additional funding to complete the tasks.
  • An issue has been opened to reflect this position.

Issues

  • As the result of resource contention within service management for SharePoint development from higher priority projects the project will not complete by the planned date. An issues has been raised to reflect the current situation. A re-plan is underway to determine new delivery milestones.

Next steps

  • Complete bug fixing and minor changes
  • Schedule a further round of UAT
  • Migration re-plan expected week commencing 8th October

 

USG012 ThankQ Upgrade

 

Category: Discretionary

Milestones

Target Date Title
23-Nov-2018 Planning
RAG Status

GREEN

Report by Chris Konczak for September 2018

Achievements this Period

  • Meeting set up with Dev Tech, Production, business and the supplier to scope out the ThankQ upgrade
  • Quote for hosting proposal circulated to business and Dev Tech for review

Issues

  • None

Next Steps

  • Meet with business and supplier and scope out the project.
  • Begin the brief writeup
  • Milestones planned

 

Section Four: Closed or Withdrawn Projects

Project Info Project Manager's Commentary
USG010 Clearing 2018 This project was started in March 2018 and was closed on the 21 September 2018. The Completion Report is available to view.

 

Programme Status
Has formal escalation taken place?
No