September 2014

Report Date
September 2014

Report compiled by Sheila Fraser (IS Apps Programme Manager)

Section One: Programme Commentary, RAG and Resources Update

Commentary

This programme overall is GREEN as the projects are expected to complete within the year.

For DAS008 issues remain with the ThankQ to IDM connector, and the decision needed to resolve the Events Booking issue (remove or improve the functionality) is not yet agreed. The project is therefore AMBER, and now becoming more urgent as this is needed in LIVE before the General Council Elections in November. Less effort was used in September than expected due to the lack of resolution, this is now expected to be resolved in October.

Resources

RAG & Forward Look

 Section Two: Projects Not Started

Project Info

Project Managers Commentary

Dev & Alumni - Fundraising CRM business case and options appraisal 14/15

Discretionary

Planning February 2015

Delivery April 2015

RAG Status

GREEN

Plan

Development & Alumni will lead on the project, the IS Applications involvement is expected to be limited mainly to development resources in relation to estimation for any integration work that may be required. This is currently expected to be around 5d.

Dependencies

Development & Alumni starting the business case. Potential overlap with other CRM projects: HSS004 CRM for HSS Options Appraisal and New University-wide CRM.

 

Section Three: Projects in Progress

Project InfoProject Managers Commentary

DAS008 - Decommission Alumni Live Database

Category: Compliance (Funded)

Milestones

15-Oct-2014Events Booking ASOR
15-Oct-2014New ThankQ > IDM Connection: ASOR
21-Oct-2014Events Booking Deploy to LIVE
21-Oct-2014New ThankQ > IDM Connection: Deploy to LIVE
28-Oct-2014New ThankQ > IDM Connection: DSOR
28-Oct-2014Events Booking DSOR
31-Oct-2014Complete Decomission of ALUMLIVE Instance

RAG Status

AMBER

Report for September 2014 by David Watters

Achievements this Period

  • UAT checks continuing with Applications Management and Development & Alumni
  • More fixes to IDM connector made by ThankQ
  • Agreement reached on how to address issues with Events Booking channel, however resolution requires decision on removing or improving the Events Booking feed.

Issues

  • ThankQ -> IDM Connector not yet signed off as tests not fully complete
  • Awaiting decision on whether to remove or improve Events Booking feed. Project reported as AMBER because this decision is not yet agreed, and additional effort may be required dependent on approach.

Next Steps

  • Finalise resolution of feed to Events Booking and deploy agreed changes to LIVE.
  • Finalise testing of IDM connector and deploy changes to LIVE.
  • Decommission AlumLive

Section Four: Closed or Withdrawn Projects

Project InfoProject Managers Commentary
No projects closed yet this year. 

 

Documentation