August 2014

Report Date
August 2014

Report compiled by Sheila Fraser (IS Apps Programme Manager)

Section One: Programme Commentary, RAG and Resources Update

Commentary

This programme is GREEN as the funding for the unplanned carry-over is agreed, and the projects are expected to complete within the year.

For DAS008 good progress has been made with the ThankQ to IDM connector, however it is still RED as the date and approach to resolving the performance issues with the Events Booking selection are still to be resolved. A plan to resolve this will be agreed in the coming month.

SAS001 has been transferred into the Research Programme within the CSG Portfolio.

Resources

RAG & Forward Look

 Section Two: Projects Not Started

Project Info

Project Managers Commentary

Dev & Alumni - Fundraising CRM business case and options appraisal 14/15

Discretionary

Planning February 2015

Delivery April 2015

RAG Status

GREEN

Plan

Development & Alumni will lead on the project, the IS Applications involvement is expected to be limited mainly to development resources in relation to estimation for any integration work that may be required. This is currently expected to be around 5d.

Dependencies

Development & Alumni starting the business case. Potential overlap with other CRM projects: HSS004 CRM for HSS Options Appraisal and New University-wide CRM.

 

Section Three: Projects in Progress

Project InfoProject Managers Commentary

DAS008 - Decommission Alumni Live Database

Category: Compliance (Funded)

Milestones

tbcEvents Booking ASORAccept
tbcEvents Booking Deploy to LIVEDeliver
tbcEvents Booking DSORDeliver
29-Aug-2014New ThankQ > IDM Connection: ASORAccept
22-Sep-2014New ThankQ > IDM Connection: Deploy to LIVEDeliver
29-Sep-2014New ThankQ > IDM Connection: DSORDeliver
03-Oct-2014Complete Decomission of ALUMLIVE InstanceDeliver
10-Oct-2014ClosureClose

RAG Status

RED

Report for August 2014 by David Watters

Achievements this Period

  • IDM Connector documented and deployed into TEST
  • UAT started with Development & Alumni
  • Iterative fixes to connector made by ThankQ
  • UAT checks continuing with Applications Management

Issues

  • ThankQ -> IDM Connector not yet signed off as tests not fully complete
  • New feed for Events Booking not yet signed off - questions around performance times to be addressed - hence RED status
  • Project reported as Amber given outstanding milestones on Events Booking

Next Steps

  • Finalise testing of feed to Events Booking and deploy changes to LIVE.
  • Finalise testing of IDM connector and deploy changes to LIVE.

Section Four: Closed or Withdrawn Projects

Project InfoProject Managers Commentary
No projects closed yet this year. 

 

Documentation

Not available.