November 2014

Report Date
November 2014

Report compiled by Sheila Fraser (IS Apps Programme Manager)

Section One: Programme Commentary, RAG and Resources Update

Commentary

The programme has been renamed to USG Portfolio Projects following the recent change of SASG to University Secretary's Group (USG).

This programme overall is GREEN as the projects are expected to complete within the year.

For DAS008 the ThankQ to IDM connector still has 4 remaining issues to be resolved. As these are not resolved, and the cut-off for the General Council Elections has passed, the deployment to LIVE will not be able to be completed until February. The decision to resolve the Events Booking issue is to remove the functionality, and this is now planned and funding agreed to complete the work. As expected more effort was spent in Novemer resolving issues and the outstanding decision; this is now expected to continue into December, with re-testing in February to confirm the ThankQ to IDM interface is fully functional before deploying to LIVE.

Resources

RAG & Forward Look

 Section Two: Projects Not Started

Project Info

Project Managers Commentary

Dev & Alumni - Fundraising CRM business case and options appraisal 14/15

Discretionary

Planning February 2015

Delivery April 2015

RAG Status

GREEN

Plan

Development & Alumni will lead on the project, the IS Applications involvement is expected to be limited mainly to development resources in relation to estimation for any integration work that may be required. This is currently expected to be around 5d.

Dependencies

Development & Alumni starting the business case. Potential overlap with other CRM projects: HSS004 CRM for HSS Options Appraisal and New University-wide CRM.

 

Section Three: Projects in Progress

Project InfoProject Managers Commentary

DAS008 - Decommission Alumni Live Database

Category: Compliance (Funded)

Milestones

10-Dec-2014Events Booking ASORAccept
10-Dec-2014New ThankQ > IDM Connection: ASORAccept
04-Mar-2015Events Booking Deploy to LIVEDeliver
04-Mar-2015New ThankQ > IDM Connection: Deploy to LIVEDeliver
11-Mar-2015Events Booking DSORDeliver
11-Mar-2015New ThankQ > IDM Connection: DSORDeliver
19-Mar-2015Complete Decomission of ALUMLIVE InstanceDeliver
26-Mar-2015ClosureClose

RAG Status

GREEN

Report for November 2014 by David Watters

Achievements this Period

  • UAT checks continuing with Applications Management and Development & Alumni - some more tests passed but issues remaing

Issues

  • Testing sign-off not yet achieved - milestones to be revised again because of hiatus required for period of General Council elections
  • New issue of data transfer to IDM reported - to be investigated by Dev Tech
  • Resource unavailable to make changes to Events Booking feed (because of higher priority work)

Next Steps

  • Test and implement changes for feed to Events Booking and deploy modifications to LIVE
  • Sign-off testing of IDM connector and deploy changes to LIVE
  • Decommission AlumLive

Section Four: Closed or Withdrawn Projects

Project InfoProject Managers Commentary
No projects closed yet this year. 

 