Report for April 2018
- Report Date
- April 2018
Report compiled by Muriel Mewissen (IS Apps Programme Manager)
for Jim McGeorge (USG), Kate Brook (D&A), Jenny Shaw (D&A), Stefan Kaempf (IS Applications), Ian Sutherland (SRA), Jim Galbraith (GaSP) and other interested business area owners.
Section One: Programme Commentary, RAG and Resources Update
Commentary
Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.
Overall the USG Other Programme is AMBER, with three active projects, one delayed by external supplier (USG002) and one suspended (USG011) due to internal resource conflict. The utilisation rate remains low due to the slow progress in USG002 and USG011 as mentioned. USG010 recently started and work is expected to increase in coming weeks. The contingency held within the USG Other Programme (32d as programme contingency and 55d as portfolio contingency) is expected to be released in support of compliance work in Human Resources.
USG002 - AMBER - due to vendor not delivering on agreed date of 19-Mar-18, instead expecting to be now in early May with an expected knock-on delay to the closure date. Delivery ahead of 25-May-18 remains feasible and likely. While the risk remains for the potential that consent may need to be sought if legitimate interest is no longer a viable proposal this is now very low probability.
USG010 - GREEN - project initiated earlier than planned to enable the room allocation issue to be resolved: likely alternative space identified in Argyle House.
USG011 - SUSPENDED - Suspension due to resource conflict with higher priority projects.
Forward Look - April 2018

Resources to end April 2018:

Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
|---|---|
| N/A | All planned projects are currently in progress. |
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | |||||||||||||
|
Report by David Watters for April 2018 Achievements
Issues
Next steps
|
|||||||||||||
|
Report by Emma McNab for April 2018 Achievements
Issues
Next steps
|
|||||||||||||
|
Report by Geoff Cropley for April 2018 Achievements
Issues
Next steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
|---|---|
|
AP78-092 Organisational Hierarchy Admin Page End of Life Updates Category: Compliance |
Report by Sheila Fraser This project was withdrawn on 06-Oct-17. |
|
Category: Discretionary |
Report by Emma McNab This project was closed on 15-Sep-17. Please see the Closure Report for further information. |
|
USG005 Student Alumni Platform Category: Discretionary |
Report by David Watters This project was closed on 18-Jan-18. Please see the Closure Report for further information. |
|
Category: Discretionary |
Report by Sheila Fraser This project was withdrawn on 02-Feb-18. |
|
USG008 USG End of Life Compliance - Analysis Category: Compliance |
Report by Sheila Fraser This project was closed on 07-Mar-18. Please see the Closure Report for further information. |
|
Multi-Project Balance Row USG Application, Infrastructure & Database End of Life Compliance Category: Compliance |
Report by Sheila Fraser This project was withdrawn on 09-Mar-18. |
