October 2014

Report Date
October 2014

Report compiled by Sheila Fraser (IS Apps Programme Manager)

Section One: Programme Commentary, RAG and Resources Update

Commentary

This programme overall is GREEN as the projects are expected to complete within the year.

For DAS008 issues still remain with the ThankQ to IDM connector, and so the project is AMBER. The decision to resolve the Events Booking issue is to remove the functionality, and this is now planned and funding agreed to complete the work. As expected more effort was spent in October resolving issues and the outstanding decision; this is now expected to continue into November with closure in December.

Resources

RAG & Forward Look

 Section Two: Projects Not Started

Project Info

Project Managers Commentary

Dev & Alumni - Fundraising CRM business case and options appraisal 14/15

Discretionary

Planning February 2015

Delivery April 2015

RAG Status

GREEN

Plan

Development & Alumni will lead on the project, the IS Applications involvement is expected to be limited mainly to development resources in relation to estimation for any integration work that may be required. This is currently expected to be around 5d.

Dependencies

Development & Alumni starting the business case. Potential overlap with other CRM projects: HSS004 CRM for HSS Options Appraisal and New University-wide CRM.

 

Section Three: Projects in Progress

Project InfoProject Managers Commentary

DAS008 - Decommission Alumni Live Database

Category: Compliance (Funded)

Milestones

06-Nov-2014New ThankQ > IDM Connection: ASORAccept
07-Nov-2014Events Booking ASORAccept
12-Nov-2014Events Booking Deploy to LIVEDeliver
12-Nov-2014New ThankQ > IDM Connection: Deploy to LIVEDeliver
19-Nov-2014New ThankQ > IDM Connection: DSORDeliver
19-Nov-2014Events Booking DSORDeliver
12-Dec-2014Complete Decomission of ALUMLIVE InstanceDeliver
19-Dec-2014ClosureClose

RAG Status

AMBER

Report for October 2014 by David Watters

Achievements this Period

  • UAT checks continuing with Applications Management and Development & Alumni - more tests passed
  • Development & Alumni agreed that Events Booking functionality can be removed
  • Development & Alumni approved funding for additional effort

Issues

  • ThankQ -> IDM Connector not yet signed off as tests not fully complete
  • Risk that project may have to be suspended during election period if deployment to LIVE cannot be completed in November

Next Steps

  • Implement changes for feed to Events Booking and deploy modifications to LIVE.
  • Sign-off testing of IDM connector and deploy changes to LIVE.
  • Decommission AlumLive

Section Four: Closed or Withdrawn Projects

Project InfoProject Managers Commentary
No projects closed yet this year. 

 

Documentation

Not available.