August 2017

Report Date
August 2017

Report compiled by Sheila Fraser (IS Apps Programme Manager)

for Jim McGeorge (USG), Grant Spence (D&A), Jenny Shaw (D&A), Simon Raeside (Careers), Shelagh Green (Careers), Stefan Kaempf (IS Applications), Ian Sutherland (SRA), Jim Galbraith (GaSP) and other interested business area owners.

 

Section One: Programme Commentary, RAG and Resources Update

Commentary

Overall the USG Other Programme is GREEN, as the expected projects are all on track. There is a potential small project with Records Management to ensure compliance for FOI that has yet to be confirmed.

USG002 - GREEN - the Information Commissioner's Office is still not yet able to answer whether the University will be considered a public body, but a strong indication has been given that HEIs can use the basis of legitimate interest. The project will proceed with legitimate interest as the working principle, and risks raised for the potential that consent may need to be sought if this should change.

USG005 - The Student Alumni Platform project is GREEN, with the responses evaluated and a recommendation made for board approval. The follow-on project of 50d for the implementation is currently expected in 17/18.

USG006 - The Clearing 2017 project is GREEN, the rUK Clearing was completed successfully on 17th August and the project is now moving to closure.

There was a project originally anticipated in the 17/18 plan for Records Management - Request Handling Monitor Updates that can actually be done in 18/19 and so is in the plan for 18/19. As a result, there may be changes needed to the current FOI application that are required ahead of the May 18 GDPR deadline. This need is currently being investigated, and may result in a small project to make changes to the current application. This may be undertaken within the STU programme.

RAG & Forward Look

Resources to end of August 2017

 

Section Two: Projects Not Started

Project Info Programme Manager's Commentary

Organisational Hierarchy Admin Page End of Life Updates

Compliance

Planning: August 2017

Delivery: TBC in 17/18

RAG Status

GREEN

Plan

The administration pages for the Organisational Hierarchy application run on a java applet that requires an old browser to be used. As this browser is going out of support, we require the administration pages to be revisited, and an alternative method for the administration of the Organisational Hierarchy pages. This project will determine the approach and implement those changes so that changes to the Organisational Hierarchy can continue to be made.

An initial investigation has determined a potential solution, which is currently being tested. If successful this may not require a full project. Note however, that there may be additional work for the FOI application, which would require a project and would be considered to replace this one.

Dependencies

None known.

USG Application, Infrastructure & Database End of Life Compliance

Compliance

Planning: October 2017

Delivery: July 2018

RAG Status

AMBER

Plan

There is a need to identify applications, databases and infrastructure which will come to the end of their working life in the next 3 years, and to plan upgrades, migrations or replacements accordingly.

This project is expected to start around October for business analysis, however this could be started sooner or later to enable smoothing of resource demand where appropriate. The status is AMBER due to the need to clarify which applications require to be reviewed.

Dependencies

Clarity on end of life position from Production Management for each component of the architecture.

A view of future work from Service Excellence would also be helpful though not essential for this work to start.

USG Business Support

Discretionary

Planning: November 2017

Delivery: July 2018

RAG Status

GREEN

Plan

This project is to provide a basis of days on which a call-off can be made for areas of priority for USG, in a similar manner to that of the ring-fence for the Colleges. As such there is no immediate clarity on the scope, this is most likely to be a number of small pieces of business analysis, with potential follow-on work dependent on the outcomes of the analyses.

This is GREEN as the work is expected to be small, and to fit in with other work as appropriate.

Dependencies

None known.

Clearing 2018

Compliance

Planning: May 2018

Delivery: August 2018

RAG Status

GREEN

Plan

The University will likely enter UCAS clearing again for 2018 with places being available to prospective students from Scotland and the rest of the UK (rUK)

The project will start in May 2018 to ensure we are ready.

Dependencies

Decision from the University to enter Scottish and rUK Clearing in 2018.

 

Section Three: Projects in Progress

Project Info Project Managers Commentary

USG005 Student Alumni Platform

Category: Discretionary

Milestones

06-Sep-2017 Award Decision
03-Oct-2017 Contract Negotiations completed - Award made
17-Oct-2017 Closure report completed

RAG Status

GREEN

Report by David Watters for August 2017

Achievements

  • Scoring of bids finalised
  • Consensus meeting held mid-August
  • Recommendation made to project board

Issues

  • None

Next steps

  • Work with project board and Procurement on commercial negotiations
  • Work through post-ITT checklist
  • Plan for follow-on implementation project

USG006 Clearing 2017

Category: Discretionary

Milestones

15-September-17 Closure

RAG Status

GREEN

 

Report by Emma McNab - August 2017

Achievements this Period

  • Finalise training
  • Call centre go live for Scottish Clearing
  • SIMD taken down
  • Call centre go live for rUK SIMD
  • Telephony taken down

Issues

  • None

Next Steps

  • Closure

USG002 D&A - Compliance with PECR, Etherington & Data Protection Regulation

Category: Discretionary

Milestones

11-Sep-2017 End of Planning Plan

RAG Status

GREEN

Report by David Watters for August 2017

Achievements

  • Continued work on project brief, estimations and planning
  • Further consultations with business partners

Issues

  • None

Next steps

  • Completion and sign-off of project brief
  • Commence business analysis with business partners

 

 

Section Four: Closed or Withdrawn Projects

There are no projects that have been closed or withdrawn in 17/18 to date.

AttachmentSize
Image icon usg_resources_aug_17.png42.15 KB
Image icon usg_rag_aug_17.png34.83 KB

Documentation