March 2018
- Report Date
- March 2018
Report compiled by Sheila Fraser (IS Apps Programme Manager)
for Jim McGeorge (USG), Grant Spence (D&A), Jenny Shaw (D&A), Simon Raeside (Careers), Shelagh Green (Careers), Stefan Kaempf (IS Applications), Ian Sutherland (SRA), Jim Galbraith (GaSP) and other interested business area owners.
Section One: Programme Commentary, RAG and Resources Update
Commentary
Overall the USG Other Programme is GREEN, as it is expected that planned essential work can be completed in this year. This is GREEN with the note that the utilisation rate is low due to:
- The contingency held within the USG Other Programme (32d as programme contingency and 55d as portfolio contingency).
- Work started early in USG010, which will increase in the coming weeks.
- If the above items are removed from the budget the utilisation rate is running at 93% for the year to date.
USG002 - AMBER - due to vendor not delivering on agreed date of 19-Mar-18, instead expecting to be early April with an expected knock-on delay to the closure date. Delivery ahead of 25-May-18 remains feasible and likely. While the risk remains for the potential that consent may need to be sought if legitimate interest is no longer a viable proposal this is now very low probability.
USG010 - GREEN - project initiated earlier than planned to enable the room allocation issue to be resolved: likely alternative space identified in Argyle House.
USG011 - AMBER - delivery likely to be delayed due to under-estimation of work involved, increase in complexity of solution required, and prioritisation of GDPR SharePoint work. Risk of estimate increase.
USG008 - BLUE - Closed with a 1-slide summary here and the closure report here.
RAG & Forward Look

Resources to end of March 2017
In the table below the USG011 is showing as Not Started, this is erroneous, the project is In Progress, and will be rectified ahead of the next reporting period.

Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
| All planned projects are currently in progress. |
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|
USG002 D&A - Compliance with PECR, Etherington & Data Protection RegulationCategory: Discretionary Milestones
RAG StatusAMBER |
Report by David Watters for March 2018 Achievements
Issues
Next steps
|
||||||||||
USG011 Clearing 2018Category: Discretionary Milestones
RAG StatusGREEN |
Report by Emma McNab for March 2018 Achievements this Period
Issuesn/a Next Steps
|
||||||||||
USG011 Legal Services SharePoint SiteCategory: Discretionary Milestones
RAG StatusAMBER |
Report by Geoff Cropley for March 2018 Achievements
Issues
Next steps
|
Section Four: Closed or Withdrawn Projects
There are no projects that have been closed or withdrawn in 17/18 to date.
| Project Info | Project Managers Commentary |
|---|---|
|
AP78-092 Organisational Hierarchy Admin Page End of Life Updates Category: Compliance |
Report by Sheila Fraser This project was withdrawn on 06-Oct-17. |
|
Category: Discretionary |
Report by Emma McNab This project was closed on 15-Sep-17. Please see the Closure Report for further information. |
|
USG005 Student Alumni Platform Category: Discretionary |
Report by David Watters This project was closed on 18-Jan-18. Please see the Closure Report for further information. |
|
Category: Discretionary |
Report by Sheila Fraser This project was withdrawn on 02-Feb-18. |
|
USG008 USG End of Life Compliance - Analysis Category: Compliance |
Report by Sheila Fraser This project was closed on 07-Mar-18. Please see the Closure Report for further information. |
|
Multi-Project Balance Row USG Application, Infrastructure & Database End of Life Compliance Category: Compliance |
Report by Sheila Fraser This project was withdrawn on 09-Mar-18. |
| Attachment | Size |
|---|---|
| 24.4 KB | |
| 36.23 KB |
