Report for May 2019
- Report Date
- May 2019
Section One: Programme Commentary, RAG and Resources Update
Commentary:
The overall status of the SCE programme is AMBER, with both the College Project Marking Tool and the GeoSciences project reporting an AMBER status this month. There are 61 days available to use in 18/19, so options are being considered to make best use of this funding within the constraint of available IS resourcing to the end of 18/19.
During May:
- Development work continued for the SCE014 project, however the fourth sprint did not complete all items and a fifth sprint is being arranged. A decision is still required on whether to increase the project scope to move the tool into an IS hosted environment, pending sight of the related requirements, estimate and timescale. Either way, the project will re-plan its delivery and closure milestones.
- The planning stage for SCE015 was further extended in order to complete the analysis and secure estimates from IS Development Technology, following a resource conflict within that team and a subsequent resource conflict within Project Services.
- Work was undertaken to understand the feasibility of securing resources for the next phase project for PGT deposits. However, the dependency on core systems is preventing resources from being secured and a discussion should take place to discuss feasibility and next steps.
Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.
Forward Look - May 2019:

Resources to end May 2019:

Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
|---|---|
|
The project scope for PGT Deposits Phase 2 had been agreed in principle, but challenges are being posed with regards to securing the appropriate resources - meaning the project cannot yet be initiated until an agreement takes place. Discussions are being held with Service Excellence Programme to see if they could bring forward their timeline for delivering deposits functionality under their Finance strand, and to confirm their depedency on the finance elements of the core systems implementation. A request has been put forward for Business Analysis resource to deliver a small piece of process mapping for the College to look at a system for Student Scholarship requests and approvals. The proposal for a project to support GDPR was put forward in 2017/18 but hasn't been resourced or started in 2018/19; it's now likely to be undertaken in 19/20. |
CSE has a budget of 150 ring fenced days for 18/19; with 89 days assigned to the following projects:
61 days are yet to be allocated. |
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | ||||||||||||||||||||||||||||||||||||||||
|
SCE014 Creation of a developer community for a College Project Marking Tool Category: Discretionary Milestones
RAG Status: AMBER
|
Report by Ken Miller for May 2019Achievements
Issues
Next Steps
|
||||||||||||||||||||||||||||||||||||||||
|
SCE015 GeoSciences Databases Upgrade and Migration Category: Discretionary
Milestones: TBC
RAG Status: AMBER |
Report by Victoria Weinsberg for May 2019
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Manager's Commentary |
|---|---|
|
SCE012 Support for PGT Deposits - Requirements |
This project was approved by WIS for closure on 15th February 2019. See here for the closure report https://secure.projects.ed.ac.uk/project/sce012/closure-report |
| SCE013 ShareLatex and Overleaf software trial | This project was approved by WIS for closure on 8th March 2019. See here for the closure report https://secure.projects.ed.ac.uk/project/sce013/closure-report |
Section Five: Programme Meeting Minutes
| Date | Comments |
|---|---|
| 27 June 2019 | Programme Review for May 2019 - meeting notes |
| 9 May 2019 | Programme Review for April 2019 - meeting notes |
| 11 April 2019 | Programme Review for March 2019 - meeting notes |
| 5 March 2019 | Programme Review for February 2019 - meeting notes |
| 29 November 2018 | Programme Review for October 2018 - meeting notes |
| 30 October 2018 | Programme Review for September 2018 - meeting notes |
| 27 September 2018 | Programme Review for August 2018 - meeting notes |
| 22 August 2018 | Programme Review for July 2018 - meeting notes |
| 16 July 2018 | Programme Review for June 2018 - meeting notes |
| 18 June 2018 | Programme Review for May 2018 - meeting notes |
| 17 May 2018 | Programme Review for April 2018 - meeting notes |
| 16 April 2018 | Programme Review for March 2018 - meeting notes |
| 21 March 2018 | Programme Review for February 2018 - meeting notes |
| 12 February 2018 | Programme Review for December 2017 & January 2018 - meeting notes |
| 15 January 2018 | Programme Review for November 2017 - meeting notes |
