Report for February 2014
- Report Date
- February 2014
Nikki Stuart (IS Apps Portfolio Manager) for Bruce Nelson (Portfolio Owner)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Commentary
SCE001 PATH - Project closure to be reviewed at 4th March Steering Group meeting. Steering Group will be ask to confirm any further actions which would be carried forward via a new project.
SCE002 Tomography Control - new project
CSE Portfolio Owner is collating requests for utalisation of the ring fenced days.
Projects of interest in other programmes or portfolios;
ITS092 BOXI Upgrade (https://www.projects.ed.ac.uk/project/its092) - LIVE migrations underway and communications with users ongoing.
Enterprise Reagent Manager Upgrade (https://www.projects.ed.ac.uk/project/pps005) - ERM was upgraded in January 2014.
Timetabling Programme (https://www.projects.ed.ac.uk/programme/ttu) - 'MyTimetable' - Personalised Timetables for Taught Students (via MyEd) went live in August 2013
eRecruitment Phase 2 (Talent Pool), LIVE deployment planned for March 2015. This project will allow the University to benefit from enhanced functionalityby including a major upgrade to the software in the project.


Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
CSE Ring fenced days | 150 days ring fenced days allocated from core funding for 13/14. CSE to confirm how these days are to be allocated. |
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | ||||||||
Category: Discretionary, IS Funded
Milestones
RAG Status GREEN
| Report by Franck Bergeret for February 2014 Achievements in last period
Issues
Next Steps
| ||||||||
SCE002 Tomography Control Category: Discretionary, Funded
Milestones
RAG Status GREEN | Report by Dave Berry for February 2014Achievements in Last PeriodThe Brief was completed and signed off. Build work has begun as planned. IssuesThe new hardware has taken longer than expected to arrive. This means that the new software has not been tested with the new camera or the new PC. So there is a risk that problems may be discovered when the hardware does arrive, which may entail more effort than planned. This is being managed under the existing risk for unexpected technical issues. The project sponsor is aware of the risk and happy to proceed. Next StepsIn March we will complete the build and test in with the new hardware. |
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
Project Code x Project Title x
Category
| Report by xx
|