Report for June 2018
- Report Date
- June 2018
Report compiled by Muriel Mewissen (IS Apps Programme Manager)
for Jim McGeorge (USG), Kate Brook (D&A), Jenny Shaw (D&A), Stefan Kaempf (IS Applications), Ian Sutherland (SRA), Jim Galbraith (GaSP) and other interested business area owners.
Section One: Programme Commentary, RAG and Resources Update
Commentary
During June 2018, work has progressed well over all the projects and the USG Other Programme status is GREEN:
- USG002 - GREEN - Delivery was achieved. The closure report is drafted and will be finalised and signed off following staff annual leave.
- USG010 - GREEN - Planning is done, and execution has started.
- USG011 - GREEN - Project resumed on the 18 June following suspension because of a resource conflict in the SharePoint service management team.
The budget for USG002 was reduced by 8 days, see USG002 PICCL 8. In turn, the programme budget was reduced by 8 days to 316 days, see PRICCL 112.
Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.
Forward Look - June 2018

Resources to end June 2018:

Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
|---|---|
| N/A | All planned projects are currently in progress. |
Section Three: Projects in Progress
|
Project Info |
Project Managers Commentary | ||||||||||||||||||||||||||||||||||||||
|
USG002 D&A - Compliance with PECR, Etherington & Data Protection Regulation
Category: Discretionary
RAG StatusGREEN
|
Report by David Watters for June 2018 Achievements
Issues
Next steps
|
||||||||||||||||||||||||||||||||||||||
|
Category: Discretionary
RAG StatusGREEN
|
Report by Emma McNab for June 2018 Achievements
Issues
Next steps
|
||||||||||||||||||||||||||||||||||||||
|
USG011 Legal Services SharePoint Site
Category: Discretionary
RAG StatusGREEN |
Report by Geoff Cropley for June 2018 Achievements
Issues
Next steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
|---|---|
|
AP78-092 Organisational Hierarchy Admin Page End of Life Updates Category: Compliance |
Report by Sheila Fraser This project was withdrawn on 06-Oct-17. |
|
Category: Discretionary |
Report by Emma McNab This project was closed on 15-Sep-17. Please see the Closure Report for further information. |
|
USG005 Student Alumni Platform Category: Discretionary |
Report by David Watters This project was closed on 18-Jan-18. Please see the Closure Report for further information. |
|
Category: Discretionary |
Report by Sheila Fraser This project was withdrawn on 02-Feb-18. |
|
USG008 USG End of Life Compliance - Analysis Category: Compliance |
Report by Sheila Fraser This project was closed on 07-Mar-18. Please see the Closure Report for further information. |
|
Multi-Project Balance Row USG Application, Infrastructure & Database End of Life Compliance Category: Compliance |
Report by Sheila Fraser This project was withdrawn on 09-Mar-18. |