January 2018
- Report Date
- January 2018
Report compiled by Sheila Fraser (IS Apps Programme Manager)
for Jim McGeorge (USG), Grant Spence (D&A), Jenny Shaw (D&A), Simon Raeside (Careers), Shelagh Green (Careers), Stefan Kaempf (IS Applications), Ian Sutherland (SRA), Jim Galbraith (GaSP) and other interested business area owners.
Section One: Programme Commentary, RAG and Resources Update
Commentary
Overall the USG Other Programme is GREEN, as it is expected that planned essential work can be completed in this year. This is GREEN with the note that the utilisation rate is low due to:
- Clearing work that is not due to start until May (35d).
- Work identified in USG008 to replace the Freedom of Information application, which will start as soon as possible when initiation is agreed (83d).
- An increase in contingency held within the USG Other Programme (32d as programme contingency and 55d as portfolio contingency).
- If the above 3 items are removed from the budget the utilisation rate is running at 104% for the year to date.
USG002 - AMBER - due to delivery date extension by 1 month to allow vendors to make last-minute changes in case of changes from ICO. The risk remains for the potential that consent may need to be sought if legitimate interest is no longer a viable proposal.
USG005 - DELIVERED - implementation project in progress as STU258.
USG008 - AMBER - late emerging issue with physical end of life of database server after completion of draft report and closure means analysis to be reviewed and potentially updated with slight delay to delivery of report and closure. No significant impact as the identified follow-on work is planned.
RAG & Forward Look

Resources to end of December 2017

Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
Multi-Project Balance Row USG Application, Infrastructure & Database End of Life ComplianceCompliance Planning: October 2017 Delivery: July 2018 RAG StatusAMBER |
PlanThere is a need to identify applications, databases and infrastructure which will come to the end of their working life in the next 3 years, and to plan upgrades, migrations or replacements accordingly. This work has started in October for business analysis in USG008. A number of areas for further work have been identified, and discussion is being undertaken on how best to undertake these. These will be initiated on a call-off basis from this balance row where a need is identified for work in 17/18 during USG008. This is AMBER due to the change in allocation from 153d to 83d as:
DependenciesClarity on end of life position from Production Management for each component of the architecture. Discussion with Service Excellence regarding planning and timelines for USG applications in SEP scope. |
Clearing 2018Compliance Planning: May 2018 Delivery: August 2018 RAG StatusGREEN |
PlanThe University will likely enter UCAS clearing again for 2018 with places being available to prospective students from Scotland and the rest of the UK (rUK) The project will start in May 2018 to ensure we are ready. DependenciesDecision from the University to enter Scottish and rUK Clearing in 2018. |
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | |||||||||
|---|---|---|---|---|---|---|---|---|---|---|
USG002 D&A - Compliance with PECR, Etherington & Data Protection RegulationCategory: Discretionary Milestones
RAG StatusAMBER |
Report by David Watters for January 2018 Achievements
Issues
Next steps
|
|||||||||
USG008 USG End of Life Compliance - AnalysisCategory: Compliance Milestones
RAG StatusAMBER |
Report by Sheila Fraser for January 2018 Achievements
Issues
Next steps
|
Section Four: Closed or Withdrawn Projects
There are no projects that have been closed or withdrawn in 17/18 to date.
| Project Info | Project Managers Commentary |
|---|---|
|
AP78-092 Organisational Hierarchy Admin Page End of Life Updates Category: Compliance |
Report by Sheila Fraser This project was withdrawn on 06-Oct-17. |
|
Category: Discretionary |
Report by Emma McNab This project was closed on 15-Sep-17. Please see the Closure Report for further information. |
|
USG005 Student Alumni Platform Category: Discretionary |
Report by David Watters This project was closed on 18-Jan-18. Please see the Closure Report for further information. |
|
Category: Discretionary |
Report by Sheila Fraser This project was withdrawn on 02-Feb-18. |
| Attachment | Size |
|---|---|
| 64.19 KB | |
| 54.06 KB |