Report for September 2013

Report Date
September 2013

Report compiled by Jamie Thin (IS Apps Programme Manager)

Section One: Programme Commentary, RAG and Resources Update

 

Work on DAS008 has been carried over to 13-14. Development and Alumni have requested that the project is suspended until Feb 2014.

--

 

 Section Two: Projects Not Started

 

None

 

Section Three: Projects in Progress

 

 

Project InfoProject Managers Commentary

RES049

 

Category: Core

Milestones

22-Nov-2013REF Freeze ends
06-Dec-2013Delivery: Completion of Bug fixes in lIve
20-Dec-2013DSOR
10-Jan-2014Closure

RAG Status

GREEN

Report for September 2013 by Sue Woodger

Achievements in Last Period

  • Planning milestone and project brief approved 6/9/13
  • Bug fixes sorted in Beta and test - will go into live after REF freeze :
    •  RES049-29 missing persons no PI Split

  • Bug fixes resolved

    • RES049-30, RES049-31, RES049-34: all about documentation - now on wiki

Issues

  • Ref freeze started 15 September so no fixes can go into live until the freeze ends

Next Steps for September

  • Continuation with fixing bugs in remaining jiras: RES049-15; RES049-38

 

Project is GREEN as plan available and on schedule

 

DAS008

Decommission Alumni Live Database

 

Category: Core

Milestones

 

   Target date         Title
08-Nov-2013Deploy New Version of CCTS and Events Booking to LIVE
15-Nov-2013DSOR - CCTS and Events booking
31-Mar-2014Deploy New ThankQ Feed to TEST
31-Mar-2014Complete Decomission of ALUMLIVE Instance
31-Mar-2014Deploy New ThankQ Feed to LIVE
31-Mar-2014DSOR - ThankQ Feed
31-Mar-2014ASOR - ThankQ Feed
31-Mar-2014Closure

 

RAG Status

AMBER

Report for September 2013
  • Achievements in Last Period

Discussed and agreed approach and estimates to complete CCTS and Events Booking Changes with Development Services.

Agreed dates with Business users  for next stage of testing.

  • Issues

Resourcing is required to close off the events booking and CCTS pats of the project

  • Next Steps

Confirm resources to deploy Events booking to TEST

Test and deploy CCTS and Events Booking to LIVE

Replan milestones accordingly and restimate current and new tasks.

The plan to complete the Events Bookings and CCTS part of the project are to be resourced.

 

Section Four: Closed or Withdrawn Projects

 

None