Report for December 2013

Report Date
December 2013

Report compiled by Jamie Thin (IS Apps Programme Manager)

Section One: Programme Commentary, RAG and Resources Update

 

New project has started to migrate the PURE DB to the new DB tier infrastructure.

 

--

 

 Section Two: Projects Not Started

 

None

 

Section Three: Projects in Progress

 

 

Project InfoProject Managers Commentary

RES049

 

Category: Core

Milestones

13-Jan-2014DSOR
20-Jan-2014Closure

RAG Status

GREEN

Report for December 2013 by Sue Woodger

 

Achievements in Last Period

  • All fixes now live - signed off 6 December

Issues

  • Due to unavailabilty of team members due to Christmas holidays DSOR and Closure delayed to January 14

 

 Next Steps for January 14

  •  DSOR 13 January 2014

  • Closure 20 January 2014 

 

Project is GREEN as plan available and on schedule

 

DAS008

Decommission Alumni Live Database

 

Category: Core

Milestones

 

   Target date         Title
13-Nov-2013Deploy New Version of CCTS and Events booking to TEST
20-Nov-2013ASOR- CCTS and Event Booking
22-Nov-2013Deploy New Version of CCTS and Events Booking to LIVE
29-Nov-2013DSOR - CCTS and Events booking
31-Mar-2014Deploy New ThankQ Feed to TEST
31-Mar-2014Complete Decomission of ALUMLIVE Instance
31-Mar-2014Deploy New ThankQ Feed to LIVE
31-Mar-2014DSOR - ThankQ Feed
31-Mar-2014ASOR - ThankQ Feed
31-Mar-2014Closure

 

RAG Status

AMBER

Report for December 2013
  • Achievements in Last Period

Events Booking now in the TEST envrionment .

  • Issues

Careers tester unable to complete testing before extended Christmas break.

  • Next Steps

Replan Events bookings testing and deployment to LIVE.

Test and deploy CCTS and Events Booking to LIVE.

Suspend rest of project until Development and Alumni are ready to test.

 

Section Four: Closed or Withdrawn Projects

 

None

Documentation

Not available.