May 2017

Report Date
May 2017

Report compiled by Sheila Fraser (IS Apps Programme Manager)

for Jim McGeorge (USG), Grant Spence (D&A), Jenny Shaw (D&A), Simon Raeside (Careers), Shelagh Green (Careers), Stefan Kaempf (IS Applications), Ian Sutherland (SRA) and other interested business area owners.

 

Section One: Programme Commentary, RAG and Resources Update

Commentary

The University has determined that it will enter the clearing process again this year. USG006 has been initiated as "Clearing 2017" to support this with Emma McNabb identified as Project Manager.

The D&A Compliance with PECR, Etherington and GDPR (USG002) initiation remains expected in July because the Information Commissioner's Office is still not yet able to answer whether the University will be considered a public body. The D&A team are working with other institutions to jointly petition the ICO for clarity. Risk12 has been raised in relation to the portfolio budget for 17/18 due to this delay.

AP67-071 / USG003 - The USG Application, Infrastructure & Database End of Life Compliance analysis will start shortly as USG003, with the decision on the approach for how to update the php applications as the highest priority. This is estimated at 35d in 16/17, with the balance being returned (RED due to forthcoming reduction in estimate from 85d to 20d).

USG004 - The Edinburgh Global Directory simple approach of trying an upgrade Apache tomcat was partly successful - it identified that it could work on the latest version if an update was also made to the Spring framework, meaning no significant development work would be needed. The project has been re-estimated as 26d in total, with some milestones later, hence is AMBER.

USG005 - The Student Alumni Platform project is on track, with the ITT prepared for issue ahead of the 08 June target date. The project estimate is 50d for this procurement work, with a further 50d expected for an implementation in 17/18.

RAG & Forward Look

Resources to end of May 2017

In the table below the balance for AP67-038 is in error as some work is expected in July, pending information from the ICO or a decision on how to proceed from D&A.

 

Section Two: Projects Not Started

Project Info Programme Manager's Commentary

USG002 D&A - Compliance with PECR, Etherington & Data Protection Regulation

Compliance

Planning: July 2017

Delivery: TBC in 17/18

RAG Status

GREEN

Plan

This project is to comply with three separate strands of regulatory changes:

  • The Privacy and Electronic Communications Regulations (PECR)
  • The Etherington review of how charities are regulated
  • The draft EU Data Protection Regulation

The above is core-funded work. In addition there will be sponsor-funded work to migrate to the web based version of thankQ as estimated in USG001.

This is GREEN following agreement to delay initiation to July because the Information Commissioner's Office (ICO) has yet to clarify whether HE institutions will be deemed public authorities and, if they are, which of their activities will be covered. This would influence the decision about the legal basis for processing and is a blocker to identifying requirements. The D&A team are working with other institutions to jointly petition the ICO for clarity, and it is hoped that this would be reached before July to enable sufficient time to update the systems before the legislation comes into force in May 2018.

This means that the 50d that was expected to be undertaken in 16/17 will now be needed mostly in 17/18. Risk12 has been raised accordingly for potential impact to other projects in 17/18.

USG003 USG Application, Infrastructure & Database End of Life Compliance

Compliance

Planning: June 2017

Delivery: July 17 (analysis)

RAG Status

RED

Plan

This project is to identify applications, databases and infrastructure which will come to the end of their working life in the next 3 years, and to plan upgrades, migrations or replacements accordingly.

The status is RED as it is now clear that the only remaining work that must be delivered in 16/17 is the Edinburgh Global Directory updates, now initiated as USG005, and so the budget can be reduced accordingly (RED due to forthcoming budget reduction from 85d to 20d, with 6d will be transferred to USG005, 5d retained as contingency for USG005, and 15d allocated for php analysis). The analysis of those changes to be implemented for 17/18 will be started in parallel with USG005. There is work that will be needed early in 17/18, and the analysis should enable this to be identified and prioritised.

Following initiation discussions on STU256 it is clear that the decision on the approach for php, including the UG & PG Degree Finders, is the next highest priority. 15d will be retained for this analysis, and combined with the 20d previously released from the STU budget for STU256, to enable initiation of what will be USG003 with an estimate of 35d.

 

Section Three: Projects in Progress

Project Info Project Managers Commentary

USG004 Edinburgh Global Directory End of Life Compliance

Category: Compliance

Milestones

09-Jun-2017     TEST upgrade of apache tomcat complete
16-Jun-2017     User acceptance test post apache tomcat upgrade
03-Jul-2017     LIVE upgrade apache tomcat
17-Jul-2017     Deployment sign-off review
24-Jul-2017     Closure

RAG Status

AMBER

Report by Morna Findlay for May 2017

Achievements

  • Morna Findlay taken on Project Manager role (from Sheila Fraser)
  • Project planning approved
  • Update to spring framework was required to enable upgrade to supported tomcat and apache versions
  • Project build stage completed
  • Project reviewed, re-estimated and new milestones proposed

Issues

  • Delay to build sign off (due to requirement to update spring framework) requires new milestones and new estimate to be approved.
  • EDG is now running on unsupported software (tomcat)

Next steps

  • Approval of new milestones and estimate
  • Upgrade and refresh of TEST
  • Carry out user acceptance testing and sign off TEST

RAG Commentary

Change: New milestones and estimate to be approved (see Resources table for yellow -6d balance to be allocated from AP67-071).

USG005 Student Alumni Platform

Category: Discretionary

Milestones

08-Jun-2017 Publish Invitation to Tender Analyse
10-Jul-2017 Closing date for return of tenders Procure
18-Aug-2017 Completion of evaluations Procure
06-Sep-2017 Award Decision Procure
03-Oct-2017 Contract Negotiations completed - Award made Procure
17-Oct-2017 Closure report completed Close

RAG Status

GREEN

Report by David Watters for May 2017

Achievements

  • Project brief & planning completed
  • Question sets prepared and reviewed by stakeholders
  • ITT prepared by Procurement team

Issues

  • None

Next steps

  • ITT to be published early June
  • Preparations for receipt, and subsequent analysis/scoring, of bids to be made

USG006 Clearing 2017

Category: Discretionary

Milestones

09-June-17          End of Planning
14-July-17 Deploy Widening Participation Indicator Tool to University Web Site
08-August-17 UCAS Clearing - Scotland
17-August-17 UCAS Clearing rUK
25-August-17

Remove Clearing Infrastructure

15-09-17 Closure

RAG Status

GREEN

Report by Emma McNab for May 2017

Achievements

  • Project initiated and Project Manager identified as Emma McNab                                      
  • Initial consultations with business partners

Issues

  • None

Next steps

  • End of Project Planning
  • Telephony Call flow and script development
  • Development of Training Packs
  • Analysis and Development of SIMD Checker

Section Four: Closed or Withdrawn Projects

There are no closed or withdrawn USG Other projects in 16/17.

Documentation

Not available.