December 2013

Report Date
December 2013

Nikki Stuart (IS Apps Portfolio Manager) for Bruce Nelson (Portfolio Owner)

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update

 

Commentary

CSE001 PATH - Programme Builder now LIVE. Closure milestone likely to be delayed to allow feedback from the steering group in February.

CSE Portfolio Owner is collating requests for utalisation of the ring fenced days. 

 

Projects of interest in other programmes or portfolios;

ITS092 BOXI Upgrade (https://www.projects.ed.ac.uk/project/its092) - LIVE migrations underway and communications with users ongoing. 

Enterprise Reagent Manager Upgrade (https://www.projects.ed.ac.uk/project/pps005) - ERM will be upgraded in January 2014. School of Chemistry involved in discussions regarding planning and testing. Project will focus on upgrading the software rather than delivering any enhancements. 

Timetabling Programme (https://www.projects.ed.ac.uk/programme/ttu) - 'MyTimetable' - Personalised Timetables for Taught Students (via MyEd) went live in August 2013

eRecruitment Phase 2 (Talent Pool) now likely to delivery January 2015 to allow the University to benefit from enhanced functionalityby including a major upgrade to the software in the project. eRecruitment Project Board will review and agree timescales early February 2014.

 

 

 

 

 

 Section Two: Projects Not Started

 

Project InfoProgramme Manager's Commentary

CSE Ring fenced days

150 days ring fenced days allocated from core funding for 13/14. CSE to confirm how these days are to be allocated. 
  

 

 

Section Three: Projects in Progress

 

Project InfoProject Managers Commentary

 SCE001 Path

 

 

Category: Discretionary, IS Funded

 

Milestones

 

17-Jan-2014Closure  
 

RAG Status

GREEN

 

Report by  Franck Bergeret for December 2013

Achievements in last period

  • Programme Builder deployed to Live
  • Path: deployment to MyEd channel Test signed off

Issues

 

n/a

Next Steps

  • Deploy Path onto MyEd channelLive
  • Evaluation report: deliverable not required- Agreed at at the Steering Group on 2/12
  • Delay closure to allow next Steering Group meeting in February to get further feedback form the 3 schools (from student,  and staff at the liaison commitee early Feb)

 

 

 

Section Four: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary

  

Project Code 

x

Project Title

 x

 

Category

 

Report by xx

 

 

 

Programme Info

Documentation

Not available.