Report for January 2014
- Report Date
- January 2014
Report compiled by Jamie Thin (IS Apps Programme Manager)
Section One: Programme Commentary, RAG and Resources Update
SASG contingency balance row reduced by 22 days to fund the compliance DB migrations for PUBS and CARS (in STU programme).
11 days unallocated contingency remaining in SASG Other balance row for last 6 months of 13-14
--

Section Two: Projects Not Started
Project Info | Project Managers Commentary | ||
| None
|
|
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | ||||||||||||||||||
| Report for January 2014 by Sally Hayward
Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||||
RES049
Category: Core Milestones
RAG Status GREEN | Report for December 2013 by Sue Woodger
Achievements in Last Period
Issues
Next Steps for January 14
Project is GREEN as plan available and on schedule
| ||||||||||||||||||
DAS008 Decommission Alumni Live Database
Category: Core Milestones Target date Title
RAG Status AMBER | Report for January 2014
Testing completed on Events booking on TEST
CCTS still to complete testing of additional changes from Applications Management..
Complete testing of CCTS and deploy CCTS and Events Booking to LIVE. Suspend rest of project until Development and Alumni are ready to test. |
Section Four: Closed or Withdrawn Projects
RES049 Pure Enhancements Compliance | Report by Sue Woodger This project was closed on 20-Jan-14 Please see the Completion Report for further information |
None