July 2014

Report Date
July 2014

Report compiled by Sheila Fraser (IS Apps Programme Manager)

Section One: Programme Commentary, RAG and Resources Update

This programme remains as overall RED for the current year as the funding for the unplanned carry-over is not yet agreed.

DAS008 is RED as the budget for completion of the work, now in 14/15, is not yet clear. Assuming the funding can be provided it is still expected that the project will be able to deliver the decommissioning before the drop dead date for the infrastructure as the 2 week concentrated period is confirmed as scheduled to start 7th August. There is also agreement on the new affiliation types, with the decision being taken to remove these from the ThankQ to IDM interface at this point.

In relation to the budget and balances in the table below, the SAS001 PURE Database Migration programme budget will be reduced this year to reflect the work now expected following the re-plan. This project will be transferred to the Research Programme within CSG for next year (corresponding to the wider University organisational changes), and so the unplanned carry-over will transfer with it.

 Section Two: Projects Not Started

Project Info

Project Managers Commentary

Dev & Alumni - Fundraising CRM business case and options appraisal 14/15

Discretionary

Planning February 2015

Delivery April 2015

RAG Status

GREEN

Plan

Development & Alumni will lead on the project, the IS Applications involvement is expected to be limited mainly to development resources in relation to estimation for any integration work that may be required. This is currently expected to be around 5d.

Dependencies

Development & Alumni starting the business case. Potential overlap with other CRM projects: HSS004 CRM for HSS Options Appraisal and New University-wide CRM.

 

Section Three: Projects in Progress

Project InfoProject Managers Commentary

SAS001 - PURE Database Migration

Category: Compliance

Milestones

29-Jul-2014Build Stage Sign-off PPBR
18-Aug-2014Integration Sign-off PPIR
26-Aug-2014Acceptance Sign-off ASOR
28-Aug-2014Deployment of Database Migration

RAG Status

GREEN

Report for July 2014 by Sheila Fraser (for Sally Hayward)

Achievements in Last Period

  • Work has been completed on the DEV environment, including checks and build sign-off
  • Work has started on building the TEST environment

Issues

  • None

Next Steps

  • Confirm that the TAD includes the new version of the PURE software
  • Complete the build of the TEST environment, complete testing and acceptance sign-off and deploy to LIVE

DAS008

Decommission Alumni Live Database

Category: Core

Milestones

17-Jul-2014Events Booking ASORAccept
24-Jul-2014Events Booking Deploy to LIVEDeliver
29-Jul-2014New ThankQ > IDM Connection: PPBRBuild
29-Jul-2014New ThankQ > IDM Connection: Develop short SDS & Implementation Plan for ThankQ > IDM & Update TADAnalyse
29-Jul-2014Events Booking DSORDeliver
07-Aug-2014New ThankQ > IDM Connection: Deploy to TESTExecute
29-Aug-2014New ThankQ > IDM Connection: ASORAccept
22-Sep-2014New ThankQ > IDM Connection: Deploy to LIVEDeliver
29-Sep-2014New ThankQ > IDM Connection: DSORDeliver

RAG Status

RED

Report for July 2014 by Craig Middlemass for David Watters

Achievements this Reporting Period

  • Design and users roles reworked for ThankQ to IDM connector
  • Review of design and implementation plan completed ready for deployment to Test
  • Test EASE accounts provided for ThankQ to use in UAT
  • Details of existing alumni provided to ThankQ to exclude from the inital load reducing impact on IDM processing

 

Issues

  • New feed for Events Booking not yet signed off - questions around performance times to be addressed.
  • Differences between environments identified (i.e. DEV for one application pointing to TEST for another)
  • Project reported as RED given a) outstanding issues on Events Booking b) delays to getting IDM connector for ThankQ finalised and c) unplanned carry-over into 14/15 to complete the work

 

Next Steps

  • Finalise testing of feed to Events Booking and deploy changes to LIVE.
  • Iron out incongruities between environments for the various applications in DEV & TEST.
  • Testing of IDM connector.

 

 

 

Section Four: Closed or Withdrawn Projects

RES049

Pure Enhancements

Compliance

Report by Sue Woodger

This project was closed on 20-Jan-14

Please see the Completion Report for further information

 